Penggunaan Standar Metode Work Breakdown Structure (WBS) Pada Proyek Pembangunan Gudang BPBD dan Rumah Jabatan Dandim

Sultra Civil Engineering Journal (SCiEJ) · Vol. 5 No. 2 (2024) · pp. 300–307

DOI
10.54297/sciej.v5i2.626
ISSN
2716-1714
Published
2024-10-25
Publisher
Universitas Sulawesi Tenggara
Language
eng
License
creativecommons.org/licenses/by/4.0

Abstract

In today's modern era, the construction of buildings stands as a crucial element in the development of infrastructure. Among the various methods utilized for managing such construction projects, the Work Breakdown Structure (WBS) has emerged as an effective tool. WBS serves as a project management technique, breaking down complex tasks into smaller, manageable components, thereby facilitating efficient planning, execution, and monitoring throughout the project lifecycle.This research employs the Earned Value Method (EVM) approach, chosen for its adeptness in quantifying project cost and time performance. By integrating three key dimensions - scope, schedule, and budget - EVM offers a comprehensive framework for evaluating project performance.The findings of this study reveal subpar cost and time performance in the construction of the BPBD Warehouse and Military District Commander's office building. Conversely, the construction of the Veterans Building demonstrates stable performance in both cost and time aspects.The observed impact of implementing WBS standards, particularly in the construction of the Veterans Building, proves instrumental in enhancing project control. The detailed breakdown of work items and the clearer identification of required resources streamline the planning of Purchasing Orders (PO), thereby facilitating cost management efforts.

Collaboration network of the authors

40 authors · 155 co-authorship links · 9 across different organisations · showing the 40 most connected

Hover or tap a name to highlight its co-authors. Double-click to open the author's page.

  • Universitas Halu Oleo
  • Universitas Sulawesi Tenggara
  • Universitas Sembilanbelas November Kolaka
  • Affiliation unknown
  • Different organisations
  • Same organisation
  • Affiliation unknown
  • Thicker line = more joint articles · bigger circle = more articles
Show as table
Co-authorOrganisationJoint articles
La WelendoAffiliation unknown7
Siti Nurjanah AhmadUniversitas Halu Oleo6
Baso MursidiAffiliation unknown5
Sufrianto SufriantoUniversitas Sulawesi Tenggara4
La Ode Muhamad Nurrakhmad ArsyadUniversitas Halu Oleo4
Nasrul NasrulUniversitas Halu Oleo4
Adris Ade PutraAffiliation unknown3
sulha sulhaAffiliation unknown3
Ainussalbi Al IkhsanAffiliation unknown2
Muhammad Syarif PrasetiaAffiliation unknown2
Mappa NasrunAffiliation unknown2
Fathur Rahman RustanUniversitas Sembilanbelas November Kolaka2
La Ode Muhammad Nurrakhmad ArsyadAffiliation unknown2
Fitriah Mas'udAffiliation unknown2
Mappa NashrunAffiliation unknown2
St Nawal JayaUniversitas Halu Oleo2
ARMAN FASLIHAffiliation unknown2
Adris A. PutraAffiliation unknown2
Statiswaty StatiswatyUniversitas Halu Oleo2
Gede Agus SutrayasaUniversitas Halu Oleo2
Laode DenyUniversitas Halu Oleo2
Kadir RamadanUniversitas Halu Oleo2
Galih Adi SulistyoUniversitas Halu Oleo2
Anafi MinmahddunUniversitas Halu Oleo2
Irwan LakawaUniversitas Sulawesi Tenggara1
Vickky Anggara IlhamUniversitas Sulawesi Tenggara1
Hujiyanto HujiyantoUniversitas Sulawesi Tenggara1
Andi Makkawaru Isazarni JassinAffiliation unknown1
Syamsuddin SyamsuddinUniversitas Sulawesi Tenggara1
Andi MakkawaruUniversitas Sulawesi Tenggara1
M. Awal Rafli JanwarUniversitas Sulawesi Tenggara1
Asriyati AsriyatiAffiliation unknown1
Maudhy SatyadharmaAffiliation unknown1
Hakiman HakimanUniversitas Sulawesi Tenggara1
Muhammad MuhsarUniversitas Sulawesi Tenggara1

Affiliations come from OpenAlex; journal OAI-PMH metadata carries none. Authors without an OpenAlex ID are matched by name, which can merge or split people.

Metadata source: OAI-PMH (metadata jurnal) https://jurnal-unsultra.ac.id/index.php/scej/oai, first harvested 30 Okt 2026, last seen 30 Okt 2026.
Original metadata (oai_dc)
<oai_dc:dc xmlns="http://www.openarchives.org/OAI/2.0/" xmlns:dc="http://purl.org/dc/elements/1.1/" xmlns:oai_dc="http://www.openarchives.org/OAI/2.0/oai_dc/" xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:schemaLocation="http://www.openarchives.org/OAI/2.0/oai_dc/  http://www.openarchives.org/OAI/2.0/oai_dc.xsd">
	<dc:title xml:lang="en-US">Penggunaan Standar Metode Work Breakdown Structure (WBS) Pada Proyek Pembangunan Gudang BPBD dan Rumah Jabatan Dandim</dc:title>
	<dc:creator>Soeparyanto, Try Sugiyarto</dc:creator>
	<dc:creator>Nuhun, Ridwan Syah</dc:creator>
	<dc:creator>Ismayana, Ismayana</dc:creator>
	<dc:creator>Apriani, Meri</dc:creator>
	<dc:creator>Hado, Hado</dc:creator>
	<dc:description xml:lang="en-US">In today's modern era, the construction of buildings stands as a crucial element in the development of infrastructure. Among the various methods utilized for managing such construction projects, the Work Breakdown Structure (WBS) has emerged as an effective tool. WBS serves as a project management technique, breaking down complex tasks into smaller, manageable components, thereby facilitating efficient planning, execution, and monitoring throughout the project lifecycle.This research employs the Earned Value Method (EVM) approach, chosen for its adeptness in quantifying project cost and time performance. By integrating three key dimensions - scope, schedule, and budget - EVM offers a comprehensive framework for evaluating project performance.The findings of this study reveal subpar cost and time performance in the construction of the BPBD Warehouse and Military District Commander's office building. Conversely, the construction of the Veterans Building demonstrates stable performance in both cost and time aspects.The observed impact of implementing WBS standards, particularly in the construction of the Veterans Building, proves instrumental in enhancing project control. The detailed breakdown of work items and the clearer identification of required resources streamline the planning of Purchasing Orders (PO), thereby facilitating cost management efforts.</dc:description>
	<dc:publisher xml:lang="en-US">Universitas Sulawesi Tenggara</dc:publisher>
	<dc:date>2024-10-25</dc:date>
	<dc:type>info:eu-repo/semantics/article</dc:type>
	<dc:type>info:eu-repo/semantics/publishedVersion</dc:type>
	<dc:format>application/pdf</dc:format>
	<dc:identifier>https://jurnal-unsultra.ac.id/index.php/scej/article/view/626</dc:identifier>
	<dc:identifier>10.54297/sciej.v5i2.626</dc:identifier>
	<dc:source xml:lang="en-US">Sultra Civil Engineering Journal (SCiEJ); Vol 5 No 2 (2024): Sultra Civil Engineering Journal (SCiEJ); 300-307</dc:source>
	<dc:source>2716-1714</dc:source>
	<dc:source>10.54297/sciej.v5i2</dc:source>
	<dc:language>eng</dc:language>
	<dc:relation>https://jurnal-unsultra.ac.id/index.php/scej/article/view/626/403</dc:relation>
	<dc:relation>10.54297/sciej.v5i2.626.g403</dc:relation>
	<dc:rights xml:lang="en-US">Copyright (c) 2024 Try Sugiyarto Soeparyanto, Ridwan Syah Nuhun, Ismayana Ismayana, Meri Apriani, Hado Hado</dc:rights>
	<dc:rights xml:lang="en-US">http://creativecommons.org/licenses/by/4.0</dc:rights>
</oai_dc:dc>