Productivity Analysis PC-300 and PC-400 in Earthworks at a Gold Mining Project in Indonesia

Journal of the Civil Engineering Forum · Vol. 9 No. 3 (2023) · hlm. 343–356

DOI
10.22146/jcef.6600
ISSN
2549-5925, 2581-1037
Terbit
2023-07-24
Penerbit
Department of Civil and Environmental Engineering, Faculty of Engineering, Universitas Gadjah Mada
Bahasa
eng

Abstrak

Material movement is a significant and costly aspect of gold or general mining projects. This involves the utilization of expensive heavy equipment, necessitating careful management to ensure optimal efficiency. Therefore, this study aimed to analyze the productivity of excavators PC-300 and PC-400 as well as compare theoretical calculation results with actual conditions. The basis was formed by real field data, collected by earthwork supervisors at a gold mine in Indonesia. This data encompassed daily heavy equipment usage, including the duration, the quantity of material moved, and the types of material involved in the relocation process. The calculations resulted in theoretical productivity of 121.45 m3 hour-1 and 99.56 m3 hour-1 for PC-400 and PC-300. Meanwhile, the calculations based on actual conditions resulted in an average productivity of 114.4 m3 hour-1 and 66.3 m3 hour-1 for PC-400 and PC-300 during a one-year project period. The difference between actual and theoretical productivity for PC-400 and PC-300 was relatively small and large at -7.05 m3 hour-1 and -33.26 m3 hour-1, with 0.94 and 0.64 match factors, respectively. The large difference in productivity for the PC-300 was because the equipment supported work projects, such as opening work area access, maintaining area of work, and serving as supporting equipment. Furthermore, it occurred in the total actual production of the material movement against the one-year target production, which was less than -31,921 m3 (-2.5%) out of the 1,277,325 m3 total. The production deficit was attributed to a construction failure that caused PC-400 and PC-300 to be temporarily relocated for reparation. Based on the simulation, target production was achieved by the actual condition at month 13 (additional 1-month duration) with a total production of 1,283,856 m3, which obtained more than +6,531 m3 (+0.51%).

Kata kunci

Jaringan kolaborasi para penulis

6 penulis · 7 tautan kepenulisan bersama · 1 lintas organisasi

Arahkan kursor atau ketuk sebuah nama untuk menyorot rekan penulisnya. Klik dua kali untuk membuka halaman penulis.

  • UIN Sunan Ampel Surabaya
  • Universitas Gadjah Mada
  • Organisasi berbeda
  • Organisasi sama
  • Afiliasi tidak diketahui
  • Garis lebih tebal = lebih banyak artikel bersama · lingkaran lebih besar = lebih banyak artikel
Tampilkan sebagai tabel
Rekan penulisOrganisasiArtikel bersama
Siti Nafilatul MunawwarohUIN Sunan Ampel Surabaya1
Intan Nur Fauziyah AmaliyahUIN Sunan Ampel Surabaya1
Abd. Rachman AssegafUIN Sunan Ampel Surabaya1
Husniyatus Salamah ZainiyahUIN Sunan Ampel Surabaya1

Afiliasi berasal dari OpenAlex; metadata OAI-PMH jurnal tidak memuatnya. Penulis tanpa ID OpenAlex dicocokkan berdasarkan nama, sehingga dua orang bisa tergabung atau satu orang bisa terpisah.

Sumber metadata: OAI-PMH (metadata jurnal) https://jurnal.ugm.ac.id/v3/jcef/oai, pertama di-harvest 9 Nov 2026, terakhir terlihat 16 Nov 2026.
Metadata asli (oai_dc)
<oai_dc:dc xmlns="http://www.openarchives.org/OAI/2.0/" xmlns:dc="http://purl.org/dc/elements/1.1/" xmlns:oai_dc="http://www.openarchives.org/OAI/2.0/oai_dc/" xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:schemaLocation="http://www.openarchives.org/OAI/2.0/oai_dc/  http://www.openarchives.org/OAI/2.0/oai_dc.xsd">
	<dc:title xml:lang="en-US">Productivity Analysis PC-300 and PC-400 in Earthworks at a Gold Mining Project in Indonesia</dc:title>
	<dc:creator>Fahmi, Muhammad</dc:creator>
	<dc:creator>Ghuzdewan, Toriq Arif </dc:creator>
	<dc:subject xml:lang="en-US">Earthwork Construction</dc:subject>
	<dc:subject xml:lang="en-US">Excavator Productivity</dc:subject>
	<dc:subject xml:lang="en-US">Heavy Equipment Simulation</dc:subject>
	<dc:subject xml:lang="en-US">Material Movement</dc:subject>
	<dc:subject xml:lang="en-US">Heavy Equipment Construction</dc:subject>
	<dc:description xml:lang="en-US">Material movement is a significant and costly aspect of gold or general mining projects. This involves the utilization of expensive heavy equipment, necessitating careful management to ensure optimal efficiency. Therefore, this study aimed to analyze the productivity of excavators PC-300 and PC-400 as well as compare theoretical calculation results with actual conditions. The basis was formed by real field data, collected by earthwork supervisors at a gold mine in Indonesia. This data encompassed daily heavy equipment usage, including the duration, the quantity of material moved, and the types of material involved in the relocation process. The calculations resulted in theoretical productivity of 121.45 m3 hour-1 and 99.56 m3 hour-1 for PC-400 and PC-300. Meanwhile, the calculations based on actual conditions resulted in an average productivity of 114.4 m3 hour-1 and 66.3 m3 hour-1 for PC-400 and PC-300 during a one-year project period. The difference between actual and theoretical productivity for PC-400 and PC-300 was relatively small and large at -7.05 m3 hour-1 and -33.26 m3 hour-1, with 0.94 and 0.64 match factors, respectively. The large difference in productivity for the PC-300 was because the equipment supported work projects, such as opening work area access, maintaining area of work, and serving as supporting equipment. Furthermore, it occurred in the total actual production of the material movement against the one-year target production, which was less than -31,921 m3 (-2.5%) out of the 1,277,325 m3 total. The production deficit was attributed to a construction failure that caused PC-400 and PC-300 to be temporarily relocated for reparation. Based on the simulation, target production was achieved by the actual condition at month 13 (additional 1-month duration) with a total production of 1,283,856 m3, which obtained more than +6,531 m3 (+0.51%).</dc:description>
	<dc:publisher xml:lang="en-US">Department of Civil and Environmental Engineering, Faculty of Engineering, Universitas Gadjah Mada</dc:publisher>
	<dc:date>2023-07-24</dc:date>
	<dc:type>info:eu-repo/semantics/article</dc:type>
	<dc:type>info:eu-repo/semantics/publishedVersion</dc:type>
	<dc:type xml:lang="en-US">Peer-reviewed Article</dc:type>
	<dc:type xml:lang="en-US">text</dc:type>
	<dc:format>application/pdf</dc:format>
	<dc:identifier>https://jurnal.ugm.ac.id/v3/JCEF/article/view/6600</dc:identifier>
	<dc:identifier>10.22146/jcef.6600</dc:identifier>
	<dc:source xml:lang="en-US">Journal of the Civil Engineering Forum; Vol. 9 No. 3 (September 2023); 343-356</dc:source>
	<dc:source>2549-5925</dc:source>
	<dc:source>2581-1037</dc:source>
	<dc:language>eng</dc:language>
	<dc:relation>https://jurnal.ugm.ac.id/v3/JCEF/article/view/6600/3066</dc:relation>
	<dc:rights xml:lang="en-US">Copyright (c) 2023 The Author(s)</dc:rights>
</oai_dc:dc>