Study on the Design and Implementation of BPPT-lock Armored Groin for Sediment Control Structure in Front of Sea Water Intake

Study On The Design And Implementation Of Bppt-Lock Armored Groin For Sediment Control Structure In Front Of Sea Water Intake

Zona Laut Jurnal Inovasi Sains Dan Teknologi Kelautan · Vol. ume No. vember (2023) · hlm. 240–247

DOI
10.62012/zl.v4i3.28244
ISSN
2721-5717, 2747-2124
Terbit
2023-11-09
Penerbit
Departemen Teknik Kelautan Universitas Hasanuddin
Bahasa
en
Lisensi
creativecommons.org/licenses/by/4.0

Abstrak

Inggris

High rate accumulation of sediment materials in front of the sea water intake (SWI) of a petrochemical factory cooling water system has caused high maintenance dredging costs. A study was conducted to identify the pattern and rate of sedimentation and to find an engineering solution that enables controlling sedimentation rate reduction. Based on numerical simulation, it is identified that the existing total rate of sedimentation around the channel in front of the SWI is 50cm/year. Further numerical simulation series revealed an optimum mitigation scenario by the construction of a pair of groin along both sides of the channel in front of the SWI as a sediment control structure. Under this scenario, the average bed level change becomes 0.10 cm/year and the maximum value of the bed level change is around 24.96 cm/year. A BPPT-lock armored rubble mound-type structure was designed for this sediment control groin by considering its feasibility, ease of construction, and local availability of structure materials. BPPT-lock is selected due to its high hydraulic stability (KD) of 17 for the trunk application and 13 for the head application. It is found that about twenty-five percent more armor unit numbers were required at the final stage of construction compared to the designed one. The actual method of armor unit placement and arrangement during construction is considered the main cause of this difference. In this case, the calculation was designed for random placement, but the actual construction was in uniform placement. To provide economical insight, a calculation was made to compare the construction budget requirement between this constructed groin armored with BPPT-lock and if the same structure armored with tetrapod. The calculation result shows that BPPT-lock armor units required 64% less budget compared to the tetrapod.

Bahasa Indonesia

High rate accumulation of sediment materials in front of the sea water intake (SWI) of a petrochemical factory cooling water system has caused high maintenance dredging costs. A study was conducted to identify the pattern and rate of sedimentation and to find an engineering solution that enables controlling sedimentation rate reduction. Based on numerical simulation, it is identified that the existing total rate of sedimentation around the channel in front of the SWI is 50cm/year. Further numerical simulation series revealed an optimum mitigation scenario by the construction of a pair of groin along both sides of the channel in front of the SWI as a sediment control structure. Under this scenario, the average bed level change becomes 0.10 cm/year and the maximum value of the bed level change is around 24.96 cm/year. A BPPT-lock armored rubble mound-type structure was designed for this sediment control groin by considering its feasibility, ease of construction, and local availability of structure materials. BPPT-lock is selected due to its high hydraulic stability (KD) of 17 for the trunk application and 13 for the head application. It is found that about twenty-five percent more armor unit numbers were required at the final stage of construction compared to the designed one. The actual method of armor unit placement and arrangement during construction is considered the main cause of this difference. In this case, the calculation was designed for random placement, but the actual construction was in uniform placement. To provide economical insight, a calculation was made to compare the construction budget requirement between this constructed groin armored with BPPT-lock and if the same structure armored with tetrapod. The calculation result shows that BPPT-lock armor units required 64% less budget compared to the tetrapod.

Kata kunci

Jaringan kolaborasi para penulis

37 penulis · 196 tautan kepenulisan bersama · 7 lintas organisasi

Arahkan kursor atau ketuk sebuah nama untuk menyorot rekan penulisnya. Klik dua kali untuk membuka halaman penulis.

  • National Research and Innovation Agency
  • Indonesian National Institute of Aeronautics and Space
  • Afiliasi tidak diketahui
  • Organisasi berbeda
  • Organisasi sama
  • Afiliasi tidak diketahui
  • Garis lebih tebal = lebih banyak artikel bersama · lingkaran lebih besar = lebih banyak artikel
Tampilkan sebagai tabel
Rekan penulisOrganisasiArtikel bersama
Aloysius Bagyo WidagdoNational Research and Innovation Agency5
Khusnul Setia WardaniNational Research and Innovation Agency4
Tjahjono PrijambodoAfiliasi tidak diketahui2
Khusnul Setia WardaniAfiliasi tidak diketahui2
Wahyu HendriyonoAfiliasi tidak diketahui2
Tjahjono PrijambodoNational Research and Innovation Agency2
Wahyu HendriyonoNational Research and Innovation Agency2
Hanah KhoirunnisaNational Research and Innovation Agency2
SurantoAfiliasi tidak diketahui2
Ika Sukma WulandariNational Research and Innovation Agency2
Shafan A. AziizNational Research and Innovation Agency2
Yofan T.D. HaritaNational Research and Innovation Agency2
Affandy HamidNational Research and Innovation Agency2
Ahmad ShodikinAfiliasi tidak diketahui1
Muh Alfan SantosoAfiliasi tidak diketahui1
Tjahyono PriambodoAfiliasi tidak diketahui1
Maria Noosa AirawatiAfiliasi tidak diketahui1
Hamzah Haru Radityo SuharyantoNational Research and Innovation Agency1
Reno Arief RachmanNational Research and Innovation Agency1
Fajar YuliantoIndonesian National Institute of Aeronautics and Space1
Ibnu FauziNational Research and Innovation Agency1
Nofika Cahyani PutriNational Research and Innovation Agency1
Dhedy Husada Fadjar PerdanaNational Research and Innovation Agency1

Afiliasi berasal dari OpenAlex; metadata OAI-PMH jurnal tidak memuatnya. Penulis tanpa ID OpenAlex dicocokkan berdasarkan nama, sehingga dua orang bisa tergabung atau satu orang bisa terpisah.

Sumber metadata: OAI-PMH (metadata jurnal) https://journal.unhas.ac.id/index.php/zonalaut/oai, pertama di-harvest 2 Nov 2026, terakhir terlihat 15 Nov 2026.
Metadata asli (oai_dc)
<oai_dc:dc xmlns="http://www.openarchives.org/OAI/2.0/" xmlns:dc="http://purl.org/dc/elements/1.1/" xmlns:oai_dc="http://www.openarchives.org/OAI/2.0/oai_dc/" xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:schemaLocation="http://www.openarchives.org/OAI/2.0/oai_dc/  http://www.openarchives.org/OAI/2.0/oai_dc.xsd">
	<dc:title xml:lang="en">Study on the Design and Implementation of BPPT-lock Armored Groin for Sediment Control Structure in Front of Sea Water Intake</dc:title>
	<dc:title xml:lang="id">Study On The Design And Implementation Of Bppt-Lock Armored Groin For Sediment Control Structure In Front Of Sea Water Intake</dc:title>
	<dc:creator xml:lang="en">Firmansyah, Raka</dc:creator>
	<dc:creator xml:lang="en">Jauzi, Muhammad Zuhdan</dc:creator>
	<dc:creator xml:lang="en">Istiyanto, Dinar Catur</dc:creator>
	<dc:creator xml:lang="en">Subarkah, Aris</dc:creator>
	<dc:creator xml:lang="en">Sujoko, Sungsang Urip</dc:creator>
	<dc:creator xml:lang="en">Wibowo, Mardi</dc:creator>
	<dc:creator xml:lang="en">Yuniardi, Rizaldi Caesar</dc:creator>
	<dc:creator xml:lang="id">Firmansyah, Raka</dc:creator>
	<dc:creator xml:lang="id">Jauzi, Muhammad Zuhdan</dc:creator>
	<dc:creator xml:lang="id">Istiyanto, Dinar Catur</dc:creator>
	<dc:creator xml:lang="id">Subarkah, Aris</dc:creator>
	<dc:creator xml:lang="id">Sujoko, Sungsang Urip</dc:creator>
	<dc:creator xml:lang="id">Wibowo, Mardi</dc:creator>
	<dc:creator xml:lang="id">Yuniardi, Rizaldi Caesar</dc:creator>
	<dc:subject xml:lang="en">BPPT-lock, Budget, Design, Groin, Sediment control</dc:subject>
	<dc:subject xml:lang="en">-</dc:subject>
	<dc:description xml:lang="en">High rate accumulation of sediment materials in front of the sea water intake (SWI) of a petrochemical factory cooling water system has caused high maintenance dredging costs. A study was conducted to identify the pattern and rate of sedimentation and to find an engineering solution that enables controlling sedimentation rate reduction. Based on numerical simulation, it is identified that the existing total rate of sedimentation around the channel in front of the SWI is 50cm/year. Further numerical simulation series revealed an optimum mitigation scenario by the construction of a pair of groin along both sides of the channel in front of the SWI as a sediment control structure. Under this scenario, the average bed level change becomes 0.10 cm/year and the maximum value of the bed level change is around 24.96 cm/year. A BPPT-lock armored rubble mound-type structure was designed for this sediment control groin by considering its feasibility, ease of construction, and local availability of structure materials. BPPT-lock is selected due to its high hydraulic stability (KD) of 17 for the trunk application and 13 for the head application. It is found that about twenty-five percent  more armor unit numbers were required at the final stage of construction compared to the designed one. The actual method of armor unit placement and arrangement during construction is considered the main cause of this difference. In this case, the calculation was designed for random placement, but the actual construction was in uniform placement. To provide economical insight, a calculation was made to compare the construction budget requirement between this constructed groin armored with BPPT-lock and if the same structure armored with tetrapod. The calculation result shows that BPPT-lock armor units required 64% less budget compared to the tetrapod.</dc:description>
	<dc:description xml:lang="id">High rate accumulation of sediment materials in front of the sea water intake (SWI) of a petrochemical factory cooling water system has caused high maintenance dredging costs. A study was conducted to identify the pattern and rate of sedimentation and to find an engineering solution that enables controlling sedimentation rate reduction. Based on numerical simulation, it is identified that the existing total rate of sedimentation around the channel in front of the SWI is 50cm/year. Further numerical simulation series revealed an optimum mitigation scenario by the construction of a pair of groin along both sides of the channel in front of the SWI as a sediment control structure. Under this scenario, the average bed level change becomes 0.10 cm/year and the maximum value of the bed level change is around 24.96 cm/year. A BPPT-lock armored rubble mound-type structure was designed for this sediment control groin by considering its feasibility, ease of construction, and local availability of structure materials. BPPT-lock is selected due to its high hydraulic stability (KD) of 17 for the trunk application and 13 for the head application. It is found that about twenty-five percent  more armor unit numbers were required at the final stage of construction compared to the designed one. The actual method of armor unit placement and arrangement during construction is considered the main cause of this difference. In this case, the calculation was designed for random placement, but the actual construction was in uniform placement. To provide economical insight, a calculation was made to compare the construction budget requirement between this constructed groin armored with BPPT-lock and if the same structure armored with tetrapod. The calculation result shows that BPPT-lock armor units required 64% less budget compared to the tetrapod.</dc:description>
	<dc:publisher xml:lang="en">Departemen Teknik Kelautan Universitas Hasanuddin</dc:publisher>
	<dc:date>2023-11-09</dc:date>
	<dc:type>info:eu-repo/semantics/article</dc:type>
	<dc:type>info:eu-repo/semantics/publishedVersion</dc:type>
	<dc:format>application/pdf</dc:format>
	<dc:identifier>https://journal.unhas.ac.id/index.php/zonalaut/article/view/28244</dc:identifier>
	<dc:identifier>10.62012/zl.v4i3.28244</dc:identifier>
	<dc:source xml:lang="en">Zona Laut Jurnal Inovasi Sains Dan Teknologi Kelautan; Volume 4, Number 3, November 2023 Edition; 240-247</dc:source>
	<dc:source xml:lang="id">Zona Laut : Jurnal Inovasi Sains Dan Teknologi  Kelautan; Volume 4, Nomor 3, Edisi November 2023; 240-247</dc:source>
	<dc:source>2721-5717</dc:source>
	<dc:source>2747-2124</dc:source>
	<dc:language>en</dc:language>
	<dc:relation>https://journal.unhas.ac.id/index.php/zonalaut/article/view/28244/10539</dc:relation>
	<dc:rights xml:lang="en">Copyright (c) 2023 Raka Firmansyah, M. Zuhdan Jauzi, Dinar Catur Istiyanto, Aris Subarkah, Sungsang Urip Sujoko, Mardi Wibowo, Rizaldi Caesar Yuniardi</dc:rights>
	<dc:rights xml:lang="en">https://creativecommons.org/licenses/by/4.0</dc:rights>
</oai_dc:dc>