Perencanaan Teknis dan Biaya Reklamasi Lahan Bekas Penambangan Batubara Pit 1 di PT Seluma Prima Coal, Desa Rangkiling, Kecamatan Mandiangin, Kabupaten Sarolangun, Provinsi Jambi

JTK (Jurnal Teknik Kebumian) · Vol. 8 No. 01 (2024) · hlm. 31–40

DOI
10.22437/jtk.v8i01.23138
ISSN
2715-5587, 2477-8583
Terbit
2024-02-01
Penerbit
Jurusan Teknik Kebumian, Fakultas Sains dan Teknologi
Bahasa
en
Lisensi
creativecommons.org/licenses/by-nc-sa/4.0

Abstrak

Coal is a fossil fuel derived from sedimentary rocks that can be burned and formed from organic deposits and formed through the coalification process. One of the open pit coal mining methods applied by mining companies in Indonesia is the open pit method. After mining activities in a pit are completed, the ex- mining land will leave openings. The openings are backfilled with material from the overburden in the pits that are mined next.. This study uses quantitative, descriptive, and interviews with the company. The use of this method, because in the future research will use data in the form of numbers and present data in a visual form that is processed from data modeling so that it is easy to understand. The planned reclamation area is pit 1 opening area. The total area of the plan for reclamation of former coal mining pit 1 is 11.43 Ha, with an area for revegetation that is 9.13 Ha, and the area for other uses is 2.3 Ha (roads and trench). In the implementation of reclamation activities, it is inseparable from the design of the reclamation plan and the calculation of the reclamation cost plan. The design for the reclamation of pit 1 was made using a topographic map of the research area and a map of the mine situation. The reclamation design carried out includes road geometry with a straight road width of 9 m, a bend road width of 16 m, and a road grade of 8% (4.6o); level geometry with a ladder angle of 45°, an overall angle of 13°, a width of 5 meters, and a height of 6 meters; the terrace design used is a garden terrace with a terrace width of ± 1.5 m; and ditch construction with a width of 0.5 meters and a depth of 1 meter. The cost of the reclamation plan in the form of revegetation pit 1 to reclaim a land area of 9.13 hectares is Rp. 647,486,722 (six hundred forty- seven million four hundred and eighty-six thousand seven hundred and twenty-two rupiah). This cost includes the cost of land management, revegetation, and maintenance for 3 years.Keywords: Reclamation, coal, cost

Jaringan kolaborasi para penulis

28 penulis · 93 tautan kepenulisan bersama

Arahkan kursor atau ketuk sebuah nama untuk menyorot rekan penulisnya. Klik dua kali untuk membuka halaman penulis.

  • Universitas Jambi
  • Afiliasi tidak diketahui
  • Organisasi berbeda
  • Organisasi sama
  • Afiliasi tidak diketahui
  • Garis lebih tebal = lebih banyak artikel bersama · lingkaran lebih besar = lebih banyak artikel
Tampilkan sebagai tabel
Rekan penulisOrganisasiArtikel bersama
Bagus AdhityaUniversitas Jambi4
Yudi Arista YulandaAfiliasi tidak diketahui3
Aditya Denny PrabawaAfiliasi tidak diketahui2
Jarot WiratamaAfiliasi tidak diketahui2
Muhammad IkrarAfiliasi tidak diketahui1
Dimas Agung PermadiAfiliasi tidak diketahui1
Affif Farras ChanAfiliasi tidak diketahui1
Siti SadariahAfiliasi tidak diketahui1
Muhammad Ikrar LagowaAfiliasi tidak diketahui1
Maulina TanjungAfiliasi tidak diketahui1
BagusAfiliasi tidak diketahui1
Itang Ahmad MahbubAfiliasi tidak diketahui1
NeliyatiAfiliasi tidak diketahui1
Itang Ahmad MahbubUniversitas Jambi1
Gindo TampubolonUniversitas Jambi1
Neliyati NeliyatiAfiliasi tidak diketahui1
Faizar FaridAfiliasi tidak diketahui1
Muhammad El HakimAfiliasi tidak diketahui1
Tiara PratiwiAfiliasi tidak diketahui1
Engla KardetaAfiliasi tidak diketahui1
Lenny MarlindaAfiliasi tidak diketahui1
M AL KahfiAfiliasi tidak diketahui1
Wahyudi ZaharAfiliasi tidak diketahui1
Dhaffin IbransyahAfiliasi tidak diketahui1
Fitri KhairunnisaAfiliasi tidak diketahui1

Afiliasi berasal dari OpenAlex; metadata OAI-PMH jurnal tidak memuatnya. Penulis tanpa ID OpenAlex dicocokkan berdasarkan nama, sehingga dua orang bisa tergabung atau satu orang bisa terpisah.

Sumber metadata: OAI-PMH (metadata jurnal) https://online-journal.unja.ac.id/index.php/jtk/oai, pertama di-harvest 6 Nov 2026, terakhir terlihat 8 Nov 2026.
Metadata asli (oai_dc)
<oai_dc:dc xmlns="http://www.openarchives.org/OAI/2.0/" xmlns:dc="http://purl.org/dc/elements/1.1/" xmlns:oai_dc="http://www.openarchives.org/OAI/2.0/oai_dc/" xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:schemaLocation="http://www.openarchives.org/OAI/2.0/oai_dc/  http://www.openarchives.org/OAI/2.0/oai_dc.xsd">
	<dc:title xml:lang="en">Perencanaan Teknis dan Biaya Reklamasi Lahan Bekas Penambangan Batubara Pit 1 di PT Seluma Prima Coal, Desa Rangkiling, Kecamatan Mandiangin, Kabupaten Sarolangun, Provinsi Jambi</dc:title>
	<dc:creator xml:lang="en">Hafifa, Lides </dc:creator>
	<dc:creator xml:lang="en">Megasukma, Yosa </dc:creator>
	<dc:creator xml:lang="en">Tampubolon, Gindo </dc:creator>
	<dc:description xml:lang="en">Coal is a fossil fuel derived from sedimentary rocks that can be burned and formed from organic deposits and formed through the coalification process. One of the open pit coal mining methods applied by mining companies in Indonesia is the open pit method. After mining activities in a pit are completed, the ex- mining land will leave openings. The openings are backfilled with material from the overburden in the pits that are mined next.. This study uses quantitative, descriptive, and interviews with the company. The use of this method, because in the future research will use data in the form of numbers and present data in a visual form that is processed from data modeling so that it is easy to understand. The planned reclamation area is pit 1 opening area. The total area of the plan for reclamation of former coal mining pit 1 is 11.43 Ha, with an area for revegetation that is 9.13 Ha, and the area for other uses is 2.3 Ha (roads and trench). In the implementation of reclamation activities, it is inseparable from the design of the reclamation plan and the calculation of the reclamation cost plan. The design for the reclamation of pit 1 was made using a topographic map of the research area and a map of the mine situation. The reclamation design carried out includes road geometry with a straight road width of 9 m, a bend road width of 16 m, and a road grade of 8% (4.6o); level geometry with a ladder angle of 45°, an overall angle of 13°, a width of 5 meters, and a height of 6 meters; the terrace design used is a garden terrace with a terrace width of ± 1.5 m; and ditch construction with a width of 0.5 meters and a depth of 1 meter. The cost of the reclamation plan in the form of revegetation pit 1 to reclaim a land area of 9.13 hectares is Rp. 647,486,722 (six hundred forty- seven million four hundred and eighty-six thousand seven hundred and twenty-two rupiah). This cost includes the cost of land management, revegetation, and maintenance for 3 years.Keywords: Reclamation, coal, cost</dc:description>
	<dc:publisher xml:lang="en">Jurusan Teknik Kebumian, Fakultas Sains dan Teknologi</dc:publisher>
	<dc:date>2024-02-01</dc:date>
	<dc:type>info:eu-repo/semantics/article</dc:type>
	<dc:type>info:eu-repo/semantics/publishedVersion</dc:type>
	<dc:type xml:lang="en">Peer-reviewed Article</dc:type>
	<dc:format>application/pdf</dc:format>
	<dc:identifier>https://online-journal.unja.ac.id/jtk/article/view/23138</dc:identifier>
	<dc:identifier>10.22437/jtk.v8i01.23138</dc:identifier>
	<dc:source xml:lang="en">JTK (Jurnal Teknik Kebumian); Vol. 8 No. 01 (2022): JURNAL TEKNIK KEBUMIAN (JTK); 31-40</dc:source>
	<dc:source>2715-5587</dc:source>
	<dc:source>2477-8583</dc:source>
	<dc:language>en</dc:language>
	<dc:relation>https://online-journal.unja.ac.id/jtk/article/view/23138/14982</dc:relation>
	<dc:rights xml:lang="en">https://creativecommons.org/licenses/by-nc-sa/4.0</dc:rights>
</oai_dc:dc>