Analysis Of Fbb Block (Fore Bulbous Bow) Scheduling Using The PDM Method

Zona Laut Jurnal Inovasi Sains Dan Teknologi Kelautan · Vol. ume (2025) · hlm. 232–244

DOI
10.62012/zl.vi.44968
ISSN
2721-5717, 2747-2124
Terbit
2025-07-11
Penerbit
Departemen Teknik Kelautan Universitas Hasanuddin
Bahasa
en
Lisensi
creativecommons.org/licenses/by/4.0

Abstrak

Inggris

Shipyards play a direct role in the development of maritime transportation in Indonesia. A shipyard is a special place equipped with facilities to support the process of building, repairing and maintaining ships. Scheduling is an important part of a new ship building project, apart from prioritizing a minimum budget and maximizing project quality. Careful project scheduling planning will support the achievement of production targets, both in quantity and quality. A shipyard in Surabaya must have its own innovation and advantages to face these challenges in order to compete with domestic and foreign shipbuilding companies. Therefore, work scheduling must be prepared using effective and efficient methods. In determining scheduling, there are several influencing factors, such as the number of workers, level of work difficulty, production facilities, and material availability. This research aims to optimize processing time planning for ship X's FBB block (rescheduling) based on various delay factors to obtain the fastest processing time for the production process. The results of accelerating critical activities using the PDM method with the alternative of additional labor are considered more efficient, where the actual duration can be accelerated by 35.6%.

Bahasa Indonesia

Galangan kapal berperan langsung dalam pengembangan transportasi laut di Indonesia. Galangan kapal merupakan tempat khusus yang dilengkapi dengan fasilitas untuk mendukung proses pembangunan, perbaikan, dan perawatan kapal. Penjadwalan merupakan bagian penting dalam suatu proyek pembangunan kapal baru, selain mengutamakan anggaran yang minimal dan memaksimalkan kualitas proyek. Perencanaan penjadwalan proyek yang matang akan mendukung tercapainya target produksi, baik secara kuantitas maupun kualitas. Sebuah galangan kapal di Surabaya harus memiliki inovasi dan keunggulan tersendiri untuk menghadapi tantangan tersebut agar dapat bersaing dengan perusahaan galangan kapal dalam dan luar negeri. Oleh karena itu, penjadwalan pekerjaan harus disusun dengan menggunakan metode yang efektif dan efisien. Dalam menentukan penjadwalan, terdapat beberapa faktor yang mempengaruhi, seperti jumlah tenaga kerja, tingkat kesulitan pekerjaan, fasilitas produksi, dan ketersediaan material. Penelitian ini bertujuan untuk mengoptimalkan perencanaan waktu pengerjaan pada blok FBB kapal X (rescheduling) berdasarkan berbagai faktor keterlambatan untuk mendapatkan waktu pengerjaan proses produksi yang tercepat. Hasil percepatan aktivitas kritis menggunakan metode PDM dengan alternatif penambahan tenaga kerja dinilai lebih efisien, dimana durasi aktual dapat ipercepat 35,6%.

Kata kunci

Jaringan kolaborasi para penulis

15 penulis · 41 tautan kepenulisan bersama

Arahkan kursor atau ketuk sebuah nama untuk menyorot rekan penulisnya. Klik dua kali untuk membuka halaman penulis.

  • Universitas Hang Tuah
  • Afiliasi tidak diketahui
  • Organisasi berbeda
  • Organisasi sama
  • Afiliasi tidak diketahui
  • Garis lebih tebal = lebih banyak artikel bersama · lingkaran lebih besar = lebih banyak artikel
Tampilkan sebagai tabel
Rekan penulisOrganisasiArtikel bersama
Tri Agung KristiyonoUniversitas Hang Tuah3
Tri Agung KristiyonoAfiliasi tidak diketahui2
Muhammad Ridwan EfendyAfiliasi tidak diketahui2
Muhammad Ridwan EfendyUniversitas Hang Tuah2
Danny Arisetya Saputra ArisetyaAfiliasi tidak diketahui1
Akhmad Basuki WidodoAfiliasi tidak diketahui1
Ali AzharUniversitas Hang Tuah1
Akhmad Basuki WidodoUniversitas Hang Tuah1
Danny Arisetya Saputra ArisetyaUniversitas Hang Tuah1
SuharyokoUniversitas Hang Tuah1
Syiam Laksono HarmawantoAfiliasi tidak diketahui1
Syiam Laksono HarmawantoUniversitas Hang Tuah1

Afiliasi berasal dari OpenAlex; metadata OAI-PMH jurnal tidak memuatnya. Penulis tanpa ID OpenAlex dicocokkan berdasarkan nama, sehingga dua orang bisa tergabung atau satu orang bisa terpisah.

Sumber metadata: OAI-PMH (metadata jurnal) https://journal.unhas.ac.id/index.php/zonalaut/oai, pertama di-harvest 2 Nov 2026, terakhir terlihat 15 Nov 2026.
Metadata asli (oai_dc)
<oai_dc:dc xmlns="http://www.openarchives.org/OAI/2.0/" xmlns:dc="http://purl.org/dc/elements/1.1/" xmlns:oai_dc="http://www.openarchives.org/OAI/2.0/oai_dc/" xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:schemaLocation="http://www.openarchives.org/OAI/2.0/oai_dc/  http://www.openarchives.org/OAI/2.0/oai_dc.xsd">
	<dc:title xml:lang="en">Analysis Of Fbb Block (Fore Bulbous Bow) Scheduling Using The PDM Method</dc:title>
	<dc:title xml:lang="id">Analysis Of Fbb Block (Fore Bulbous Bow) Scheduling Using The PDM Method</dc:title>
	<dc:creator xml:lang="en">Amrozi, Akhmad</dc:creator>
	<dc:creator xml:lang="en">Baroroh, Intan</dc:creator>
	<dc:creator xml:lang="id">Amrozi, Akhmad</dc:creator>
	<dc:creator xml:lang="id">Baroroh, Intan</dc:creator>
	<dc:subject xml:lang="en">bulbous bow</dc:subject>
	<dc:subject xml:lang="en">scheduling</dc:subject>
	<dc:subject xml:lang="en">PDM</dc:subject>
	<dc:subject xml:lang="en">analysis of ship building projects</dc:subject>
	<dc:subject xml:lang="id">bulbous bow</dc:subject>
	<dc:subject xml:lang="id">penjadwalan</dc:subject>
	<dc:subject xml:lang="id">PDM</dc:subject>
	<dc:subject xml:lang="id">analisis proyek pembangunan kapal</dc:subject>
	<dc:description xml:lang="en">Shipyards play a direct role in the development of maritime transportation in Indonesia. A shipyard is a special place equipped with facilities to support the process of building, repairing and maintaining ships. Scheduling is an important part of a new ship building project, apart from prioritizing a minimum budget and maximizing project quality. Careful project scheduling planning will support the achievement of production targets, both in quantity and quality. A shipyard in Surabaya must have its own innovation and advantages to face these challenges in order to compete with domestic and foreign shipbuilding companies. Therefore, work scheduling must be prepared using effective and efficient methods. In determining scheduling, there are several influencing factors, such as the number of workers, level of work difficulty, production facilities, and material availability. This research aims to optimize processing time planning for ship X's FBB block (rescheduling) based on various delay factors to obtain the fastest processing time for the production process. The results of accelerating critical activities using the PDM method with the alternative of additional labor are considered more efficient, where the actual duration can be accelerated by 35.6%.</dc:description>
	<dc:description xml:lang="id">Galangan kapal berperan langsung dalam pengembangan transportasi laut di Indonesia. Galangan kapal merupakan tempat khusus yang dilengkapi dengan fasilitas untuk mendukung proses pembangunan, perbaikan, dan perawatan kapal. Penjadwalan merupakan bagian penting dalam suatu proyek pembangunan kapal baru, selain mengutamakan anggaran yang minimal dan memaksimalkan kualitas proyek. Perencanaan penjadwalan proyek yang matang akan mendukung tercapainya target produksi, baik secara kuantitas maupun kualitas. Sebuah galangan kapal di Surabaya harus memiliki inovasi dan keunggulan tersendiri untuk menghadapi tantangan tersebut agar dapat bersaing dengan perusahaan galangan kapal dalam dan luar negeri. Oleh karena itu, penjadwalan pekerjaan harus disusun dengan menggunakan metode yang efektif dan efisien. Dalam menentukan penjadwalan, terdapat beberapa faktor yang mempengaruhi, seperti jumlah tenaga kerja, tingkat kesulitan pekerjaan, fasilitas produksi, dan ketersediaan material. Penelitian ini bertujuan untuk mengoptimalkan perencanaan waktu pengerjaan pada blok FBB kapal X (rescheduling) berdasarkan berbagai faktor keterlambatan untuk mendapatkan waktu pengerjaan proses produksi yang tercepat. Hasil percepatan aktivitas kritis menggunakan metode PDM dengan alternatif penambahan tenaga kerja dinilai lebih efisien, dimana durasi aktual dapat ipercepat 35,6%.</dc:description>
	<dc:publisher xml:lang="en">Departemen Teknik Kelautan Universitas Hasanuddin</dc:publisher>
	<dc:date>2025-07-11</dc:date>
	<dc:type>info:eu-repo/semantics/article</dc:type>
	<dc:type>info:eu-repo/semantics/publishedVersion</dc:type>
	<dc:format>application/pdf</dc:format>
	<dc:identifier>https://journal.unhas.ac.id/index.php/zonalaut/article/view/44968</dc:identifier>
	<dc:identifier>10.62012/zl.vi.44968</dc:identifier>
	<dc:source xml:lang="en">Zona Laut Jurnal Inovasi Sains Dan Teknologi Kelautan; Volume 6, Number 2, July 2025 Edition; 232-244</dc:source>
	<dc:source xml:lang="id">Zona Laut : Jurnal Inovasi Sains Dan Teknologi  Kelautan; Volume 6, Number 2, July 2025 Edition; 232-244</dc:source>
	<dc:source>2721-5717</dc:source>
	<dc:source>2747-2124</dc:source>
	<dc:language>en</dc:language>
	<dc:language>id</dc:language>
	<dc:relation>https://journal.unhas.ac.id/index.php/zonalaut/article/view/44968/13143</dc:relation>
	<dc:rights xml:lang="en">Copyright (c) 2025 Akhmad Amrozi, Intan Baroroh</dc:rights>
	<dc:rights xml:lang="en">https://creativecommons.org/licenses/by/4.0</dc:rights>
</oai_dc:dc>