EVALUATION OF PROJECT IMPLEMENTATION PERFORMANCE WITH EARNED VALUE METHODS

Logic: Jurnal Rancang Bangun dan Teknologi · Vol. 18 No. 2 (2018) · hlm. 98–108

DOI
10.31940/logic.v18i2.978
ISSN
2580-5649, 1412-114X
Terbit
2018-07-30
Penerbit
Pusat Penelitian dan Pengabdian kepada Masyarakat (P3M) Politeknik Negeri Bali
Bahasa
eng

Abstrak

Planning and controlling the execution of a project is part of the overall construction project management. In addition to assessment in terms of quality, achievement of a project can be assessed in terms of cost and time. Earned value method is the integrated cost control and project schedule. This method provides project performance status information in terms of cost and time in the project reporting period. In evaluating the performance of the development project of Villa Shimamoto Ryosaku, the performance of the cost aspect shows the savings from the plan, This is shown from the value Cost Performance Index (CPI) > 1 On monthly reporting3 = 1.39, the monthly 6 = 1.97, and the monthly 11 = 1.73 While the performance of the schedule aspect shows the delay of the plan, this is shown from the value Schedule Performance Index (SPI) < 1 on monthly reporting 3= 0.79,the monthly 6 = 0.93, and the monthly 11 = 0.94. Estimate Temporary Cost (ETC) is Rp 480,175,422.16, and Estimation At Completion (EAS) is Rp2,026,445,457.16, while Budgeted At Completion (BAC) is Rp3,502,000,000.00 so get Variance at Compeltioan (VAC) is Rp1,409,621,615.49 and Estimation Temporary Schedule (ETS) is 3.2 month, and Estimation At Schedul (EAS) is 14.2 Month while the time specified in the contract during 14 month, So the project is delayed during 0.2 month (1 week).

Jaringan kolaborasi para penulis

30 penulis · 69 tautan kepenulisan bersama

Arahkan kursor atau ketuk sebuah nama untuk menyorot rekan penulisnya. Klik dua kali untuk membuka halaman penulis.

  • Politeknik Negeri Bali
  • Afiliasi tidak diketahui
  • Organisasi berbeda
  • Organisasi sama
  • Afiliasi tidak diketahui
  • Garis lebih tebal = lebih banyak artikel bersama · lingkaran lebih besar = lebih banyak artikel
Tampilkan sebagai tabel
Rekan penulisOrganisasiArtikel bersama
I Made TapayasaPoliteknik Negeri Bali4
I Made Anom SantianaPoliteknik Negeri Bali4
I Wayan SuasiraPoliteknik Negeri Bali4
I Nengah Darma SusilaPoliteknik Negeri Bali3
I Made SudiarsaPoliteknik Negeri Bali2
Ida Bagus WirahajiPoliteknik Negeri Bali2
I Nyoman SutapaPoliteknik Negeri Bali2
I Wayan WiragaAfiliasi tidak diketahui2
I G A G Surya NegaraAfiliasi tidak diketahui2
Ni Kadek Ayu Trisna DewiPoliteknik Negeri Bali1
I Nyoman Sedana TriadiPoliteknik Negeri Bali1
I Nyoman ArdikaPoliteknik Negeri Bali1
I Putu Agus KrisnadinataPoliteknik Negeri Bali1
I Wayan AryaAfiliasi tidak diketahui1
I Nyoman SutarnaPoliteknik Negeri Bali1
I Wayan Darya SupartaPoliteknik Negeri Bali1
I Nyoman RamiaPoliteknik Negeri Bali1
Denin Lintang TuhujatiPoliteknik Negeri Bali1
I Made Anom SantianaAfiliasi tidak diketahui1
I Putu Rian Surya WigunaAfiliasi tidak diketahui1
I Komang SudiartaPoliteknik Negeri Bali1
I Nyoman SuardikaPoliteknik Negeri Bali1
Kadek Adi SuryawanPoliteknik Negeri Bali1
I Made Suardana KaderPoliteknik Negeri Bali1
I Made Tapa YasaPoliteknik Negeri Bali1
Putu Dana Pariawan SalainPoliteknik Negeri Bali1
I Wayan SudiasaAfiliasi tidak diketahui1

Afiliasi berasal dari OpenAlex; metadata OAI-PMH jurnal tidak memuatnya. Penulis tanpa ID OpenAlex dicocokkan berdasarkan nama, sehingga dua orang bisa tergabung atau satu orang bisa terpisah.

Sumber metadata: OAI-PMH (metadata jurnal) https://ojs.pnb.ac.id/index.php/LOGIC/oai, pertama di-harvest 19 Nov 2026, terakhir terlihat 19 Nov 2026.
Metadata asli (oai_dc)
<oai_dc:dc xmlns="http://www.openarchives.org/OAI/2.0/" xmlns:dc="http://purl.org/dc/elements/1.1/" xmlns:oai_dc="http://www.openarchives.org/OAI/2.0/oai_dc/" xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:schemaLocation="http://www.openarchives.org/OAI/2.0/oai_dc/  http://www.openarchives.org/OAI/2.0/oai_dc.xsd">
	<dc:title xml:lang="en-US">EVALUATION OF PROJECT IMPLEMENTATION PERFORMANCE WITH EARNED VALUE METHODS</dc:title>
	<dc:creator>Sudiarsa, Made</dc:creator>
	<dc:creator>Wibawa, I Gede Sastra</dc:creator>
	<dc:creator>Sutapa, I Ketut</dc:creator>
	<dc:description xml:lang="en-US">Planning and controlling the execution of a project is part of the overall construction project management. In addition to assessment in terms of quality, achievement of a project can be assessed in terms of cost and time. Earned value method is the integrated cost control and project schedule. This method provides project performance status information in terms of cost and time in the project reporting period. In evaluating the performance of the development project of Villa Shimamoto Ryosaku, the performance of the cost aspect shows the savings from the plan, This is shown from the value Cost Performance Index (CPI) &amp;gt; 1 On monthly reporting3 = 1.39, the monthly 6 = 1.97, and the monthly 11 = 1.73 While the performance of the schedule aspect shows the delay of the plan, this is shown from the value Schedule Performance Index (SPI) &amp;lt; 1 on monthly reporting 3= 0.79,the monthly 6 = 0.93, and the monthly 11 = 0.94. Estimate Temporary Cost (ETC) is Rp 480,175,422.16, and &amp;nbsp;Estimation At &amp;nbsp;Completion (EAS) is &amp;nbsp;Rp2,026,445,457.16, while Budgeted At &amp;nbsp;Completion (BAC) is &amp;nbsp;Rp3,502,000,000.00 so get Variance at Compeltioan (VAC) is&amp;nbsp;&amp;nbsp; Rp1,409,621,615.49 and Estimation Temporary Schedule (ETS) is 3.2 month, and Estimation At Schedul (EAS) is 14.2 Month while the time specified in the contract during 14 month, So the project is delayed during 0.2 month (1 week).</dc:description>
	<dc:publisher xml:lang="en-US">Pusat Penelitian dan Pengabdian kepada Masyarakat (P3M) Politeknik Negeri Bali</dc:publisher>
	<dc:date>2018-07-30</dc:date>
	<dc:type>info:eu-repo/semantics/article</dc:type>
	<dc:type>info:eu-repo/semantics/publishedVersion</dc:type>
	<dc:type xml:lang="en-US">Peer-reviewed Article</dc:type>
	<dc:format>application/pdf</dc:format>
	<dc:identifier>https://ojs.pnb.ac.id/index.php/LOGIC/article/view/978</dc:identifier>
	<dc:identifier>10.31940/logic.v18i2.978</dc:identifier>
	<dc:source xml:lang="en-US">Logic : Jurnal Rancang Bangun dan Teknologi; Vol 18 No 2 (2018): July; 98-108</dc:source>
	<dc:source>2580-5649</dc:source>
	<dc:source>1412-114X</dc:source>
	<dc:source>10.31940/logic.v18i2</dc:source>
	<dc:language>eng</dc:language>
	<dc:relation>https://ojs.pnb.ac.id/index.php/LOGIC/article/view/978/780</dc:relation>
	<dc:rights xml:lang="en-US">Copyright (c) 2018 LOGIC Jurnal Rancang Bangun dan Teknologi</dc:rights>
</oai_dc:dc>