Preventive Maintenance Scheduling with Age Replacement Method at CNG Station
Aptisi Transactions on Technopreneurship (ATT) · Vol. 4 No. 2 (2022) · hlm. 153–163
ISSN 2656-8888, 2655-8807
Terbit 2022-07-21
Penerbit Pandawan
Bahasa en
Abstrak
CNG Mother Station focused to distribute Compressed Natural Gas for various industries. In the period from December 2020 to November 2021, there were 40 breakdowns in the distribution process machine causing delays in distribution of CNG. Company has to pay attention to the maintenance scheduling for vulnerabl components. This study aims to determine Preventive Maintenance scheduling and calculating maintenance costs using Age Replacement method for the critical components. The results showed that the critical components are Air Supply’s Hose (ASH) and Double Nipple Stage 4 (DNS-4). The proposed optimal replacement time interval for the ASH is 20 days where 19 component replacements are scheduled in 1 year with a cost reduction up to 4.8% compared to existing. The optimal replacement time interval for DNS-4 components is 24 days, which is scheduled for 16 component replacements in 1 year with cost reduction up to 29.1% compared to existing.
Jaringan kolaborasi para penulis
21 penulis ·
43 tautan kepenulisan bersama
· 10 lintas organisasi
Arahkan kursor atau ketuk sebuah nama untuk menyorot rekan penulisnya. Klik dua kali untuk membuka halaman penulis.
Universitas Esa Unggul Multimedia Nusantara University Universitas Raharja Universitas Pamulang Afiliasi tidak diketahui
Organisasi berbeda
Organisasi sama
Afiliasi tidak diketahui
Garis lebih tebal = lebih banyak artikel bersama · lingkaran lebih besar = lebih banyak artikel
Tampilkan sebagai tabel
Afiliasi berasal dari OpenAlex; metadata OAI-PMH jurnal tidak memuatnya. Penulis tanpa ID OpenAlex dicocokkan berdasarkan nama, sehingga dua orang bisa tergabung atau satu orang bisa terpisah.
Sumber metadata: OAI-PMH (metadata jurnal) https://att.aptisi.or.id/index.php/att/oai, pertama di-harvest 6 Nov 2026, terakhir terlihat 8 Nov 2026.
Metadata asli (oai_dc)
<oai_dc:dc xmlns="http://www.openarchives.org/OAI/2.0/" xmlns:dc="http://purl.org/dc/elements/1.1/" xmlns:oai_dc="http://www.openarchives.org/OAI/2.0/oai_dc/" xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:schemaLocation="http://www.openarchives.org/OAI/2.0/oai_dc/ http://www.openarchives.org/OAI/2.0/oai_dc.xsd">
<dc:title xml:lang="en">Preventive Maintenance Scheduling with Age Replacement Method at CNG Station </dc:title>
<dc:creator xml:lang="en">Bangun, Cicilia</dc:creator>
<dc:creator xml:lang="en">Jalil, Abdul</dc:creator>
<dc:creator xml:lang="en">Amperajaya, Derajat </dc:creator>
<dc:creator xml:lang="en">Rasjidin, Roesfiansjah </dc:creator>
<dc:subject xml:lang="en">Preventive Maintenance</dc:subject>
<dc:subject xml:lang="en">Mean Time to Failure</dc:subject>
<dc:subject xml:lang="en">Mean Time to Repair</dc:subject>
<dc:subject xml:lang="en">Age Replacement</dc:subject>
<dc:subject xml:lang="en">Cost saving</dc:subject>
<dc:description xml:lang="en">CNG Mother Station focused to distribute Compressed Natural Gas for various industries. In the period from December 2020 to November 2021, there were 40 breakdowns in the distribution process machine causing delays in distribution of CNG. Company has to pay attention to the maintenance scheduling for vulnerabl components. This study aims to determine Preventive Maintenance scheduling and calculating maintenance costs using Age Replacement method for the critical components. The results showed that the critical components are Air Supply’s Hose (ASH) and Double Nipple Stage 4 (DNS-4). The proposed optimal replacement time interval for the ASH is 20 days where 19 component replacements are scheduled in 1 year with a cost reduction up to 4.8% compared to existing. The optimal replacement time interval for DNS-4 components is 24 days, which is scheduled for 16 component replacements in 1 year with cost reduction up to 29.1% compared to existing.</dc:description>
<dc:publisher xml:lang="en">Pandawan</dc:publisher>
<dc:date>2022-07-21</dc:date>
<dc:type>info:eu-repo/semantics/article</dc:type>
<dc:type>info:eu-repo/semantics/publishedVersion</dc:type>
<dc:type xml:lang="en">Peer-reviewed Article</dc:type>
<dc:format>application/pdf</dc:format>
<dc:identifier>https://att.aptisi.or.id/index.php/att/article/view/260</dc:identifier>
<dc:identifier>10.34306/att.v4i2.260</dc:identifier>
<dc:source xml:lang="en">Aptisi Transactions on Technopreneurship (ATT); Vol. 4 No. 2 (2022): July; 153-163</dc:source>
<dc:source xml:lang="id">Aptisi Transactions On Technopreneurship (ATT); Vol 4 No 2 (2022): July; 153-163</dc:source>
<dc:source>2656-8888</dc:source>
<dc:source>2655-8807</dc:source>
<dc:source>10.34306/att.v4i2</dc:source>
<dc:language>en</dc:language>
<dc:relation>https://att.aptisi.or.id/index.php/att/article/view/260/173</dc:relation>
<dc:rights xml:lang="en">Copyright (c) 2022 Cicilia Bangun, Abdul Jalil, Derajat Amperajaya, Roesfiansjah Rasjidin</dc:rights>
<dc:rights xml:lang="en">https://creativecommons.org/licenses/by/4.0</dc:rights>
</oai_dc:dc>
Sitasi dan pengindeksan
Jumlah menurut tiap indeks pada 13 Nov 2026; setiap indeks menghitung sitasi dengan cara berbeda.
OpenAlex juga mencatat karya ini di: crossref, doaj.
Sitasi artikel ini
APA 7
Bangun, C., Jalil, A., Amperajaya, D., & Rasjidin, R. (2022). Preventive Maintenance Scheduling with Age Replacement Method at CNG Station. Aptisi Transactions on Technopreneurship (ATT), 4(2), 153–163. https://doi.org/10.34306/att.v4i2.260
Salin
IEEE
C. Bangun, A. Jalil, D. Amperajaya, and R. Rasjidin, “Preventive Maintenance Scheduling with Age Replacement Method at CNG Station,” Aptisi Transactions on Technopreneurship (ATT), vol. 4, no. 2, pp. 153–163, 2022, doi: 10.34306/att.v4i2.260.
Salin
Dibuat dari metadata jurnal; periksa nama penulis sebelum dipakai.