Analisis Kinerja Alat Berat Pada Proyek Normalisasi dan Perkuatan Tebing Sungai

Sultra Civil Engineering Journal (SCiEJ) · Vol. 3 No. 1 (2022) · pp. 1–8

DOI
10.54297/sciej.v3i1.239
ISSN
2716-1714
Published
2022-06-27
Publisher
Universitas Sulawesi Tenggara
Language
eng
License
creativecommons.org/licenses/by/4.0

Abstract

The purpose of this study was to analyze the performance of heavy equipment and the duration of time required to complete the Windo River Cliff Normalization and Reinforcement Project, Pamandati Village, Laeya District, South Konawe Regency. The results showed that the excavator's performance in excavation work (mechanical) was 38.68 m3/hour, dump truck 2.99 m3/hour. As for the embankment work imported from outside, the performance of the excavator is 98.53 m3/hour and the dump truck is 3.05 m3/hour. Where the duration of time required to complete the excavation work (mechanical) with an excavator is 12 days and for embankment work imported from outside is 2 days..

Collaboration network of the authors

40 authors · 118 co-authorship links · 4 across different organisations · showing the 40 most connected

Hover or tap a name to highlight its co-authors. Double-click to open the author's page.

  • Universitas Sulawesi Tenggara
  • Universitas Halu Oleo
  • World Bank
  • Affiliation unknown
  • Different organisations
  • Same organisation
  • Affiliation unknown
  • Thicker line = more joint articles · bigger circle = more articles
Show as table
Co-authorOrganisationJoint articles
Sufrianto SufriantoUniversitas Sulawesi Tenggara22
Hujiyanto HujiyantoUniversitas Sulawesi Tenggara11
Sulaiman SulaimanUniversitas Sulawesi Tenggara11
Vickky Anggara IlhamUniversitas Sulawesi Tenggara9
Catrin SudardjatUniversitas Sulawesi Tenggara4
Haryono HaryonoUniversitas Sulawesi Tenggara4
Hakiman HakimanUniversitas Sulawesi Tenggara3
La Ode Musa RachmatUniversitas Sulawesi Tenggara3
Andi MakkawaruUniversitas Sulawesi Tenggara2
Hayadi HayadiUniversitas Sulawesi Tenggara2
La Ode Muhamad MagribiUniversitas Sulawesi Tenggara2
Syamsuddin SyamsuddinUniversitas Halu Oleo2
Andi Makkawaru Isazarny JassinUniversitas Sulawesi Tenggara2
Komang Agus SaputraUniversitas Sulawesi Tenggara1
Andi Kukuh SetiawanUniversitas Sulawesi Tenggara1
Hado HadoUniversitas Sulawesi Tenggara1
Catrin SudardjatUniversitas Sulawesi Tenggara1
Syamsuddin SyamsuddinUniversitas Sulawesi Tenggara1
Sri Jayani SafitriUniversitas Sulawesi Tenggara1
Nurmaida NurmaidaUniversitas Sulawesi Tenggara1
Andi Makkawaru Isazarni JassinAffiliation unknown1
Hado HadoUniversitas Sulawesi Tenggara1
Syamsuddin SyamsuddinUniversitas Sulawesi Tenggara1
Ahmad AhmadUniversitas Sulawesi Tenggara1
M BasriUniversitas Sulawesi Tenggara1
Sulaiman sulaimanAffiliation unknown1
La Ode Muh MagribiUniversitas Sulawesi Tenggara1
Sumariyani SumariyaniWorld Bank1
Dian FitrawansyahUniversitas Sulawesi Tenggara1
Eko Efendi JuantoroUniversitas Sulawesi Tenggara1
La Ode Munawal Akbar IdatiUniversitas Sulawesi Tenggara1
Arsum Rheza Djaya SaputraUniversitas Sulawesi Tenggara1
La Ode Ahmad RasyidAffiliation unknown1
Neti RahmawatiAffiliation unknown1
Sulaiman SulaimanUniversitas Sulawesi Tenggara1
La Derita FlorentinusUniversitas Sulawesi Tenggara1

Affiliations come from OpenAlex; journal OAI-PMH metadata carries none. Authors without an OpenAlex ID are matched by name, which can merge or split people.

Metadata source: OAI-PMH (metadata jurnal) https://jurnal-unsultra.ac.id/index.php/scej/oai, first harvested 30 Okt 2026, last seen 30 Okt 2026.
Original metadata (oai_dc)
<oai_dc:dc xmlns="http://www.openarchives.org/OAI/2.0/" xmlns:dc="http://purl.org/dc/elements/1.1/" xmlns:oai_dc="http://www.openarchives.org/OAI/2.0/oai_dc/" xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:schemaLocation="http://www.openarchives.org/OAI/2.0/oai_dc/  http://www.openarchives.org/OAI/2.0/oai_dc.xsd">
	<dc:title xml:lang="en-US">Analisis Kinerja Alat Berat Pada Proyek Normalisasi dan Perkuatan Tebing Sungai</dc:title>
	<dc:creator>Jaya, Ansar</dc:creator>
	<dc:creator>Lakawa, Irwan</dc:creator>
	<dc:creator>Hawa, Sitti</dc:creator>
	<dc:creator>Bona, Muh Samtun</dc:creator>
	<dc:description xml:lang="en-US">The purpose of this study was to analyze the performance of heavy equipment and the duration of time required to complete the Windo River Cliff Normalization and Reinforcement Project, Pamandati Village, Laeya District, South Konawe Regency. The results showed that the excavator's performance in excavation work (mechanical) was 38.68 m3/hour, dump truck 2.99 m3/hour. As for the embankment work imported from outside, the performance of the excavator is 98.53 m3/hour and the dump truck is 3.05 m3/hour. Where the duration of time required to complete the excavation work (mechanical) with an excavator is 12 days and for embankment work imported from outside is 2 days..</dc:description>
	<dc:publisher xml:lang="en-US">Universitas Sulawesi Tenggara</dc:publisher>
	<dc:date>2022-06-27</dc:date>
	<dc:type>info:eu-repo/semantics/article</dc:type>
	<dc:type>info:eu-repo/semantics/publishedVersion</dc:type>
	<dc:format>application/pdf</dc:format>
	<dc:identifier>https://jurnal-unsultra.ac.id/index.php/scej/article/view/239</dc:identifier>
	<dc:identifier>10.54297/sciej.v3i1.239</dc:identifier>
	<dc:source xml:lang="en-US">Sultra Civil Engineering Journal (SCiEJ); Vol 3 No 1 (2022): Sultra Civil Engineering Journal (SCiEJ); 1-8</dc:source>
	<dc:source>2716-1714</dc:source>
	<dc:source>10.54297/sciej.v3i1</dc:source>
	<dc:language>eng</dc:language>
	<dc:relation>https://jurnal-unsultra.ac.id/index.php/scej/article/view/239/146</dc:relation>
	<dc:relation>10.54297/sciej.v3i1.239.g146</dc:relation>
	<dc:rights xml:lang="en-US">Copyright (c) 2022 Ansar Jaya, Irwan Lakawa, Sitti Hawa, Muh Samtun Bona</dc:rights>
	<dc:rights xml:lang="en-US">http://creativecommons.org/licenses/by/4.0</dc:rights>
</oai_dc:dc>