Analysing The Causes of Management and Production Delays in The Implementation of Construction Project Work

Journal of Applied Engineering and Technological Science (JAETS) · Vol. 5 No. 2 (2024) · hlm. 1221–1231

DOI
10.37385/jaets.v5i2.1994
ISSN
2715-6079, 2715-6087
Terbit
2024-06-06
Penerbit
Yayasan Riset dan Pengembangan Intelektual (YRPI)
Bahasa
en

Abstrak

This study aims to analyse the causes of delays in the implementation of construction projects caused by management (owners/consultants) and production (contractors). The research sample consists of 56 respondents who are directly involved in the implementation of construction projects (owners, consultants, contractors, field supervisors, and estimators). The quantitative data analysis technique used was descriptive analysis technique, while the qualitative data obtained by interviewing 5 construction project experts was analysed by qualitative descriptive method. To analyse the causes of delays in project implementation, an analysis technique using the Relative Importance Index (RII) formula was used with a reference value of RII> 0.710. The results showed that 1) the average RII on management factors was 0.895> 0.710. This means that management factors (owner/consultant) can cause delays in the implementation of construction projects; 2) the average RII on production factors is 0.917> 0.710. This means that production factors (contractors) can cause delays in the implementation of construction projects. This means that production factors (contractors) can cause delays in the implementation of construction projects. This research is directly useful for construction service providers and contributes to the development of Project / Construction Management science.

Kata kunci

Jaringan kolaborasi para penulis

26 penulis · 81 tautan kepenulisan bersama · 44 lintas organisasi

Arahkan kursor atau ketuk sebuah nama untuk menyorot rekan penulisnya. Klik dua kali untuk membuka halaman penulis.

  • State University of Medan
  • Universitas Pertamina
  • Sebelas Maret University
  • Politeknik ATK Yogyakarta
  • Kementerian Kesehatan Republik Indonesia
  • University of Brawijaya
  • Universitas Pembangunan Nasional Veteran Yogyakarta
  • Organisasi lain
  • Afiliasi tidak diketahui
  • Organisasi berbeda
  • Organisasi sama
  • Afiliasi tidak diketahui
  • Garis lebih tebal = lebih banyak artikel bersama · lingkaran lebih besar = lebih banyak artikel
Tampilkan sebagai tabel
Rekan penulisOrganisasiArtikel bersama
I Wayan Koko SuryawanUniversitas Pertamina2
Angga Dheta Shirajjudin AjiUniversity of Brawijaya2
Sapta SuhardonoSebelas Maret University2
Evi Siti SofiyahUniversitas Pertamina2
Almira Davina NastitiUniversitas Pertamina2
Wahyu RatnaningsihAfiliasi tidak diketahui1
Wahyu RatnaningsihPoliteknik ATK Yogyakarta1
Andri Dwi SaputraPoliteknik ATK Yogyakarta1
Husna Muizzati ShabrinaUniversitas Pembangunan Nasional Veteran Yogyakarta1
Betanti RidhosariUniversitas Pertamina1
Laili FitriaTanjungpura University1
Esi EmiliaState University of Medan1
Risti RosmiatiState University of Medan1
Erli MutiaraState University of Medan1
Nila Reswari HaryanaState University of Medan1
Rachmat MulyanaState University of Medan1
Teguh Budi PrijantoKementerian Kesehatan Republik Indonesia1
Nia Yuniarti HasanKementerian Kesehatan Republik Indonesia1
Kahar KaharPoltekkes Kemenkes Bandung1
Muammar QadafiBandung Institute of Technology1
Iva Yenis SeptiarivaSebelas Maret University1
Betanti RidhosariUniversitas Pertamina1

Afiliasi berasal dari OpenAlex; metadata OAI-PMH jurnal tidak memuatnya. Penulis tanpa ID OpenAlex dicocokkan berdasarkan nama, sehingga dua orang bisa tergabung atau satu orang bisa terpisah.

Sumber metadata: OAI-PMH (metadata jurnal) https://journal.yrpipku.com/index.php/jaets/oai, pertama di-harvest 9 Nov 2026, terakhir terlihat 16 Nov 2026.
Metadata asli (oai_dc)
<oai_dc:dc xmlns="http://www.openarchives.org/OAI/2.0/" xmlns:dc="http://purl.org/dc/elements/1.1/" xmlns:oai_dc="http://www.openarchives.org/OAI/2.0/oai_dc/" xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:schemaLocation="http://www.openarchives.org/OAI/2.0/oai_dc/  http://www.openarchives.org/OAI/2.0/oai_dc.xsd">
	<dc:title xml:lang="en">Analysing The Causes of Management and Production Delays in The Implementation of Construction Project Work</dc:title>
	<dc:creator xml:lang="en">Luthan, Putri Lynna</dc:creator>
	<dc:creator xml:lang="en">Sitanggang, Nathanael</dc:creator>
	<dc:creator xml:lang="en"> Alvan, Syahreza</dc:creator>
	<dc:creator xml:lang="en">Prayogo, Wisnu</dc:creator>
	<dc:subject xml:lang="en">Project Delay</dc:subject>
	<dc:subject xml:lang="en">Construction</dc:subject>
	<dc:subject xml:lang="en">Management</dc:subject>
	<dc:subject xml:lang="en">Production</dc:subject>
	<dc:description xml:lang="en">This study aims to analyse the causes of delays in the implementation of construction projects caused by management (owners/consultants) and production (contractors). The research sample consists of 56 respondents who are directly involved in the implementation of construction projects (owners, consultants, contractors, field supervisors, and estimators). The quantitative data analysis technique used was descriptive analysis technique, while the qualitative data obtained by interviewing 5 construction project experts was analysed by qualitative descriptive method. To analyse the causes of delays in project implementation, an analysis technique using the Relative Importance Index (RII) formula was used with a reference value of RII&amp;gt; 0.710. The results showed that 1) the average RII on management factors was 0.895&amp;gt; 0.710. This means that management factors (owner/consultant) can cause delays in the implementation of construction projects; 2) the average RII on production factors is 0.917&amp;gt; 0.710. This means that production factors (contractors) can cause delays in the implementation of construction projects. This means that production factors (contractors) can cause delays in the implementation of construction projects. This research is directly useful for construction service providers and contributes to the development of Project / Construction Management science.</dc:description>
	<dc:publisher xml:lang="en">Yayasan Riset dan Pengembangan Intelektual (YRPI)</dc:publisher>
	<dc:date>2024-06-06</dc:date>
	<dc:type>info:eu-repo/semantics/article</dc:type>
	<dc:type>info:eu-repo/semantics/publishedVersion</dc:type>
	<dc:format>application/pdf</dc:format>
	<dc:identifier>https://journal.yrpipku.com/index.php/jaets/article/view/1994</dc:identifier>
	<dc:identifier>10.37385/jaets.v5i2.1994</dc:identifier>
	<dc:source xml:lang="en">Journal of Applied Engineering and Technological Science (JAETS); Vol. 5 No. 2 (2024): Journal of Applied Engineering and Technological Science (JAETS); 1221-1231</dc:source>
	<dc:source>2715-6079</dc:source>
	<dc:source>2715-6087</dc:source>
	<dc:source>10.37385/jaets.v5i2</dc:source>
	<dc:language>en</dc:language>
	<dc:relation>https://journal.yrpipku.com/index.php/jaets/article/view/1994/2945</dc:relation>
	<dc:rights xml:lang="en">Copyright (c) 2024 Journal of Applied Engineering and Technological Science (JAETS)</dc:rights>
</oai_dc:dc>