Effectiveness of dashboard as a work progress scheduling, monitoring, and decision-making in construction projects

International Journal of Advances in Applied Sciences · Vol. 14 No. 3 (2025) · hlm. 878–885

DOI
10.11591/ijaas.v14.i3.pp878-885
ISSN
2722-2594, 2252-8814
Terbit
2025-09-01
Penerbit
Institute of Advanced Engineering and Science
Bahasa
eng
Lisensi
creativecommons.org/licenses/by-sa/4.0

Abstrak

Scheduling, monitoring, and decision-making are important factors in determining the general achievement of sustainable construction. Therefore, this study was conducted to determine the effectiveness of a dashboard as a measuring tool for construction project scheduling, monitoring, and decision-making. A survey with a Likert scale (5 scale) on each viewpoint, including planning, oversight, and independent direction, of 15 respondents from project executors and 7 respondents from supervisors was used as instrumentation. The results showed that the dashboard was evaluated with a value of 92.25 among executors and supervisors linked to product characteristics. Executors also used the scheduling dashboard with a value of 91.73, and the feature of employing the concept for supervision was appropriate as a measuring instrument, scoring 92.15. Furthermore, the final step was the aspect of using the dashboard for decision-making, which was tested and used with a value of 88.14. The use dashboard model is an effective tool for work progress scheduling, monitoring, and decision-making in construction projects.

Jaringan kolaborasi para penulis

4 penulis · 6 tautan kepenulisan bersama

Arahkan kursor atau ketuk sebuah nama untuk menyorot rekan penulisnya. Klik dua kali untuk membuka halaman penulis.

  • State University of Medan
  • Organisasi berbeda
  • Organisasi sama
  • Afiliasi tidak diketahui
  • Garis lebih tebal = lebih banyak artikel bersama · lingkaran lebih besar = lebih banyak artikel
Tampilkan sebagai tabel
Rekan penulisOrganisasiArtikel bersama
Wisnu PrayogoState University of Medan2
Syahreza AlvanState University of Medan2

Afiliasi berasal dari OpenAlex; metadata OAI-PMH jurnal tidak memuatnya. Penulis tanpa ID OpenAlex dicocokkan berdasarkan nama, sehingga dua orang bisa tergabung atau satu orang bisa terpisah.

Sumber metadata: OAI-PMH (metadata jurnal) http://ijaas.iaescore.com/index.php/IJAAS/oai, pertama di-harvest 8 Nov 2026, terakhir terlihat 16 Nov 2026.
Metadata asli (oai_dc)
<oai_dc:dc xmlns="http://www.openarchives.org/OAI/2.0/" xmlns:dc="http://purl.org/dc/elements/1.1/" xmlns:oai_dc="http://www.openarchives.org/OAI/2.0/oai_dc/" xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:schemaLocation="http://www.openarchives.org/OAI/2.0/oai_dc/  http://www.openarchives.org/OAI/2.0/oai_dc.xsd">
	<dc:title xml:lang="en-US">Effectiveness of dashboard as a work progress scheduling, monitoring, and decision-making in construction projects</dc:title>
	<dc:creator>Luthan, Putri Lynna Adelina</dc:creator>
	<dc:creator>Sitanggang, Nathanael</dc:creator>
	<dc:description xml:lang="en-US">Scheduling, monitoring, and decision-making are important factors in determining the general achievement of sustainable construction. Therefore, this study was conducted to determine the effectiveness of a dashboard as a measuring tool for construction project scheduling, monitoring, and decision-making. A survey with a Likert scale (5 scale) on each viewpoint, including planning, oversight, and independent direction, of 15 respondents from project executors and 7 respondents from supervisors was used as instrumentation. The results showed that the dashboard was evaluated with a value of 92.25 among executors and supervisors linked to product characteristics. Executors also used the scheduling dashboard with a value of 91.73, and the feature of employing the concept for supervision was appropriate as a measuring instrument, scoring 92.15. Furthermore, the final step was the aspect of using the dashboard for decision-making, which was tested and used with a value of 88.14. The use dashboard model is an effective tool for work progress scheduling, monitoring, and decision-making in construction projects.</dc:description>
	<dc:publisher xml:lang="en-US">Institute of Advanced Engineering and Science</dc:publisher>
	<dc:contributor xml:lang="en-US">Medan State University</dc:contributor>
	<dc:date>2025-09-01</dc:date>
	<dc:type>info:eu-repo/semantics/article</dc:type>
	<dc:type>info:eu-repo/semantics/publishedVersion</dc:type>
	<dc:type xml:lang="en-US"></dc:type>
	<dc:format>application/pdf</dc:format>
	<dc:identifier>https://ijaas.iaescore.com/index.php/IJAAS/article/view/21439</dc:identifier>
	<dc:identifier>10.11591/ijaas.v14.i3.pp878-885</dc:identifier>
	<dc:source xml:lang="en-US">International Journal of Advances in Applied Sciences; Vol 14, No 3: September 2025; 878-885</dc:source>
	<dc:source>2722-2594</dc:source>
	<dc:source>2252-8814</dc:source>
	<dc:source>10.11591/ijaas.v14.i3</dc:source>
	<dc:language>eng</dc:language>
	<dc:relation>https://ijaas.iaescore.com/index.php/IJAAS/article/view/21439/13314</dc:relation>
	<dc:rights xml:lang="en-US">Copyright (c) 2025 Putri Lynna Adelinna Luthan, Nathanael Sitanggang</dc:rights>
	<dc:rights xml:lang="en-US">http://creativecommons.org/licenses/by-sa/4.0</dc:rights>
</oai_dc:dc>