Pengembangan Model Prediksi Kinerja Proyek Menggunakan Earned Value Management Berbasis Data Progres Mingguan

Sultra Civil Engineering Journal (SCiEJ) · Vol. 6 No. 2 (2025) · hlm. 650–662

DOI
10.54297/sciej.v6i2.1257
ISSN
2716-1714
Terbit
2025-10-27
Penerbit
Universitas Sulawesi Tenggara
Bahasa
eng
Lisensi
creativecommons.org/licenses/by/4.0

Abstrak

Construction projects are inherently complex due to the involvement of human resources, materials, equipment, costs, and schedules. In Indonesia, project delays and cost overruns remain common issues, often caused by weak monitoring and control mechanisms. Conventional reporting methods, which rely mainly on progress percentages or S-curves, are limited because they do not provide integrated information on cost, time, and performance. This study develops a project performance prediction model using Earned Value Management (EVM) based on weekly progress data, with a case study on the construction of the LPPM & BPMI Building at Veteran Bangun Nusantara University. The research applies an applied case study approach, utilizing project documents and weekly progress reports as the primary data. Indicators such as Planned Value (PV), Earned Value (EV), Schedule Variance (SV), and Schedule Performance Index (SPI) were calculated for weeks 1–13. The analysis shows that while the project was initially ahead of schedule (positive SV and SPI > 1 in weeks 1–5), performance declined significantly after week 6. At week 13, the SV turned negative with an increasing gap between planned and actual progress, while the SPI dropped to 0.44, indicating serious schedule inefficiency. Forecasting results using EVM predict that the project, initially planned for completion in 25 weeks, will require 41 weeks, resulting in a delay of approximately 16 weeks.

Jaringan kolaborasi para penulis

3 penulis · 3 tautan kepenulisan bersama

Arahkan kursor atau ketuk sebuah nama untuk menyorot rekan penulisnya. Klik dua kali untuk membuka halaman penulis.

  • Afiliasi tidak diketahui
  • Organisasi berbeda
  • Organisasi sama
  • Afiliasi tidak diketahui
  • Garis lebih tebal = lebih banyak artikel bersama · lingkaran lebih besar = lebih banyak artikel
Tampilkan sebagai tabel
Rekan penulisOrganisasiArtikel bersama

Afiliasi berasal dari OpenAlex; metadata OAI-PMH jurnal tidak memuatnya. Penulis tanpa ID OpenAlex dicocokkan berdasarkan nama, sehingga dua orang bisa tergabung atau satu orang bisa terpisah.

Sumber metadata: OAI-PMH (metadata jurnal) https://jurnal-unsultra.ac.id/index.php/scej/oai, pertama di-harvest 30 Okt 2026, terakhir terlihat 22 Nov 2026.
Metadata asli (oai_dc)
<oai_dc:dc xmlns="http://www.openarchives.org/OAI/2.0/" xmlns:dc="http://purl.org/dc/elements/1.1/" xmlns:oai_dc="http://www.openarchives.org/OAI/2.0/oai_dc/" xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:schemaLocation="http://www.openarchives.org/OAI/2.0/oai_dc/  http://www.openarchives.org/OAI/2.0/oai_dc.xsd">
	<dc:title xml:lang="en-US">Pengembangan Model Prediksi Kinerja Proyek Menggunakan Earned Value Management Berbasis Data Progres Mingguan</dc:title>
	<dc:creator>Firdausi, Annisa Azhar</dc:creator>
	<dc:creator>Ristanto, Iwan</dc:creator>
	<dc:creator>Burhanudin, Faisal</dc:creator>
	<dc:description xml:lang="en-US">Construction projects are inherently complex due to the involvement of human resources, materials, equipment, costs, and schedules. In Indonesia, project delays and cost overruns remain common issues, often caused by weak monitoring and control mechanisms. Conventional reporting methods, which rely mainly on progress percentages or S-curves, are limited because they do not provide integrated information on cost, time, and performance. This study develops a project performance prediction model using Earned Value Management (EVM) based on weekly progress data, with a case study on the construction of the LPPM &amp;amp; BPMI Building at Veteran Bangun Nusantara University. The research applies an applied case study approach, utilizing project documents and weekly progress reports as the primary data. Indicators such as Planned Value (PV), Earned Value (EV), Schedule Variance (SV), and Schedule Performance Index (SPI) were calculated for weeks 1–13. The analysis shows that while the project was initially ahead of schedule (positive SV and SPI &amp;gt; 1 in weeks 1–5), performance declined significantly after week 6. At week 13, the SV turned negative with an increasing gap between planned and actual progress, while the SPI dropped to 0.44, indicating serious schedule inefficiency. Forecasting results using EVM predict that the project, initially planned for completion in 25 weeks, will require 41 weeks, resulting in a delay of approximately 16 weeks.</dc:description>
	<dc:publisher xml:lang="en-US">Universitas Sulawesi Tenggara</dc:publisher>
	<dc:date>2025-10-27</dc:date>
	<dc:type>info:eu-repo/semantics/article</dc:type>
	<dc:type>info:eu-repo/semantics/publishedVersion</dc:type>
	<dc:format>application/pdf</dc:format>
	<dc:identifier>https://jurnal-unsultra.ac.id/index.php/scej/article/view/1257</dc:identifier>
	<dc:identifier>10.54297/sciej.v6i2.1257</dc:identifier>
	<dc:source xml:lang="en-US">Sultra Civil Engineering Journal (SCiEJ); Vol 6 No 2 (2025): Sultra Civil Engineering Journal (SCiEJ); 650-662</dc:source>
	<dc:source>2716-1714</dc:source>
	<dc:source>10.54297/sciej.v6i2</dc:source>
	<dc:language>eng</dc:language>
	<dc:relation>https://jurnal-unsultra.ac.id/index.php/scej/article/view/1257/899</dc:relation>
	<dc:rights xml:lang="en-US">Copyright (c) 2025 Annisa Azhar Firdausi, Iwan Ristanto, Faisal Burhanudin</dc:rights>
	<dc:rights xml:lang="en-US">http://creativecommons.org/licenses/by/4.0</dc:rights>
</oai_dc:dc>