Abstrak

A problem that often occurs in construction projects is the delay in the implementation process. Various factors cause the delay, but in developing countries such as Indonesia, the dominant delay occurs because the implementing contractor causes it for unforgivable reasons (non-excusable delay). This study aims to determine the influence of the non-excusable delay parameter and the relationship between these factors. The research is quantitative with data collection techniques in the form of unstructured interviews, field observations, and surveys using research questionnaires with the number of respondents obtained as many as 33 people consisting of the owner, construction management consultant, quantity surveyor consultant, and ends with confirmation of the results. Research on the implementing contractor. Data analysis was performed using multiple linear regression analysis. The test results of multiple linear regression analysis show that the non-excusable delay factor can significantly affect the completion of construction projects. The influence of each element is 0.434 units for the lack of contractor competence, 0.067 units for inappropriate implementation planning, and -0.097 for inefficient field management units. And simultaneously, these three factors can significantly increase the project delay value index.

Kata kunci

Jaringan kolaborasi para penulis

12 penulis · 23 tautan kepenulisan bersama

Arahkan kursor atau ketuk sebuah nama untuk menyorot rekan penulisnya. Klik dua kali untuk membuka halaman penulis.

  • Jakarta State Polytechnic
  • Afiliasi tidak diketahui
  • Organisasi berbeda
  • Organisasi sama
  • Afiliasi tidak diketahui
  • Garis lebih tebal = lebih banyak artikel bersama · lingkaran lebih besar = lebih banyak artikel
Tampilkan sebagai tabel
Rekan penulisOrganisasiArtikel bersama
Anis RosyidahJakarta State Polytechnic6
Oky Bima PutraJakarta State Polytechnic2
Ilham Dwiputra RamadhanJakarta State Polytechnic2
Tree Irma DindaJakarta State Polytechnic2
Jasun Widiana PutraJakarta State Polytechnic1
Hanif Satria AjiJakarta State Polytechnic1
Mayda PahinggisJakarta State Polytechnic1
Mutia Hanuun Ufaira AkbarJakarta State Polytechnic1
Erlina YanuariniAfiliasi tidak diketahui1

Afiliasi berasal dari OpenAlex; metadata OAI-PMH jurnal tidak memuatnya. Penulis tanpa ID OpenAlex dicocokkan berdasarkan nama, sehingga dua orang bisa tergabung atau satu orang bisa terpisah.

Sumber metadata: OAI-PMH (metadata jurnal) https://ojs2.pnb.ac.id/index.php/LOGIC/oai, pertama di-harvest 19 Nov 2026, terakhir terlihat 19 Nov 2026.
Metadata asli (oai_dc)
<oai_dc:dc xmlns="http://www.openarchives.org/OAI/2.0/" xmlns:dc="http://purl.org/dc/elements/1.1/" xmlns:oai_dc="http://www.openarchives.org/OAI/2.0/oai_dc/" xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:schemaLocation="http://www.openarchives.org/OAI/2.0/oai_dc/  http://www.openarchives.org/OAI/2.0/oai_dc.xsd">
	<dc:title xml:lang="en-US">The Effect of Non-Excusable Delay Factors on The Completion of Building Construction Projects</dc:title>
	<dc:creator>Dunaufal, Alvin</dc:creator>
	<dc:creator>Sucita, I Ketut</dc:creator>
	<dc:creator>Saputra, Jonathan</dc:creator>
	<dc:subject xml:lang="en-US">Delay</dc:subject>
	<dc:subject xml:lang="en-US">Non-Excusable Delay</dc:subject>
	<dc:subject xml:lang="en-US">Contractor</dc:subject>
	<dc:subject xml:lang="en-US">Construction Project</dc:subject>
	<dc:description xml:lang="en-US">A problem that often occurs in construction projects is the delay in the implementation process. Various factors cause the delay, but in developing countries such as Indonesia, the dominant delay occurs because the implementing contractor causes it for unforgivable reasons (non-excusable delay). This study aims to determine the influence of the non-excusable delay parameter and the relationship between these factors. The research is quantitative with data collection techniques in the form of unstructured interviews, field observations, and surveys using research questionnaires with the number of respondents obtained as many as 33 people consisting of the owner, construction management consultant, quantity surveyor consultant, and ends with confirmation of the results. Research on the implementing contractor. Data analysis was performed using multiple linear regression analysis. The test results of multiple linear regression analysis show that the non-excusable delay factor can significantly affect the completion of construction projects. The influence of each element is 0.434 units for the lack of contractor competence, 0.067 units for inappropriate implementation planning, and -0.097 for inefficient field management units. And simultaneously, these three factors can significantly increase the project delay value index.</dc:description>
	<dc:publisher xml:lang="en-US">Unit Publikasi Ilmiah, P3M, Politeknik Negeri Bali</dc:publisher>
	<dc:date>2023-07-31</dc:date>
	<dc:type>info:eu-repo/semantics/article</dc:type>
	<dc:type>info:eu-repo/semantics/publishedVersion</dc:type>
	<dc:format>application/pdf</dc:format>
	<dc:identifier>https://ojs2.pnb.ac.id/index.php/LOGIC/article/view/649</dc:identifier>
	<dc:identifier>10.31940/logic.v23i2.96-103</dc:identifier>
	<dc:source xml:lang="en-US"> Logic : Jurnal Rancang Bangun dan Teknologi; Vol. 23 No. 2 (2023): July; 96-103</dc:source>
	<dc:source>2580-5649</dc:source>
	<dc:source>1412-114X</dc:source>
	<dc:source>10.31940/logic.v23i2</dc:source>
	<dc:language>eng</dc:language>
	<dc:relation>https://ojs2.pnb.ac.id/index.php/LOGIC/article/view/649/632</dc:relation>
	<dc:rights xml:lang="en-US">Copyright (c) 2023  Logic : Jurnal Rancang Bangun dan Teknologi</dc:rights>
	<dc:rights xml:lang="en-US">https://scholar.google.co.id/citations?user=smBuD3gAAAAJ&amp;hl=id</dc:rights>
</oai_dc:dc>