TINJAUAN MANAJEMEN WAKTU MENGGUNAKAN METODE ACTIVITY ON NODE (AON) (Studi Kasus: Gedung Ruang Tunggu Terminal Type A Baruga)

Media Konstruksi : Jurnal Ilmiah Teknik Sipil · Vol. 1 No. 2 (2016)

DOI
10.33772/jmk.v1i2.27180
ISSN
2503-2712
Published
2016-07-01
Publisher
PRODI D3 TEKNIK SIPIL
Language
eng

Abstract

Abstract The purpose of this research is determining critis activity for the project of terminal building and knowing the diference o time and cost between project planning by contractor and researcher using AON method. Activity On Node (AON) method is the activity of the project planning which performend by text box. The correlation and linking of each tex box, showed through the lines of its AON links.Data collection is doing by comparing the activites and cost of the project from contractor. Data contais project schedule and duration of each activity. The activites followed by abalize the data and counting the cost of the project using its method. As the result of this research there are differences between the project contractor and researcher. It was 8 days faster by counting the project using this method and expenditure cost by Rp.1.903.295.294,98 from real cost Rp.2.090.328.612,28. It means that the project can save the cost around Rp.187.033.371,30 Abstrak Penulisan tugas akhir ini bertujuan untuk menentukan kegiatan kritis pada proyek pembangunan terminal dan mengetahui perbedaan dalam penentuan waktu kritis serta biaya yang digunakan antara pihak kontraktor dan peneliti dengan menggunakan metode Activity On Node (AON).Penelitian ini dilakukan dengan menggunakan Metode Activity On Node (AON). AON adalah sebuah aktifitas yang ditampilkan oleh sebuah kotak. Keterkaitan atau hubungan antara aktivitas-aktivitas yang ditunjukan oleh garis-garis antara kotak pada jaringan AON.Pengumpulan data yang dilakukan yaitu dengan mendapat durasi masing-masing kegiatan proyek dari kontrak. Setelah mendapatkan durasi masing-masing kegiatan proyek tersebut, maka langkah selanjutnya adalah melakukan pengolahan data. Pengolahan data dilakukan dengan menggunakan metode AON (Activity On Node) dilanjutkan dengan perhitungan seberapa besar biaya yang keluar setelah menggunakan metode AON. Dari hasil penelitian yang di peroleh, terdapat perbedaan lamanya proyek selesai antara perencanaan proyek dari

Collaboration network of the authors

37 authors · 112 co-authorship links · 4 across different organisations

Hover or tap a name to highlight its co-authors. Double-click to open the author's page.

  • Universitas Sembilanbelas November Kolaka
  • Universitas Halu Oleo
  • Affiliation unknown
  • Different organisations
  • Same organisation
  • Affiliation unknown
  • Thicker line = more joint articles · bigger circle = more articles
Show as table
Co-authorOrganisationJoint articles
Umran SaritaAffiliation unknown4
Fathur Rahman RustanUniversitas Sembilanbelas November Kolaka3
Romy S. E. TamburakaAffiliation unknown3
Baso MursidiAffiliation unknown2
Mappa NashrunAffiliation unknown2
Muhammad Syarif PrasetiaAffiliation unknown2
Try Sugiyarto SoeparyantoUniversitas Halu Oleo2
Billing BillingAffiliation unknown1
Anafi MinmahddunUniversitas Halu Oleo1
Putra Dwijanto MangokiAffiliation unknown1
sulha sulhaAffiliation unknown1
Azman AzmanAffiliation unknown1
Wayan MustikaAffiliation unknown1
Sabil SabilAffiliation unknown1
Veny AnjarwatiAffiliation unknown1
La Ode Muhamad Nurrakhmad ArsyadUniversitas Halu Oleo1
Imam MulyonoAffiliation unknown1
Agusti FaturrahmanAffiliation unknown1
Ainussalbi Al IkhsanAffiliation unknown1
Arung PatandiananAffiliation unknown1
Ferdinal FerdinalAffiliation unknown1
Jusmiati JusmiatiAffiliation unknown1
Muh. Rizal AlhasAffiliation unknown1
Muh. Ariyan Sukri AnggaraAffiliation unknown1
Fahril AlwanAffiliation unknown1
Laode HajiAffiliation unknown1
Lucky LuckyAffiliation unknown1
Zulkarnain ZulkarnainAffiliation unknown1
Reni DarfilunAffiliation unknown1
Awilliambuth AwilliambuthAffiliation unknown1
La Ode Rizki DarmawanAffiliation unknown1
Arman HidayatUniversitas Sembilanbelas November Kolaka1
Muhammad Buttomi MasgodeUniversitas Sembilanbelas November Kolaka1
Iramayanti IramayantiAffiliation unknown1

Affiliations come from OpenAlex; journal OAI-PMH metadata carries none. Authors without an OpenAlex ID are matched by name, which can merge or split people.

Metadata source: OAI-PMH (metadata jurnal) https://ojs.uho.ac.id/index.php/MedKons/oai, first harvested 31 Okt 2026, last seen 1 Nov 2026.
Original metadata (oai_dc)
<oai_dc:dc xmlns="http://www.openarchives.org/OAI/2.0/" xmlns:dc="http://purl.org/dc/elements/1.1/" xmlns:oai_dc="http://www.openarchives.org/OAI/2.0/oai_dc/" xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:schemaLocation="http://www.openarchives.org/OAI/2.0/oai_dc/  http://www.openarchives.org/OAI/2.0/oai_dc.xsd">
	<dc:title xml:lang="en-US">TINJAUAN MANAJEMEN WAKTU MENGGUNAKAN METODE ACTIVITY ON NODE (AON) (Studi Kasus: Gedung Ruang Tunggu Terminal Type A Baruga)</dc:title>
	<dc:creator>Milasari, Milasari</dc:creator>
	<dc:creator>Mas'ud, Fitriah</dc:creator>
	<dc:creator>Mangiri, Aloysius A. Prima</dc:creator>
	<dc:description xml:lang="en-US"> Abstract The purpose of this research is determining critis activity for the project of terminal building and knowing the diference o time and cost between project planning by contractor and researcher using AON method. Activity On Node (AON) method is the activity of the project planning which performend by text box. The correlation and linking of each tex box, showed through the lines of its AON links.Data collection is doing by comparing the activites and cost of the project from contractor. Data contais project schedule and duration of each activity. The activites followed by abalize the data and counting the cost of the project using its method. As the result of this research there are differences between the project contractor and researcher.  It was 8 days faster by counting the project using this method and expenditure cost by Rp.1.903.295.294,98 from real cost  Rp.2.090.328.612,28. It means that the project can save the cost around Rp.187.033.371,30  Abstrak Penulisan tugas akhir ini bertujuan untuk menentukan kegiatan kritis pada proyek pembangunan terminal dan mengetahui perbedaan dalam penentuan waktu kritis serta biaya yang digunakan antara pihak kontraktor dan peneliti dengan menggunakan metode Activity On Node (AON).Penelitian ini dilakukan dengan menggunakan Metode Activity On Node (AON). AON adalah sebuah aktifitas yang ditampilkan oleh sebuah kotak. Keterkaitan atau hubungan antara aktivitas-aktivitas yang ditunjukan oleh garis-garis antara kotak pada jaringan AON.Pengumpulan data yang dilakukan yaitu dengan mendapat durasi masing-masing kegiatan proyek dari kontrak. Setelah mendapatkan durasi masing-masing kegiatan proyek tersebut, maka langkah selanjutnya adalah melakukan pengolahan data. Pengolahan data dilakukan dengan menggunakan metode AON (Activity On Node) dilanjutkan dengan perhitungan seberapa besar biaya yang keluar setelah menggunakan metode AON. Dari hasil penelitian yang di peroleh, terdapat perbedaan lamanya proyek selesai antara perencanaan proyek dari </dc:description>
	<dc:publisher xml:lang="en-US">PRODI D3 TEKNIK SIPIL</dc:publisher>
	<dc:contributor xml:lang="en-US"></dc:contributor>
	<dc:date>2016-07-01</dc:date>
	<dc:type>info:eu-repo/semantics/article</dc:type>
	<dc:type>info:eu-repo/semantics/publishedVersion</dc:type>
	<dc:type xml:lang="en-US">Peer-reviewed Article</dc:type>
	<dc:format>application/pdf</dc:format>
	<dc:identifier>https://ojs.uho.ac.id/index.php/MedKons/article/view/27180</dc:identifier>
	<dc:identifier>10.33772/jmk.v1i2.27180</dc:identifier>
	<dc:source xml:lang="en-US">Media Konstruksi : Jurnal Ilmiah Teknik Sipil; Vol 1, No 2 (2016): MedKons</dc:source>
	<dc:source>2503-2712</dc:source>
	<dc:source>10.33772/jmk.v1i2</dc:source>
	<dc:language>eng</dc:language>
	<dc:relation>https://ojs.uho.ac.id/index.php/MedKons/article/view/27180/15827</dc:relation>
	<dc:rights xml:lang="en-US">Copyright (c) 2022 MEDIA KONSTRUKSI</dc:rights>
</oai_dc:dc>