METODE PELAKSANAAN PEKERJAAN LAPIS PONDASI ATAS (LPA) STUDI KASUS PEKERJAAN JALAN POROS WUNA-LAFINDE JALUR II KABUPATEN MUNA BARAT

Media Konstruksi : Jurnal Ilmiah Teknik Sipil · Vol. 5 No. 2 (2020)

DOI
10.33772/jmk.v5i2.24148
ISSN
2503-2712
Published
2020-07-01
Publisher
PRODI D3 TEKNIK SIPIL
Language
eng

Abstract

Abstract This study aimed at to find out the management problems in material mobilization and time implementation management which were applied to overcoming problems during Top Foundation Layer method implementation for improving Wuna - Lafinde road, line II, in West Muna Regency. S curve of contract document was used in analyzing the time implementation management. Analysis of costs and heavy equipment productivity used in project enforcement namely blending equipment, Wheel Loaders, barges, Excavators, dump trucks in 3.5, ton loads, dump trucks in 10 ton loads, graders, Vibrator Rollers and Water Tank Truck, refers to Minister of Public Works and Public Housing regulation No. 28 of 2016 in Highways Sector.Analysis result showed that management problems in material mobilization were the delayed of contractors in started their work, lack of dump trucks in capacity of 10 tons and the scarcity of dump trucks in 3.5 tons capacity. Time management in overcoming the problem of material mobilization is the contractor have to provide the ready mix materials before entering the first week of the S curve in contract document, add a dump truck in 10 tons capacity and augment a dump truck in 3.5 tons capacity. Abstrak Karya ilmiah ini bertujuan untuk mengetahui permasalahan manajemen dalam mobilisasi material dan manajemen waktu pelaksanaan yang diterapkan dalam mengatasi masalah yang timbul pada saat pelaksanaan pekerjaan lapis pondasi atas pada pekerjaan peningkatan jalan poros Wuna – Lafinde jalur II Kabupaten Muna Barat. Analisis manajemen waktu pelaksanaan menggunakan kurva S dokumen kontrak, Analisis biaya dan produktivitas alat berat yang digunakan dalam pelaksanaan pekerjaan yaitu blending equipment, Wheel Loader, kapal tongkang, Excavator, dump truck 3.5 ton, dump truck 10 ton, Motor Grader, Vibrator Roller dan Water Tank Truck, dengan mengacu pada Peraturan Menteri Pekerjaan Umum dan Perumahan Rakyat No. 28 Tahun 2016 Bidang Binamarga. Hasil analisa menunjukan bahwa permasalahan manajemen pada mobilisasi material yaitu keterlambatan kontraktor pelaksana memulai pekerjaan, kurangnya dump truck kapasitas 10 ton dan kurangnya dump truck kapasitas 3.5 ton. Manajemen waktu dalam mengatasi masalah mobilisasi material yaitu kontraktor pelaksana harus menyediakan ready mix material sebelum masuk minggu pertama kurva S dokumen kontrak, penambahan dump truck kapasitas 10 ton dan penambahan dump truck kapasitas 3.5 ton.

Collaboration network of the authors

40 authors · 177 co-authorship links · 9 across different organisations · showing the 40 most connected

Hover or tap a name to highlight its co-authors. Double-click to open the author's page.

  • Universitas Halu Oleo
  • Universitas Islam Negeri Ar-Raniry
  • Universitas Sembilanbelas November Kolaka
  • Affiliation unknown
  • Different organisations
  • Same organisation
  • Affiliation unknown
  • Thicker line = more joint articles · bigger circle = more articles
Show as table
Co-authorOrganisationJoint articles
sulha sulhaAffiliation unknown13
Nasrul NasrulUniversitas Halu Oleo7
Anafi MinmahddunUniversitas Halu Oleo7
Siti Nurjanah AhmadUniversitas Halu Oleo6
Wayan MustikaAffiliation unknown5
Try Sugiyarto SoeparyantoUniversitas Halu Oleo5
RIdwansyah NuhunAffiliation unknown5
Edward NgiiUniversitas Halu Oleo4
Fitriah FitriahUniversitas Islam Negeri Ar-Raniry4
Fitriah Mas'udAffiliation unknown3
Baso MursidiAffiliation unknown3
Ridwan Syah NuhunUniversitas Halu Oleo3
Sultan Machmud Hasan MasikkiAffiliation unknown3
Joko RaharjoAffiliation unknown2
Mappa NashrunAffiliation unknown2
Mappa NasrunAffiliation unknown2
La Ode Muhammad Al MurshalatAffiliation unknown2
Rudi BalakaUniversitas Halu Oleo2
Adris A. PutraAffiliation unknown2
Adris Ade PutraAffiliation unknown2
Thahir AzikinAffiliation unknown2
Muhamad IrwanAffiliation unknown2
Agustan AgustanUniversitas Halu Oleo2
La Ode Muhamad Nurrakhmad ArsyadUniversitas Halu Oleo2
Fathur Rahman RustanUniversitas Sembilanbelas November Kolaka2
Try SugiyartoAffiliation unknown1
Adrianto YusufAffiliation unknown1
Muhammad Handy Dwi AdityawanAffiliation unknown1
Tuti AlawiaAffiliation unknown1
Wa Ode Aulia Wahyu Permata NatasyaAffiliation unknown1
Mursalim Ninoy La OlaAffiliation unknown1
Hadafia’dy Hadafia’dyAffiliation unknown1
Ainussalbi Al IkhsanAffiliation unknown1
La Ode HajiAffiliation unknown1
Muh. Adya MandaraAffiliation unknown1
Muh. Ibrahim NassaAffiliation unknown1
Evy YusufAffiliation unknown1

Affiliations come from OpenAlex; journal OAI-PMH metadata carries none. Authors without an OpenAlex ID are matched by name, which can merge or split people.

Metadata source: OAI-PMH (metadata jurnal) https://ojs.uho.ac.id/index.php/MedKons/oai, first harvested 31 Okt 2026, last seen 31 Okt 2026.
Original metadata (oai_dc)
<oai_dc:dc xmlns="http://www.openarchives.org/OAI/2.0/" xmlns:dc="http://purl.org/dc/elements/1.1/" xmlns:oai_dc="http://www.openarchives.org/OAI/2.0/oai_dc/" xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:schemaLocation="http://www.openarchives.org/OAI/2.0/oai_dc/  http://www.openarchives.org/OAI/2.0/oai_dc.xsd">
	<dc:title xml:lang="en-US">METODE PELAKSANAAN PEKERJAAN LAPIS PONDASI ATAS (LPA)  STUDI KASUS PEKERJAAN JALAN POROS WUNA-LAFINDE JALUR II KABUPATEN MUNA BARAT</dc:title>
	<dc:creator>Yasir, La Ode</dc:creator>
	<dc:creator>Welendo, La</dc:creator>
	<dc:creator>Sarita, Umran</dc:creator>
	<dc:description xml:lang="en-US"> Abstract This study aimed at to find out the management problems in material mobilization and time implementation management which were applied to overcoming problems during Top Foundation Layer method implementation for improving Wuna - Lafinde road, line II, in West Muna Regency.  S curve of contract document was used in analyzing the time implementation management. Analysis of costs and heavy equipment productivity used in project enforcement namely blending equipment, Wheel Loaders, barges, Excavators, dump trucks in 3.5, ton loads, dump trucks in 10 ton loads, graders, Vibrator Rollers and Water Tank Truck, refers to Minister of Public Works and Public Housing regulation No. 28 of 2016 in Highways Sector.Analysis result showed that management problems in material mobilization were the delayed of contractors in started their work, lack of dump trucks in capacity of 10 tons and the scarcity of dump trucks in 3.5 tons capacity. Time management in overcoming the problem of material mobilization is the contractor have to provide the ready mix materials before entering the first week of the S curve in contract document, add a dump truck in 10 tons capacity and augment a dump truck in 3.5 tons capacity.  Abstrak Karya ilmiah ini bertujuan untuk mengetahui permasalahan  manajemen dalam mobilisasi material dan manajemen waktu pelaksanaan yang diterapkan dalam mengatasi masalah yang timbul pada saat pelaksanaan pekerjaan lapis pondasi atas pada pekerjaan peningkatan jalan  poros Wuna – Lafinde jalur II  Kabupaten Muna Barat. Analisis manajemen waktu pelaksanaan menggunakan  kurva S dokumen kontrak, Analisis biaya dan produktivitas alat berat yang digunakan dalam pelaksanaan pekerjaan yaitu blending equipment, Wheel Loader, kapal tongkang, Excavator, dump truck 3.5 ton, dump truck 10 ton, Motor Grader, Vibrator Roller dan Water Tank Truck, dengan mengacu pada Peraturan Menteri Pekerjaan Umum dan Perumahan Rakyat No. 28 Tahun 2016 Bidang Binamarga. Hasil analisa menunjukan bahwa permasalahan manajemen pada mobilisasi material yaitu keterlambatan kontraktor pelaksana memulai pekerjaan, kurangnya dump truck kapasitas 10 ton dan kurangnya dump truck kapasitas 3.5 ton. Manajemen waktu dalam mengatasi masalah mobilisasi material yaitu kontraktor pelaksana harus menyediakan ready mix material sebelum masuk minggu pertama kurva S dokumen kontrak, penambahan dump truck kapasitas 10 ton dan penambahan dump truck kapasitas 3.5 ton. </dc:description>
	<dc:publisher xml:lang="en-US">PRODI D3 TEKNIK SIPIL</dc:publisher>
	<dc:contributor xml:lang="en-US"></dc:contributor>
	<dc:date>2020-07-01</dc:date>
	<dc:type>info:eu-repo/semantics/article</dc:type>
	<dc:type>info:eu-repo/semantics/publishedVersion</dc:type>
	<dc:type xml:lang="en-US">Peer-reviewed Article</dc:type>
	<dc:format>application/pdf</dc:format>
	<dc:identifier>https://ojs.uho.ac.id/index.php/MedKons/article/view/24148</dc:identifier>
	<dc:identifier>10.33772/jmk.v5i2.24148</dc:identifier>
	<dc:source xml:lang="en-US">Media Konstruksi : Jurnal Ilmiah Teknik Sipil; Vol 5, No 2 (2020): MedKons</dc:source>
	<dc:source>2503-2712</dc:source>
	<dc:source>10.33772/jmk.v5i2</dc:source>
	<dc:language>eng</dc:language>
	<dc:relation>https://ojs.uho.ac.id/index.php/MedKons/article/view/24148/14484</dc:relation>
	<dc:rights xml:lang="en-US">Copyright (c) 2022 MEDIA KONSTRUKSI</dc:rights>
</oai_dc:dc>