Faktor- Faktor Yang Mempengaruhi Proses Pelaksanaan Pekerjaan Jalan Lingkar Kota Kendari II

Sultra Civil Engineering Journal (SCiEJ) · Vol. 1 No. 1 (2020) · pp. 1–20

DOI
10.54297/sciej.v1i1.52
ISSN
2716-1714
Published
2020-06-08
Publisher
Universitas Sulawesi Tenggara
Language
eng
License
creativecommons.org/licenses/by/4.0

Abstract

Project delays can come from service providers or other users who have an impact on additional time and expenses beyond the plan. If the delay comes from the contractor (Contractor), the contractor may be fined, as well as if the delay arises from the user of the service, the service user shall pay the loss incurred by the service provider, the amount stipulated in the contract in accordance with applicable legislation. Many studies have been done to determine the factors that cause the delay in completion of the project. Budgeted Cost of Work Scheduled (BCWS), describes the budget plan to a certain period of volume of the project plan to be done. Budgeted Cost of Work Performed (BCWP), describes the project plan budget for a certain period of what has been done on the actual volume of work. Land acquisition is the work of Kendari II railway project, at the time of execution of work there is a name of compensation made from the government to the community, if there is a community land whose land is affected by the project. The availability of budget is Kendari II road project, with length 38.15 km with budget amount Rp. 2.607.981.000,00 this is very limited. So that the contractor to carry out the project work according to the existing volume. Geographical conditions of the work of Kendari II city circle project, there are drawings of plans and work items before carrying out a project work. This research concludes that factors influencing the completion of construction project of Kendari II ring road.In accordance with the calculation of SPSS program (factor analysis) of 3 factors that affect the process of execution road construction project in Kendari City. The 3 factors that are contribution value in detail are: 1) availability of budget with value 93,3%, 2) land acquisition with value 68,5% and 3) Geographical condition with value 61,8%.

Collaboration network of the authors

11 authors · 20 co-authorship links · 4 across different organisations

Hover or tap a name to highlight its co-authors. Double-click to open the author's page.

  • Universitas Sulawesi Tenggara
  • National University of Samoa
  • Institut Agama Islam Negeri Kendari
  • Affiliation unknown
  • Different organisations
  • Same organisation
  • Affiliation unknown
  • Thicker line = more joint articles · bigger circle = more articles
Show as table
Co-authorOrganisationJoint articles
Sufrianto SufriantoUniversitas Sulawesi Tenggara3
La Ode Musa RachmatUniversitas Sulawesi Tenggara2
La Ode SarminUniversitas Sulawesi Tenggara1
La Ode Muh MagribiUniversitas Sulawesi Tenggara1
Syamsuddin SyamsuddinInstitut Agama Islam Negeri Kendari1
Suhardin MangidiUniversitas Sulawesi Tenggara1
Sulaiman SulaimanUniversitas Sulawesi Tenggara1
Al MustahyunUniversitas Sulawesi Tenggara1

Affiliations come from OpenAlex; journal OAI-PMH metadata carries none. Authors without an OpenAlex ID are matched by name, which can merge or split people.

Metadata source: OAI-PMH (metadata jurnal) https://jurnal-unsultra.ac.id/index.php/scej/oai, first harvested 30 Okt 2026, last seen 30 Okt 2026.
Original metadata (oai_dc)
<oai_dc:dc xmlns="http://www.openarchives.org/OAI/2.0/" xmlns:dc="http://purl.org/dc/elements/1.1/" xmlns:oai_dc="http://www.openarchives.org/OAI/2.0/oai_dc/" xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:schemaLocation="http://www.openarchives.org/OAI/2.0/oai_dc/  http://www.openarchives.org/OAI/2.0/oai_dc.xsd">
	<dc:title xml:lang="en-US">Faktor- Faktor Yang Mempengaruhi Proses Pelaksanaan Pekerjaan Jalan Lingkar Kota Kendari II</dc:title>
	<dc:creator>Madu, La</dc:creator>
	<dc:creator>Sunaryo, Sunaryo</dc:creator>
	<dc:creator>Rachmat, Laoede Musa</dc:creator>
	<dc:description xml:lang="en-US">Project delays can come from service providers or other users who have an impact on additional time and expenses beyond the plan. If the delay comes from the contractor (Contractor), the contractor may be fined, as well as if the delay arises from the user of the service, the service user shall pay the loss incurred by the service provider, the amount stipulated in the contract in accordance with applicable legislation. Many studies have been done to determine the factors that cause the delay in completion of the project. Budgeted Cost of Work Scheduled (BCWS), describes the budget plan to a certain period of volume of the project plan to be done. Budgeted Cost of Work Performed (BCWP), describes the project plan budget for a certain period of what has been done on the actual volume of work. Land acquisition is the work of Kendari II railway project, at the time of execution of work there is a name of compensation made from the government to the community, if there is a community land whose land is affected by the project. The availability of budget is Kendari II road project, with length 38.15 km with budget amount Rp. 2.607.981.000,00 this is very limited. So that the contractor to carry out the project work according to the existing volume. Geographical conditions of the work of Kendari II city circle project, there are drawings of plans and work items before carrying out a project work. This research concludes that factors influencing the completion of construction project of Kendari II ring road.In accordance with the calculation of SPSS program (factor analysis) of 3 factors that affect the process of execution road construction project in Kendari City. The 3 factors that are contribution value in detail are: 1) availability of budget with value 93,3%, 2) land acquisition with value 68,5% and 3) Geographical condition with value 61,8%.</dc:description>
	<dc:publisher xml:lang="en-US">Universitas Sulawesi Tenggara</dc:publisher>
	<dc:date>2020-06-08</dc:date>
	<dc:type>info:eu-repo/semantics/article</dc:type>
	<dc:type>info:eu-repo/semantics/publishedVersion</dc:type>
	<dc:format>application/pdf</dc:format>
	<dc:identifier>https://jurnal-unsultra.ac.id/index.php/scej/article/view/52</dc:identifier>
	<dc:identifier>10.54297/sciej.v1i1.52</dc:identifier>
	<dc:source xml:lang="en-US">Sultra Civil Engineering Journal (SCiEJ); Vol 1 No 1 (2020): Sultra Civil Engineering Journal (SCiEJ); 1-20</dc:source>
	<dc:source>2716-1714</dc:source>
	<dc:source>10.54297/sciej.v1i1</dc:source>
	<dc:language>eng</dc:language>
	<dc:relation>https://jurnal-unsultra.ac.id/index.php/scej/article/view/52/35</dc:relation>
	<dc:relation>10.54297/sciej.v1i1.52.g35</dc:relation>
	<dc:rights xml:lang="en-US">Copyright (c) 2020 La Madu, Sunaryo Sunaryo, Laoede Musa Rachmat</dc:rights>
	<dc:rights xml:lang="en-US">http://creativecommons.org/licenses/by/4.0</dc:rights>
</oai_dc:dc>