Optimization of dynamic transmission network expansion planning using binary particle swarm optimization algorithm

Bulletin of Electrical Engineering and Informatics · Vol. 14 No. 2 (2025) · hlm. 861–873

DOI
10.11591/eei.v14i2.8944
ISSN
2089-3191, 2302-9285
Terbit
2025-04-01
Penerbit
Institute of Advanced Engineering and Science (IAES)
Bahasa
en
Lisensi
creativecommons.org/licenses/by-sa/4.0/

Abstrak

Increasing power demand is usually met by the expansion of generation capacity. The transmission network should be expanded in tandem to ensure power is evacuated from generation points to the load centres. Inadequate power capacity causes congestion. Congestion results due to under-voltages and violation of transmission lines’ loading limits. Constructing additional transmission lines is required to alleviate the congestion after measures of increasing the transmission line’s transfer capability are exploited. Transmission network expansion planning (TNEP) determines the transmission lines to be added to a power system at minimal construction cost, without violating network constraints. In this research, voltage limit violations are penalized in a constrained dynamic TNEP problem for a 10-year planning horizon. The optimal location and number of new transmission lines required at minimal construction cost, and transmission losses associated with the transmission network operations are determined. Improved binary particle swarm optimization (IBPSO) algorithm is applied to optimize the dynamic transmission network expansion planning (DTNEP) results. The developed model is tested on Garver’s 6-bus system using MATLAB. The construction cost for new transmission lines is minimized, and transmission losses reduced when compared to other published works without violating voltage limits (±5%) and transmission lines’ thermal capacities. The transmission network system adequacy is improved.

Kata kunci

Jaringan kolaborasi para penulis

5 penulis · 6 tautan kepenulisan bersama

Arahkan kursor atau ketuk sebuah nama untuk menyorot rekan penulisnya. Klik dua kali untuk membuka halaman penulis.

  • Jomo Kenyatta University of Agriculture and Technology
  • Organisasi berbeda
  • Organisasi sama
  • Afiliasi tidak diketahui
  • Garis lebih tebal = lebih banyak artikel bersama · lingkaran lebih besar = lebih banyak artikel
Tampilkan sebagai tabel
Rekan penulisOrganisasiArtikel bersama
Christopher Maina MuriithiJomo Kenyatta University of Agriculture and Technology2
Brian K. WamukoyaJomo Kenyatta University of Agriculture and Technology2

Afiliasi berasal dari OpenAlex; metadata OAI-PMH jurnal tidak memuatnya. Penulis tanpa ID OpenAlex dicocokkan berdasarkan nama, sehingga dua orang bisa tergabung atau satu orang bisa terpisah.

Sumber metadata: OpenAlex API (jurnal SINTA, ADR 0048) https://openalex.org/S2765016208, pertama di-harvest 22 Nov 2026, terakhir terlihat 22 Nov 2026.
Metadata asli (oai_dc)
<oai_dc:dc xmlns:dc="http://purl.org/dc/elements/1.1/" xmlns:oai_dc="http://www.openarchives.org/OAI/2.0/oai_dc/"><dc:title xml:lang="en">Optimization of dynamic transmission network expansion planning using binary particle swarm optimization algorithm</dc:title><dc:creator>Faith Eseri Inyanga</dc:creator><dc:creator>Irene Ndunge Muisyo</dc:creator><dc:creator>Keren K. Kaberere</dc:creator><dc:subject>transmission expansion planning</dc:subject><dc:subject>binary particle swarm optimization</dc:subject><dc:subject>transmission loss</dc:subject><dc:subject>power system congestion</dc:subject><dc:subject>network adequacy</dc:subject><dc:description xml:lang="en">Increasing power demand is usually met by the expansion of generation capacity. The transmission network should be expanded in tandem to ensure power is evacuated from generation points to the load centres. Inadequate power capacity causes congestion. Congestion results due to under-voltages and violation of transmission lines’ loading limits. Constructing additional transmission lines is required to alleviate the congestion after measures of increasing the transmission line’s transfer capability are exploited. Transmission network expansion planning (TNEP) determines the transmission lines to be added to a power system at minimal construction cost, without violating network constraints. In this research, voltage limit violations are penalized in a constrained dynamic TNEP problem for a 10-year planning horizon. The optimal location and number of new transmission lines required at minimal construction cost, and transmission losses associated with the transmission network operations are determined. Improved binary particle swarm optimization (IBPSO) algorithm is applied to optimize the dynamic transmission network expansion planning (DTNEP) results. The developed model is tested on Garver’s 6-bus system using MATLAB. The construction cost for new transmission lines is minimized, and transmission losses reduced when compared to other published works without violating voltage limits (±5%) and transmission lines’ thermal capacities. The transmission network system adequacy is improved.</dc:description><dc:publisher>Institute of Advanced Engineering and Science (IAES)</dc:publisher><dc:date>2025-04-01</dc:date><dc:type>info:eu-repo/semantics/article</dc:type><dc:format>application/pdf</dc:format><dc:identifier>https://doi.org/10.11591/eei.v14i2.8944</dc:identifier><dc:identifier>10.11591/eei.v14i2.8944</dc:identifier><dc:source>Bulletin of Electrical Engineering and Informatics; Vol 14 No 2 (2025); 861-873</dc:source><dc:source>2089-3191</dc:source><dc:source>2302-9285</dc:source><dc:language>en</dc:language><dc:relation>https://beei.org/index.php/EEI/article/download/8944/4096</dc:relation><dc:rights>https://creativecommons.org/licenses/by-sa/4.0/</dc:rights></oai_dc:dc>