SCHEDULING ANALYSIS BEDUGUL VILLA CONSTRUCTION PROJECT USING PERT AND CPM METHODS

BAREKENG: Jurnal Ilmu Matematika dan Terapan · Vol. 18 No. 1 (2024) · hlm. 0105–0116

DOI
10.30598/barekengvol18iss1pp0105-0116
ISSN
2615-3017, 1978-7227
Terbit
2024-03-01
Penerbit
PATTIMURA UNIVERSITY
Bahasa
eng
Lisensi
creativecommons.org/licenses/by-sa/4.0

Abstrak

Scheduling in construction projects is necessary so that the planned time to complete the project can be achieved on time. the methods used in optimizing project scheduling are the Project Evaluation Review Technique (PERT) method and the Critical Path Method (CPM) method. Bedugul Villa is one of the projects that has been carried out with a work contract for 175 calendar days and the scheduling of which will be optimized in this study. The optimal duration for scheduling with the PERT method is to produce an optimal duration of 170 calendar days. The duration is 5 days faster than the existing schedule prepared by the project construction contractor, which is 175 calendar days. The probability of completion of the project is 87.7%. Calculations using the CPM method are 168 calendar days or 7 days earlier than the existing schedule made by the contractor.

Jaringan kolaborasi para penulis

16 penulis · 26 tautan kepenulisan bersama

Arahkan kursor atau ketuk sebuah nama untuk menyorot rekan penulisnya. Klik dua kali untuk membuka halaman penulis.

  • Universitas Jember
  • Afiliasi tidak diketahui
  • Organisasi berbeda
  • Organisasi sama
  • Afiliasi tidak diketahui
  • Garis lebih tebal = lebih banyak artikel bersama · lingkaran lebih besar = lebih banyak artikel
Tampilkan sebagai tabel
Rekan penulisOrganisasiArtikel bersama
Ahmad KamsyakawuniAfiliasi tidak diketahui6
Erick DeleniaUniversitas Jember2
Dyan Mei AnggraeniUniversitas Jember2
Ahmad KamsyakawuniUniversitas Jember1
Muhammad SeggafUniversitas Jember1
Firda FadriUniversitas Jember1
Yoyok YuliantoUniversitas Jember1
Amalia Putri Nur HabibahAfiliasi tidak diketahui1
Farokhi AbdiansyahAfiliasi tidak diketahui1
Giki KrisnawantiAfiliasi tidak diketahui1
Rahmawati Awwaliyah PutriAfiliasi tidak diketahui1
Rif’atul MakhomahAfiliasi tidak diketahui1
Tika KhairaniAfiliasi tidak diketahui1

Afiliasi berasal dari OpenAlex; metadata OAI-PMH jurnal tidak memuatnya. Penulis tanpa ID OpenAlex dicocokkan berdasarkan nama, sehingga dua orang bisa tergabung atau satu orang bisa terpisah.

Sumber metadata: OAI-PMH (metadata jurnal) https://ojs3.unpatti.ac.id/index.php/barekeng/oai, pertama di-harvest 5 Nov 2026, terakhir terlihat 15 Nov 2026.
Metadata asli (oai_dc)
<oai_dc:dc xmlns="http://www.openarchives.org/OAI/2.0/" xmlns:dc="http://purl.org/dc/elements/1.1/" xmlns:oai_dc="http://www.openarchives.org/OAI/2.0/oai_dc/" xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:schemaLocation="http://www.openarchives.org/OAI/2.0/oai_dc/  http://www.openarchives.org/OAI/2.0/oai_dc.xsd">
	<dc:title xml:lang="en-US">SCHEDULING ANALYSIS BEDUGUL VILLA CONSTRUCTION PROJECT USING PERT AND CPM METHODS</dc:title>
	<dc:creator>Santoso, Kiswara Agung</dc:creator>
	<dc:creator>Yusnita, Ade Ratna</dc:creator>
	<dc:creator>Pradjaningsih, Agustina</dc:creator>
	<dc:description xml:lang="en-US">Scheduling in construction projects is necessary so that the planned time to complete the project can be achieved on time. the methods used in optimizing project scheduling are the Project Evaluation Review Technique (PERT) method and the Critical Path Method (CPM) method. Bedugul&amp;nbsp; Villa is one of the projects that has been carried out with a work contract for 175 calendar days and the scheduling of which will be optimized in this study. The optimal duration for scheduling with the PERT method is to produce an optimal duration of 170 calendar days. The duration is 5 days faster than the existing schedule prepared by the project construction contractor, which is 175 calendar days. The probability of completion of the project is 87.7%. Calculations using the CPM method are 168 calendar days or 7 days earlier than the existing schedule made by the contractor.</dc:description>
	<dc:publisher xml:lang="en-US">PATTIMURA UNIVERSITY</dc:publisher>
	<dc:date>2024-03-01</dc:date>
	<dc:type>info:eu-repo/semantics/article</dc:type>
	<dc:type>info:eu-repo/semantics/publishedVersion</dc:type>
	<dc:format>application/pdf</dc:format>
	<dc:identifier>https://ojs3.unpatti.ac.id/index.php/barekeng/article/view/9900</dc:identifier>
	<dc:identifier>10.30598/barekengvol18iss1pp0105-0116</dc:identifier>
	<dc:source xml:lang="en-US">BAREKENG: Jurnal Ilmu Matematika dan Terapan; Vol 18 No 1 (2024): BAREKENG: Journal of Mathematics and Its Application; 0105-0116</dc:source>
	<dc:source>2615-3017</dc:source>
	<dc:source>1978-7227</dc:source>
	<dc:source>10.30598/barekengvol18iss1year2024</dc:source>
	<dc:language>eng</dc:language>
	<dc:relation>https://ojs3.unpatti.ac.id/index.php/barekeng/article/view/9900/7556</dc:relation>
	<dc:rights xml:lang="en-US">Copyright (c) 2024 Kiswara Agung Santoso, Ade Ratna Yusnita, Agustina Pradjaningsih</dc:rights>
	<dc:rights xml:lang="en-US">http://creativecommons.org/licenses/by-sa/4.0</dc:rights>
</oai_dc:dc>