Study of Contract Change Order (CCO) on Implementation Time in Building Construction Project

Journal of Applied Engineering and Technological Science (JAETS) · Vol. 4 No. 2 (2023) · hlm. 722–733

DOI
10.37385/jaets.v4i2.1664
ISSN
2715-6079, 2715-6087
Terbit
2023-06-05
Penerbit
Yayasan Riset dan Pengembangan Intelektual (YRPI)
Bahasa
en

Abstrak

The aim of this research is to identify the main causes and effects of CCO in the construction of the Palu State Islamic University (IAIN) campus II building project for the Faculty of Tarbiyah and Teacher Training and the Faculty of Sharia and Islamic Economics Lecture Building. Tasks included conducting a field survey via a questionnaire and interviews with main parties; project owner, contractors and consultants who are directly related to the project. It was determined that the top three causes of CCO from project owner, contractor and consultant. The contractor has do CCO at the beginning of the project of 70% respondent, while consultant has changed contract order at mid-project implementation of 50% respondents and 70% at the end project implementation from the contractor. The results that are quite important from this study are the discovery of volume estimation errors and changes in work methods. Errors in estimating volumes are caused by the planning consultant's inaccuracy in planning so that there is a significant difference in volume from the initial contract with conditions in the field so that some work items experience an increase or decrease in volume

Kata kunci

Jaringan kolaborasi para penulis

3 penulis · 3 tautan kepenulisan bersama

Arahkan kursor atau ketuk sebuah nama untuk menyorot rekan penulisnya. Klik dua kali untuk membuka halaman penulis.

  • Tadulako University
  • Organisasi berbeda
  • Organisasi sama
  • Afiliasi tidak diketahui
  • Garis lebih tebal = lebih banyak artikel bersama · lingkaran lebih besar = lebih banyak artikel
Tampilkan sebagai tabel
Rekan penulisOrganisasiArtikel bersama

Afiliasi berasal dari OpenAlex; metadata OAI-PMH jurnal tidak memuatnya. Penulis tanpa ID OpenAlex dicocokkan berdasarkan nama, sehingga dua orang bisa tergabung atau satu orang bisa terpisah.

Sumber metadata: OAI-PMH (metadata jurnal) https://journal.yrpipku.com/index.php/jaets/oai, pertama di-harvest 9 Nov 2026, terakhir terlihat 22 Nov 2026.
Metadata asli (oai_dc)
<oai_dc:dc xmlns="http://www.openarchives.org/OAI/2.0/" xmlns:dc="http://purl.org/dc/elements/1.1/" xmlns:oai_dc="http://www.openarchives.org/OAI/2.0/oai_dc/" xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:schemaLocation="http://www.openarchives.org/OAI/2.0/oai_dc/  http://www.openarchives.org/OAI/2.0/oai_dc.xsd">
	<dc:title xml:lang="en"> Study of Contract Change Order (CCO) on Implementation Time in Building Construction Project</dc:title>
	<dc:creator xml:lang="en">Kamaludin, Tutang Muhtar</dc:creator>
	<dc:creator xml:lang="en">Rusdin, Andi</dc:creator>
	<dc:creator xml:lang="en">Nirmalawati, Nirmalawati</dc:creator>
	<dc:subject xml:lang="en">: contract change order</dc:subject>
	<dc:subject xml:lang="en">contactor</dc:subject>
	<dc:subject xml:lang="en">project</dc:subject>
	<dc:subject xml:lang="en">cost</dc:subject>
	<dc:subject xml:lang="en">time</dc:subject>
	<dc:description xml:lang="en">The aim of this research is to identify the main causes and effects of CCO in the construction of the Palu State Islamic University (IAIN) campus II building project for the Faculty of Tarbiyah and Teacher Training and the Faculty of Sharia and Islamic Economics Lecture Building. Tasks included conducting a field survey via a questionnaire and interviews with main parties; project owner, contractors and consultants who are directly related to the project. It was determined that the top three causes of CCO from project owner, contractor and consultant. The contractor has do CCO at the beginning of the project of 70% respondent, while consultant has changed contract order at mid-project implementation of 50% respondents and 70% at the end project implementation from the contractor. The results that are quite important from this study are the discovery of volume estimation errors and changes in work methods. Errors in estimating volumes are caused by the planning consultant's inaccuracy in planning so that there is a significant difference in volume from the initial contract with conditions in the field so that some work items experience an increase or decrease in volume</dc:description>
	<dc:publisher xml:lang="en">Yayasan Riset dan Pengembangan Intelektual (YRPI)</dc:publisher>
	<dc:date>2023-06-05</dc:date>
	<dc:type>info:eu-repo/semantics/article</dc:type>
	<dc:type>info:eu-repo/semantics/publishedVersion</dc:type>
	<dc:format>application/pdf</dc:format>
	<dc:identifier>https://journal.yrpipku.com/index.php/jaets/article/view/1664</dc:identifier>
	<dc:identifier>10.37385/jaets.v4i2.1664</dc:identifier>
	<dc:source xml:lang="en">Journal of Applied Engineering and Technological Science (JAETS); Vol. 4 No. 2 (2023): Journal of Applied Engineering and Technological Science (JAETS); 722-733</dc:source>
	<dc:source>2715-6079</dc:source>
	<dc:source>2715-6087</dc:source>
	<dc:source>10.37385/jaets.v4i2</dc:source>
	<dc:language>en</dc:language>
	<dc:relation>https://journal.yrpipku.com/index.php/jaets/article/view/1664/1298</dc:relation>
	<dc:rights xml:lang="en">Copyright (c) 2023 Journal of Applied Engineering and Technological Science (JAETS)</dc:rights>
</oai_dc:dc>