Repetitive Construction Scheduling Using Line of Balance (Case Study: One of the 6-Storey Polyclinic Building Construction Project in Batang Regency)

Jurnal Teknik Sipil dan Perencanaan · Vol. 27 No. 2 (2025) · hlm. 98–107

DOI
10.15294/jtsp.v27i2.5088
ISSN
2503-1899, 1411-1772
Terbit
2025-10-31
Penerbit
Universitas Negeri Semarang
Bahasa
eng

Abstrak

Repetitive work is often encountered by contractors, so effective planning is needed so that the project can achieve its goals within the set time limit. One aspect of planning is project scheduling, which is a method that is used in construction work. One of the scheduling methods suitable for repetitive construction is a line of balance. Therefore, this research was conducted using the line of balance method on a repetitive multi-story building project to find out whether the line of balance can properly organize project implementation. The results of the analysis and calculations that have been carried out obtained the duration required to complete the construction project of the 6-story polyclinic building for 274 days. The schedule in the project plan takes 308 days to complete the project. By comparing the effectiveness of the time whose duration is at odds with 34 days, the schedule plan using the line of balance method is more effective and efficient in completing the construction project of the 6-story polyclinic building in Batang Regency.

Kata kunci

Jaringan kolaborasi para penulis

22 penulis · 67 tautan kepenulisan bersama

Arahkan kursor atau ketuk sebuah nama untuk menyorot rekan penulisnya. Klik dua kali untuk membuka halaman penulis.

  • State University of Semarang
  • Afiliasi tidak diketahui
  • Organisasi berbeda
  • Organisasi sama
  • Afiliasi tidak diketahui
  • Garis lebih tebal = lebih banyak artikel bersama · lingkaran lebih besar = lebih banyak artikel
Tampilkan sebagai tabel
Rekan penulisOrganisasiArtikel bersama
Ardiyan Adhi WibowoAfiliasi tidak diketahui1
Adi KuntoroAfiliasi tidak diketahui1
RM. Bambang Setyohadi Kuswarna PutraAfiliasi tidak diketahui1
Sherley Ika ChristantiAfiliasi tidak diketahui1
Muhammad Harits Al RasyidAfiliasi tidak diketahui1
Janae Christie Nemorai EmbongdumaAfiliasi tidak diketahui1
Syira Riskiyani SinambelaAfiliasi tidak diketahui1
Pandam Bayu Seto AjiAfiliasi tidak diketahui1
Catur Rini WidyastutiAfiliasi tidak diketahui1
Rizqi Fitri NaryantoAfiliasi tidak diketahui1
Rizki SetiadiAfiliasi tidak diketahui1
Habib BunajarAfiliasi tidak diketahui1
Iqbal Rasendriya ArafahAfiliasi tidak diketahui1
Afrilza Daffa NaryapramonoAfiliasi tidak diketahui1
Bunyamin BunyaminState University of Semarang1
Rizky SetiadiAfiliasi tidak diketahui1
Ari Dwi Nur Indriawan MusyonoAfiliasi tidak diketahui1
Sofi Alifia HidyusAfiliasi tidak diketahui1

Afiliasi berasal dari OpenAlex; metadata OAI-PMH jurnal tidak memuatnya. Penulis tanpa ID OpenAlex dicocokkan berdasarkan nama, sehingga dua orang bisa tergabung atau satu orang bisa terpisah.

Sumber metadata: OAI-PMH (metadata jurnal) https://journal.unnes.ac.id/journals/jtsp/oai, pertama di-harvest 6 Nov 2026, terakhir terlihat 8 Nov 2026.
Metadata asli (oai_dc)
<oai_dc:dc xmlns="http://www.openarchives.org/OAI/2.0/" xmlns:dc="http://purl.org/dc/elements/1.1/" xmlns:oai_dc="http://www.openarchives.org/OAI/2.0/oai_dc/" xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:schemaLocation="http://www.openarchives.org/OAI/2.0/oai_dc/  http://www.openarchives.org/OAI/2.0/oai_dc.xsd">
	<dc:title xml:lang="en">Repetitive Construction Scheduling Using Line of Balance (Case Study: One of the 6-Storey Polyclinic Building Construction Project in Batang Regency)</dc:title>
	<dc:creator xml:lang="en">Winata, Dwiki Pandu</dc:creator>
	<dc:creator xml:lang="en">Agung Budiwirawan</dc:creator>
	<dc:creator xml:lang="en">Muhammad Faizal Ardhiansyah Arifin</dc:creator>
	<dc:creator xml:lang="en">Irfandi Saputra Tua Saragi</dc:creator>
	<dc:subject xml:lang="en">repetitive work</dc:subject>
	<dc:subject xml:lang="en">project scheduling</dc:subject>
	<dc:subject xml:lang="en">line of balance</dc:subject>
	<dc:description xml:lang="en">Repetitive work is often encountered by contractors, so effective planning is needed so that the project can achieve its goals within the set time limit. One aspect of planning is project scheduling, which is a method that is used in construction work. One of the scheduling methods suitable for repetitive construction is a line of balance. Therefore, this research was conducted using the line of balance method on a repetitive multi-story building project to find out whether the line of balance can properly organize project implementation. The results of the analysis and calculations that have been carried out obtained the duration required to complete the construction project of the 6-story polyclinic building for 274 days. The schedule in the project plan takes 308 days to complete the project. By comparing the effectiveness of the time whose duration is at odds with 34 days, the schedule plan using the line of balance method is more effective and efficient in completing the construction project of the 6-story polyclinic building in Batang Regency. </dc:description>
	<dc:publisher xml:lang="en">Universitas Negeri Semarang</dc:publisher>
	<dc:date>2025-10-31</dc:date>
	<dc:type>info:eu-repo/semantics/article</dc:type>
	<dc:type>info:eu-repo/semantics/publishedVersion</dc:type>
	<dc:type xml:lang="en">Peer-reviewed Article</dc:type>
	<dc:format>application/pdf</dc:format>
	<dc:identifier>https://journal.unnes.ac.id/journals/jtsp/article/view/5088</dc:identifier>
	<dc:identifier>10.15294/jtsp.v27i2.5088</dc:identifier>
	<dc:source xml:lang="en">Jurnal Teknik Sipil dan Perencanaan; Vol. 27 No. 2 (2025): Jurnal Teknik Sipil dan Perencanaan; 98 - 107</dc:source>
	<dc:source>2503-1899</dc:source>
	<dc:source>1411-1772</dc:source>
	<dc:source>10.15294/jtsp.v27i2</dc:source>
	<dc:language>eng</dc:language>
	<dc:relation>https://journal.unnes.ac.id/journals/jtsp/article/view/5088/6739</dc:relation>
	<dc:rights xml:lang="en">Copyright (c) 2025 Jurnal Teknik Sipil dan Perencanaan</dc:rights>
</oai_dc:dc>