Abstract

The aim of the research is to find out or predict how much a project will cost during implementation and to find out the effectiveness of project control using the Earned Value Method. To overcome existing problems, an Earned Value method is used. There are two parameters or indicators used for analysis, namely BCWS, BCWP. Delay deviations can be identified by looking at the Schedule Variance (SV). This method can also be used to determine the efficiency of resource use in the form of the schedule performance index (SPI). The project implementation time aspect has a negative value up to the 12 th week of (SV) -Rp. 44,776,771.84 or schedule performance index (SPI) = 0.82 < 1. The calculation results are obtained from an effectiveness value of 0.85 for controlling project time using the Method Earned Value. In other words, the results of an effectiveness value that is smaller than 1 (one) can be said to be that the Time Performance for the Implementation of the Concrete Pavement Road Work Project in North Kolaka Regency is less effective. From the results of the time performance study using the Earned Value Method, it can be concluded that the Time Performance for the Implementation of the Concrete Pavement Road Work Project in North Kolaka Regency experienced a delay from the initial plan. It is clear that in weeks 1 to 12 the project performance was delayed from the planned schedule

Collaboration network of the authors

40 authors · 122 co-authorship links · 4 across different organisations · showing the 40 most connected

Hover or tap a name to highlight its co-authors. Double-click to open the author's page.

  • Universitas Sulawesi Tenggara
  • Institut Agama Islam Negeri Kendari
  • Affiliation unknown
  • Different organisations
  • Same organisation
  • Affiliation unknown
  • Thicker line = more joint articles · bigger circle = more articles
Show as table
Co-authorOrganisationJoint articles
Irwan LakawaUniversitas Sulawesi Tenggara29
Catrin SudardjatUniversitas Sulawesi Tenggara10
Hujiyanto HujiyantoUniversitas Sulawesi Tenggara9
Hado HadoUniversitas Sulawesi Tenggara6
Hakiman HakimanUniversitas Sulawesi Tenggara5
Sitti HawaUniversitas Sulawesi Tenggara4
Haryono HaryonoUniversitas Sulawesi Tenggara4
Sunaryo SunaryoUniversitas Sulawesi Tenggara3
Andi Makkawaru Isazarny JassinUniversitas Sulawesi Tenggara3
Muhammad MuhsarUniversitas Sulawesi Tenggara3
Lisman LismanUniversitas Sulawesi Tenggara3
Komang Agus SaputraUniversitas Sulawesi Tenggara3
Andi Kukuh SetiawanUniversitas Sulawesi Tenggara3
Haryono HaryonoUniversitas Sulawesi Tenggara2
La Ode Musa RachmatUniversitas Sulawesi Tenggara2
Fikri Aris MunandarUniversitas Sulawesi Tenggara2
La Ode Abdul MananUniversitas Sulawesi Tenggara2
Erni DanggiUniversitas Sulawesi Tenggara2
Hajar HajarUniversitas Sulawesi Tenggara2
Farra SasmitaUniversitas Sulawesi Tenggara2
Erni DanggiUniversitas Sulawesi Tenggara2
Andi Makkawaru Isazarni JassinAffiliation unknown2
Syamsuddin SyamsuddinUniversitas Sulawesi Tenggara2
Syamsuddin SyamsuddinInstitut Agama Islam Negeri Kendari2
La Ode BariunUniversitas Sulawesi Tenggara1
Humairah MuljabarUniversitas Sulawesi Tenggara1
La Ode Muhammad Isman Hardiansyah BariunAffiliation unknown1
Joko Tri BrataUniversitas Sulawesi Tenggara1
Arsalim ArsalimUniversitas Sulawesi Tenggara1
Aswad AswadUniversitas Sulawesi Tenggara1
Syamsuddin SyamsuddinUniversitas Sulawesi Tenggara1
Eko Efendi JuantoroUniversitas Sulawesi Tenggara1
La Ode Muhamad MagribiUniversitas Sulawesi Tenggara1
Ramadhan Hidayat PutraUniversitas Sulawesi Tenggara1
Amad Syarif SyukriAffiliation unknown1
Catrin SudarjatUniversitas Sulawesi Tenggara1

Affiliations come from OpenAlex; journal OAI-PMH metadata carries none. Authors without an OpenAlex ID are matched by name, which can merge or split people.

Metadata source: OAI-PMH (metadata jurnal) https://jurnal-unsultra.ac.id/index.php/scej/oai, first harvested 30 Okt 2026, last seen 30 Okt 2026.
Original metadata (oai_dc)
<oai_dc:dc xmlns="http://www.openarchives.org/OAI/2.0/" xmlns:dc="http://purl.org/dc/elements/1.1/" xmlns:oai_dc="http://www.openarchives.org/OAI/2.0/oai_dc/" xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:schemaLocation="http://www.openarchives.org/OAI/2.0/oai_dc/  http://www.openarchives.org/OAI/2.0/oai_dc.xsd">
	<dc:title xml:lang="en-US">Kinerja Waktu Pelaksanaan Proyek Pekerjaan Jalan Di Kabupaten Kolaka Utara (Studi Kasus Jalan Poros Lasusua Desa Totallang)</dc:title>
	<dc:creator>Sufrianto, Sufrianto</dc:creator>
	<dc:creator>Ilham, Vickky Anggara</dc:creator>
	<dc:creator>Makkawaru, Andi</dc:creator>
	<dc:creator>Ilahi, La Ode Altakdir</dc:creator>
	<dc:description xml:lang="en-US">The aim of the research is to find out or predict how much a project will cost during implementation and to find out the effectiveness of project control using the Earned Value Method. To overcome existing problems, an Earned Value method is used. There are two parameters or indicators used for analysis, namely BCWS, BCWP. Delay deviations can be identified by looking at the Schedule Variance (SV). This method can also be used to determine the efficiency of resource use in the form of the schedule performance index (SPI). The project implementation time aspect has a negative value up to the 12 th week of (SV) -Rp. 44,776,771.84 or schedule performance index (SPI) = 0.82 &amp;lt; 1. The calculation results are obtained from an effectiveness value of 0.85 for controlling project time using the Method Earned Value. In other words, the results of an effectiveness value that is smaller than 1 (one) can be said to be that the Time Performance for the Implementation of the Concrete Pavement Road Work Project in North Kolaka Regency is less effective. From the results of the time performance study using the Earned Value Method, it can be concluded that the Time Performance for the Implementation of the Concrete Pavement Road Work Project in North Kolaka Regency experienced a delay from the initial plan. It is clear that in weeks 1 to 12 the project performance was delayed from the planned schedule</dc:description>
	<dc:publisher xml:lang="en-US">Universitas Sulawesi Tenggara</dc:publisher>
	<dc:date>2024-10-25</dc:date>
	<dc:type>info:eu-repo/semantics/article</dc:type>
	<dc:type>info:eu-repo/semantics/publishedVersion</dc:type>
	<dc:format>application/pdf</dc:format>
	<dc:identifier>https://jurnal-unsultra.ac.id/index.php/scej/article/view/696</dc:identifier>
	<dc:identifier>10.54297/sciej.v5i2.696</dc:identifier>
	<dc:source xml:lang="en-US">Sultra Civil Engineering Journal (SCiEJ); Vol 5 No 2 (2024): Sultra Civil Engineering Journal (SCiEJ); 398-410</dc:source>
	<dc:source>2716-1714</dc:source>
	<dc:source>10.54297/sciej.v5i2</dc:source>
	<dc:language>eng</dc:language>
	<dc:relation>https://jurnal-unsultra.ac.id/index.php/scej/article/view/696/412</dc:relation>
	<dc:relation>10.54297/sciej.v5i2.696.g412</dc:relation>
	<dc:rights xml:lang="en-US">Copyright (c) 2024 Sufrianto Sufrianto, Vickky Anggara Ilham, Andi Makawaru Makkawaru, La Ode Altakdir Ilahi</dc:rights>
	<dc:rights xml:lang="en-US">http://creativecommons.org/licenses/by/4.0</dc:rights>
</oai_dc:dc>