Rancangan Pembangkit Listrik Tenaga Mikro Hidro Di Kampung Dongi Kecamatan Nuha

Dinamika : Jurnal Ilmiah Teknik Mesin · Vol. 9 No. 2 (2018) · pp. 37–44

DOI
10.33772/djitm.v9i2.4185
ISSN
2502-3373, 2085-8817
Published
2018-06-04
Publisher
Jurusan Teknik Mesin, Universitas Halu Oleo
Language
eng

Abstract

One solution to solve electrical problems in the Dongi village of Nuha District is the provision of new and renewable energi sources that are environmentally friendly as an alternative to electricity supply. Source of new energi and renewable environmentally friendly in question is Hydro Micro Power Plant. The purpose of this research is to design a PLTMH in Dongi village, Nuha sub-district, East Luwu regency, so that it can solve the electricity problem in this area. The results showed that the components of PLTMH support in Dongi village were dam with dump type with concrete layer, take-up building with debit 12,00 m3 /second and door width of intake 2 unit, Trapezoidal carrier channel from stone pair plastered with discharge of 11.00 m3 /sec and equipped with drainage channels and control boxes and culverts, tranquilizers with construction of pairs of stone plastered with a basin base of corrosion concrete (without reinforcement) waterproof, fast pipe which will be mounted from PVC pipe type with diameter 3 inchi with total length 30 meter, Power House, drainage with bottom width 2 x 4.0 m, water height 1.0 m, and length 15 m, Turbine Cross-flow with turbine specification Age wear; at least 10 years, Reliability; 300 hours per year, Overhaul; 3 years, bearing, water seal, belt, Efficiency at least 55%, Casing does not leak, Asynchronous Generator with type specification: Induction Motor As Generator, horizontal axle, foot mounted, TECO or equivalent, Double Bearing, power rating: 40 hp, 30 kW, 3 phase, 50 Hz, 220/380 V, operational rating: continous duty, warranty efficiency: 87%, 4 pole pairs, Control system uses load settings so that the amount of power generator output is always equal to load, and Power distribution network is designed using NYY wire with pole in the form of wooden pole. Keywords: Micro hydro, Weir, Turbine, Asynchronous generator

Collaboration network of the authors

11 authors · 17 co-authorship links

Hover or tap a name to highlight its co-authors. Double-click to open the author's page.

  • Universitas Muhammadiyah Parepare
  • Affiliation unknown
  • Different organisations
  • Same organisation
  • Affiliation unknown
  • Thicker line = more joint articles · bigger circle = more articles
Show as table
Co-authorOrganisationJoint articles
Aziz AsmaunaAffiliation unknown1
Ika SurikaAffiliation unknown1
Muh. Taufiq MangkaliAffiliation unknown1
Jasman JasmanUniversitas Muhammadiyah Parepare1
Irmansyah IrmansyahAffiliation unknown1
Setyo WardoyoAffiliation unknown1
Burhanuddin BurhanuddinAffiliation unknown1
Dahlia LaponduAffiliation unknown1
Roslan RoslanAffiliation unknown1

Affiliations come from OpenAlex; journal OAI-PMH metadata carries none. Authors without an OpenAlex ID are matched by name, which can merge or split people.

Metadata source: OAI-PMH (metadata jurnal) https://ojs.uho.ac.id/index.php/dinamika/oai, first harvested 31 Okt 2026, last seen 31 Okt 2026.
Original metadata (oai_dc)
<oai_dc:dc xmlns="http://www.openarchives.org/OAI/2.0/" xmlns:dc="http://purl.org/dc/elements/1.1/" xmlns:oai_dc="http://www.openarchives.org/OAI/2.0/oai_dc/" xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:schemaLocation="http://www.openarchives.org/OAI/2.0/oai_dc/  http://www.openarchives.org/OAI/2.0/oai_dc.xsd">
	<dc:title xml:lang="en-US">Rancangan Pembangkit Listrik Tenaga Mikro Hidro Di Kampung Dongi Kecamatan Nuha</dc:title>
	<dc:creator>Naim, Muhammad</dc:creator>
	<dc:creator>Ristiawan, Ichsan</dc:creator>
	<dc:subject xml:lang="en-US"></dc:subject>
	<dc:subject xml:lang="en-US"></dc:subject>
	<dc:description xml:lang="en-US">One solution to solve electrical problems in the Dongi village of Nuha District is the provision of new and renewable energi sources that are environmentally friendly as an alternative to electricity supply. Source of new energi and renewable environmentally friendly in question is Hydro Micro Power Plant. The purpose of this research is to design a PLTMH in Dongi village, Nuha sub-district, East Luwu regency, so that it can solve the electricity problem in this area. The results showed that the components of PLTMH support in Dongi village were dam with dump type with concrete layer, take-up building with debit 12,00 m3 /second and door width of intake 2 unit, Trapezoidal carrier channel from stone pair plastered with discharge of 11.00 m3 /sec and equipped with drainage channels and control boxes and culverts, tranquilizers with construction of pairs of stone plastered with a basin base of corrosion concrete (without reinforcement) waterproof, fast pipe which will be mounted from PVC pipe type with diameter 3 inchi with total length 30 meter, Power House, drainage with bottom width 2 x 4.0 m, water height 1.0 m, and length 15 m, Turbine Cross-flow with turbine specification Age wear; at least 10 years, Reliability; 300 hours per year, Overhaul; 3 years, bearing, water seal, belt, Efficiency at least 55%, Casing does not leak, Asynchronous Generator with type specification: Induction Motor As Generator, horizontal axle, foot mounted, TECO or equivalent, Double Bearing, power rating: 40 hp, 30 kW, 3 phase, 50 Hz, 220/380 V, operational rating: continous duty, warranty efficiency: 87%, 4 pole pairs, Control system uses load settings so that the amount of power generator output is always equal to load, and Power distribution network is designed using NYY wire with pole in the form of wooden pole. Keywords: Micro hydro, Weir, Turbine, Asynchronous generator</dc:description>
	<dc:publisher xml:lang="en-US">Jurusan Teknik Mesin, Universitas Halu Oleo</dc:publisher>
	<dc:contributor xml:lang="en-US"></dc:contributor>
	<dc:date>2018-06-04</dc:date>
	<dc:type>info:eu-repo/semantics/article</dc:type>
	<dc:type>info:eu-repo/semantics/publishedVersion</dc:type>
	<dc:type xml:lang="en-US"></dc:type>
	<dc:format>application/pdf</dc:format>
	<dc:identifier>https://ojs.uho.ac.id/index.php/dinamika/article/view/4185</dc:identifier>
	<dc:identifier>10.33772/djitm.v9i2.4185</dc:identifier>
	<dc:source xml:lang="en-US">Dinamika : Jurnal Ilmiah Teknik Mesin; Vol 9, No 2 (2018); 37-44</dc:source>
	<dc:source>2502-3373</dc:source>
	<dc:source>2085-8817</dc:source>
	<dc:source>10.33772/djitm.v9i2</dc:source>
	<dc:language>eng</dc:language>
	<dc:relation>https://ojs.uho.ac.id/index.php/dinamika/article/view/4185/3250</dc:relation>
	<dc:rights xml:lang="en-US">Copyright (c) 2018 DINAMIKA – Jurnal Ilmiah Teknik Mesin</dc:rights>
</oai_dc:dc>