Planning for Maintenance and Repair of Continuous Ship Unloader Using the IRRO Method

Logic: Jurnal Rancang Bangun dan Teknologi · Vol. 21 No. 1 (2021) · hlm. 52–63

DOI
10.31940/logic.v21i1.2383
ISSN
2580-5649, 1412-114X
Terbit
2021-03-30
Penerbit
Pusat Penelitian dan Pengabdian kepada Masyarakat (P3M) Politeknik Negeri Bali
Bahasa
eng

Abstrak

The problem faced is damage, especially to the screw conveyor from the Continuous Ship Unloader (CSU) as a dry bulk material transfer equipment (phosphate rock) which is taken from the ship's hold which is flowed by a screw conveyor followed by the belt conveyor to the material warehouse to be processed into a type of fertilizer. The purpose of planning is to obtain a schedule and estimated cost of maintenance and repair of CSU for the period 2022 to 2025, and to obtain the ratio of maintenance-repair costs to the profit of the machine. Planning methods uses the IRRO (Inspection, Replace, Repair, and Overhoul) method include data collection of machine maintenance history and component breakdowns, checking CSU specifications, making a list of component life predictions and component prices, predicting costs and duration of component dissasembly, screw conveyor repair, maintenance and repair scheduling, and maintenance and repair cost estimates. The real results of planning in the form of a maintenance and repair schedule for the period of 2022 to 2025; maintenance and repair costs respectively for the years 2022 to 2025 are IDR 136,873,000; IDR 335,986,000; IDR 160,687,000; and IDR 464,733,000; and the ratio between maintenance costs to profit for the years 2022 to 2025 is 0.51, 1.22, 0.57, and 1.63 which means the machine is still fit for use without the need for refurbishment because it is still prospective.

Jaringan kolaborasi para penulis

40 penulis · 118 tautan kepenulisan bersama · 28 lintas organisasi · menampilkan 40 yang paling banyak terhubung

Arahkan kursor atau ketuk sebuah nama untuk menyorot rekan penulisnya. Klik dua kali untuk membuka halaman penulis.

  • Politeknik Negeri Malang
  • University of Sarjanawiyata Tamansiswa
  • Politeknik Pertanian Negeri Pangkajene Kepulauan
  • Politeknik Negeri Semarang
  • Lambung Mangkurat University
  • Jakarta State Polytechnic
  • University of Technology Malaysia
  • Afiliasi tidak diketahui
  • Organisasi berbeda
  • Organisasi sama
  • Afiliasi tidak diketahui
  • Garis lebih tebal = lebih banyak artikel bersama · lingkaran lebih besar = lebih banyak artikel
Tampilkan sebagai tabel
Rekan penulisOrganisasiArtikel bersama
Nila AliaPoliteknik Negeri Malang3
Hangga WicaksonoPoliteknik Negeri Malang2
Nanang QosimPoliteknik Negeri Malang2
Am. MufarrihPoliteknik Negeri Malang2
Zakki Fuadi EmzainPoliteknik Negeri Malang2
Muslimin MusliminJakarta State Polytechnic2
Muhammad RiyadiPoliteknik Pertanian Negeri Pangkajene Kepulauan1
Irawan IlhamPoliteknik Pertanian Negeri Pangkajene Kepulauan1
Eko Sulkhany YuliantoUniversity of Sarjanawiyata Tamansiswa1
Tito Aji MilleniawanUniversity of Sarjanawiyata Tamansiswa1
Mohammad Ahyar Syafwan LysanderUniversity of Sarjanawiyata Tamansiswa1
Shahnur Al-HafriUniversity of Sarjanawiyata Tamansiswa1
Didik SubiyantoUniversity of Sarjanawiyata Tamansiswa1
Tri Aji PurnomoUniversity of Sarjanawiyata Tamansiswa1
Fina Andika Frida AstutiPoliteknik Negeri Malang1
Ali Sai’inPoliteknik Negeri Semarang1
Ratna MonasariPoliteknik Negeri Malang1
Sudarmadji .Afiliasi tidak diketahui1
Bambang IrawanLambung Mangkurat University1
Anggit MurdaniPoliteknik Negeri Malang1
Andhika Erlangga Setiawan PutraPoliteknik Negeri Malang1
Sza Sya Monica ValeriaPoliteknik Negeri Malang1
Rico Wahyu PratamaPoliteknik Negeri Malang1
Zakiyah AmaliaPoliteknik Negeri Malang1
Tri Setyo Aji CahyonoPoliteknik Negeri Malang1
Fica Aida Nadhifatul AiniPoliteknik Negeri Malang1
Aini Zuhra Binti Abdul KadirUniversity of Technology Malaysia1
Bayu PranotoPoliteknik Negeri Malang1
Muhammad Naufal Abiyyi HutagalungPoliteknik Negeri Malang1
Firman DwiyantoPoliteknik Negeri Malang1
Dadang KurniawanPoliteknik Negeri Malang1
Septyana RiskitasariPoliteknik Negeri Malang1
Kris WitonoPoliteknik Negeri Malang1
Talifatim MachfurohPoliteknik Negeri Malang1

Afiliasi berasal dari OpenAlex; metadata OAI-PMH jurnal tidak memuatnya. Penulis tanpa ID OpenAlex dicocokkan berdasarkan nama, sehingga dua orang bisa tergabung atau satu orang bisa terpisah.

Sumber metadata: OAI-PMH (metadata jurnal) https://ojs.pnb.ac.id/index.php/LOGIC/oai, pertama di-harvest 19 Nov 2026, terakhir terlihat 19 Nov 2026.
Metadata asli (oai_dc)
<oai_dc:dc xmlns="http://www.openarchives.org/OAI/2.0/" xmlns:dc="http://purl.org/dc/elements/1.1/" xmlns:oai_dc="http://www.openarchives.org/OAI/2.0/oai_dc/" xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:schemaLocation="http://www.openarchives.org/OAI/2.0/oai_dc/  http://www.openarchives.org/OAI/2.0/oai_dc.xsd">
	<dc:title xml:lang="en-US">Planning for Maintenance and Repair of Continuous Ship Unloader Using the IRRO Method</dc:title>
	<dc:creator>Hadi, Syamsul</dc:creator>
	<dc:creator>Azis, Alfarizi Al</dc:creator>
	<dc:creator>Viyus, Vinan</dc:creator>
	<dc:creator>Puspitasari, Etik</dc:creator>
	<dc:creator>Firdaus, Ahmad Hanif</dc:creator>
	<dc:creator>Setiawan, Andri</dc:creator>
	<dc:description xml:lang="en-US">The problem faced is damage, especially to the screw conveyor from the Continuous Ship Unloader (CSU) as a dry bulk material transfer equipment (phosphate rock) which is taken from the ship's hold which is flowed by a screw conveyor followed by the belt conveyor to the material warehouse to be processed into a type of fertilizer. The purpose of planning is to obtain a schedule and estimated cost of maintenance and repair of CSU for the period 2022 to 2025, and to obtain the ratio of maintenance-repair costs to the profit of the machine. Planning methods uses the IRRO (Inspection, Replace, Repair, and Overhoul) method include data collection of machine maintenance history and component breakdowns, checking CSU specifications, making a list of component life predictions and component prices, predicting costs and duration of component dissasembly, screw conveyor repair, maintenance and repair scheduling, and maintenance and repair cost estimates. The real results of planning in the form of a maintenance and repair schedule for the period of 2022 to 2025; maintenance and repair costs respectively for the years 2022 to 2025 are IDR 136,873,000; IDR 335,986,000; IDR 160,687,000; and IDR 464,733,000; and the ratio between maintenance costs to profit for the years 2022 to 2025 is 0.51, 1.22, 0.57, and 1.63 which means the machine is still fit for use without the need for refurbishment because it is still prospective.</dc:description>
	<dc:publisher xml:lang="en-US">Pusat Penelitian dan Pengabdian kepada Masyarakat (P3M) Politeknik Negeri Bali</dc:publisher>
	<dc:date>2021-03-30</dc:date>
	<dc:type>info:eu-repo/semantics/article</dc:type>
	<dc:type>info:eu-repo/semantics/publishedVersion</dc:type>
	<dc:type xml:lang="en-US">Peer-reviewed Article</dc:type>
	<dc:format>application/pdf</dc:format>
	<dc:identifier>https://ojs.pnb.ac.id/index.php/LOGIC/article/view/2383</dc:identifier>
	<dc:identifier>10.31940/logic.v21i1.2383</dc:identifier>
	<dc:source xml:lang="en-US">Logic : Jurnal Rancang Bangun dan Teknologi; Vol 21 No 1 (2021): March; 52-63</dc:source>
	<dc:source>2580-5649</dc:source>
	<dc:source>1412-114X</dc:source>
	<dc:source>10.31940/logic.v21i1</dc:source>
	<dc:language>eng</dc:language>
	<dc:relation>https://ojs.pnb.ac.id/index.php/LOGIC/article/view/2383/1664</dc:relation>
	<dc:rights xml:lang="en-US">Copyright (c) 2021 Logic : Jurnal Rancang Bangun dan Teknologi</dc:rights>
</oai_dc:dc>