Analisa Percepatan Dengan Metode Time Cost Trade Off Pada Proyek Pembangunan SPBI 2 × 200 Kl

Sultra Civil Engineering Journal (SCiEJ) · Vol. 6 No. 1 (2025) · hlm. 446–457

DOI
10.54297/sciej.v6i1.927
ISSN
2716-1714
Terbit
2025-04-22
Penerbit
Universitas Sulawesi Tenggara
Bahasa
eng
Lisensi
creativecommons.org/licenses/by/4.0

Abstrak

The SPBI 2×200 KL construction project, initially planned to be completed in 360 days, experienced significant delays in the 21st week, with a progress deviation of -16.434%. To address this issue, the Time Cost Trade Off (TCTO) acceleration method was implemented by adding 4 hours of overtime work per day. This strategy successfully shortened the project duration from 336 days to 231 days, reducing the total project time by 37%. The acceleration efforts were focused on critical paths that influenced the project's completion. Although there was a 17.1% increase in direct costs due to overtime wages, additional labor, and extra materials, the application of TCTO effectively reduced indirect costs associated with prolonged project duration, such as administrative and operational expenses. Overall, this method proved to be effective in bringing the project back on schedule and preventing further losses due to delays.

Jaringan kolaborasi para penulis

6 penulis · 9 tautan kepenulisan bersama

Arahkan kursor atau ketuk sebuah nama untuk menyorot rekan penulisnya. Klik dua kali untuk membuka halaman penulis.

  • Universitas Bina Darma
  • Organisasi berbeda
  • Organisasi sama
  • Afiliasi tidak diketahui
  • Garis lebih tebal = lebih banyak artikel bersama · lingkaran lebih besar = lebih banyak artikel
Tampilkan sebagai tabel
Rekan penulisOrganisasiArtikel bersama
Dwi KurniaUniversitas Bina Darma1
Achmad SyarifudinUniversitas Bina Darma1
Wanda Yudha PrawiraUniversitas Bina Darma1

Afiliasi berasal dari OpenAlex; metadata OAI-PMH jurnal tidak memuatnya. Penulis tanpa ID OpenAlex dicocokkan berdasarkan nama, sehingga dua orang bisa tergabung atau satu orang bisa terpisah.

Sumber metadata: OAI-PMH (metadata jurnal) https://jurnal-unsultra.ac.id/index.php/scej/oai, pertama di-harvest 30 Okt 2026, terakhir terlihat 22 Nov 2026.
Metadata asli (oai_dc)
<oai_dc:dc xmlns="http://www.openarchives.org/OAI/2.0/" xmlns:dc="http://purl.org/dc/elements/1.1/" xmlns:oai_dc="http://www.openarchives.org/OAI/2.0/oai_dc/" xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:schemaLocation="http://www.openarchives.org/OAI/2.0/oai_dc/  http://www.openarchives.org/OAI/2.0/oai_dc.xsd">
	<dc:title xml:lang="en-US">Analisa Percepatan Dengan Metode Time Cost Trade Off Pada Proyek Pembangunan SPBI 2 × 200 Kl</dc:title>
	<dc:creator>Sakinah, Sakinah</dc:creator>
	<dc:creator>Mazpar, Ely</dc:creator>
	<dc:creator>Mulyati, Ely</dc:creator>
	<dc:description xml:lang="en-US">The SPBI 2×200 KL construction project, initially planned to be completed in 360 days, experienced significant delays in the 21st week, with a progress deviation of -16.434%. To address this issue, the Time Cost Trade Off (TCTO) acceleration method was implemented by adding 4 hours of overtime work per day. This strategy successfully shortened the project duration from 336 days to 231 days, reducing the total project time by 37%. The acceleration efforts were focused on critical paths that influenced the project's completion. Although there was a 17.1% increase in direct costs due to overtime wages, additional labor, and extra materials, the application of TCTO effectively reduced indirect costs associated with prolonged project duration, such as administrative and operational expenses. Overall, this method proved to be effective in bringing the project back on schedule and preventing further losses due to delays.</dc:description>
	<dc:publisher xml:lang="en-US">Universitas Sulawesi Tenggara</dc:publisher>
	<dc:date>2025-04-22</dc:date>
	<dc:type>info:eu-repo/semantics/article</dc:type>
	<dc:type>info:eu-repo/semantics/publishedVersion</dc:type>
	<dc:format>application/pdf</dc:format>
	<dc:identifier>https://jurnal-unsultra.ac.id/index.php/scej/article/view/927</dc:identifier>
	<dc:identifier>10.54297/sciej.v6i1.927</dc:identifier>
	<dc:source xml:lang="en-US">Sultra Civil Engineering Journal (SCiEJ); Vol 6 No 1 (2025): Sultra Civil Engineering Journal (SCiEJ); 446-457</dc:source>
	<dc:source>2716-1714</dc:source>
	<dc:source>10.54297/sciej.v6i1</dc:source>
	<dc:language>eng</dc:language>
	<dc:relation>https://jurnal-unsultra.ac.id/index.php/scej/article/view/927/706</dc:relation>
	<dc:relation>10.54297/sciej.v6i1.927.g706</dc:relation>
	<dc:rights xml:lang="en-US">Copyright (c) 2025 Sakinah Sakinah, Ely Mazpar, Ely Mulyati</dc:rights>
	<dc:rights xml:lang="en-US">http://creativecommons.org/licenses/by/4.0</dc:rights>
</oai_dc:dc>