Determination of Optimum Resources for the Blang Kejeren Electrical System Using PSS Sincal Application

Circuit: Jurnal Ilmiah Pendidikan Teknik Elektro · Vol. 8 No. 1 (2024) · hlm. 34–45

DOI
10.22373/crc.v8i1.19441
ISSN
2549-3701, 2549-3698
Terbit
2024-01-29
Penerbit
PTE FTK UIN Ar-Raniry
Bahasa
eng

Abstrak

Currently, the Customer Service Unit (ULP) of the Blang Kejeren State Power Company (PLN) uses the system of the Diesel Power Power Centre (PLTD). Sistem ini terdiri dari PLTD yang dimiliki PLN dan PLtD Lewa, serta beberapa PLTMH (Pusat Listrik Tenaga Mikro Hidro). Aim of the study is to assess the technical viability of the 20 kV ULP Blangkejeren system if supplied with the Kutacane GI and parallel with Distributed Generation (DG). This is because there is no distribution network that can connect the Blangkejeren ULP load centre to the Kutacane GI. Using the PSS Sincal Power System Analysis Application, load scenarios for power plants and distribution networks are modeled and simulated. The findings indicate that the 20kV Ulp Blangkjeren system provided by GI Kutacana, PLTMH, PLTM Lawe, and PLTD Rema is the most appropriate scenario. This situation is regarded as optimal, with a network voltage of 21.07 kV on the ULP Blangkejeren Connection Guard Bus.

Kata kunci

Jaringan kolaborasi para penulis

9 penulis · 12 tautan kepenulisan bersama · 4 lintas organisasi

Arahkan kursor atau ketuk sebuah nama untuk menyorot rekan penulisnya. Klik dua kali untuk membuka halaman penulis.

  • Universitas Syiah Kuala
  • Universitas Sultan Muhammad Syafiuddin Sambas
  • Universitas Islam Negeri Ar-Raniry
  • Afiliasi tidak diketahui
  • Organisasi berbeda
  • Organisasi sama
  • Afiliasi tidak diketahui
  • Garis lebih tebal = lebih banyak artikel bersama · lingkaran lebih besar = lebih banyak artikel
Tampilkan sebagai tabel
Rekan penulisOrganisasiArtikel bersama
La HasanuddinAfiliasi tidak diketahui1
Ridway BalakaAfiliasi tidak diketahui1
Budi IswantoUniversitas Sultan Muhammad Syafiuddin Sambas1
Munadi MunadiUniversitas Sultan Muhammad Syafiuddin Sambas1
Septian RiswandiUniversitas Syiah Kuala1
Ramdhan Halid SiregarUniversitas Syiah Kuala1

Afiliasi berasal dari OpenAlex; metadata OAI-PMH jurnal tidak memuatnya. Penulis tanpa ID OpenAlex dicocokkan berdasarkan nama, sehingga dua orang bisa tergabung atau satu orang bisa terpisah.

Sumber metadata: OAI-PMH (metadata jurnal) https://jurnal.ar-raniry.ac.id/index.php/circuit/oai, pertama di-harvest 6 Nov 2026, terakhir terlihat 16 Nov 2026.
Metadata asli (oai_dc)
<oai_dc:dc xmlns="http://www.openarchives.org/OAI/2.0/" xmlns:dc="http://purl.org/dc/elements/1.1/" xmlns:oai_dc="http://www.openarchives.org/OAI/2.0/oai_dc/" xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:schemaLocation="http://www.openarchives.org/OAI/2.0/oai_dc/  http://www.openarchives.org/OAI/2.0/oai_dc.xsd">
	<dc:title xml:lang="en">Determination of Optimum Resources for the Blang Kejeren Electrical System Using PSS Sincal Application</dc:title>
	<dc:creator xml:lang="en">Panggabean, Ulil Azmi</dc:creator>
	<dc:creator xml:lang="en">Suriadi, Suriadi</dc:creator>
	<dc:creator xml:lang="en">Lubis, Rakhmad Syafutra</dc:creator>
	<dc:subject xml:lang="en">Isolated</dc:subject>
	<dc:subject xml:lang="en">GI</dc:subject>
	<dc:subject xml:lang="en">DG</dc:subject>
	<dc:subject xml:lang="en">power flow</dc:subject>
	<dc:subject xml:lang="en">PSS Sincal</dc:subject>
	<dc:description xml:lang="en">Currently, the Customer Service Unit (ULP) of the Blang Kejeren State Power Company (PLN) uses the system of the Diesel Power Power Centre (PLTD). Sistem ini terdiri dari PLTD yang dimiliki PLN dan PLtD Lewa, serta beberapa PLTMH (Pusat Listrik Tenaga Mikro Hidro). Aim of the study is to assess the technical viability of the 20 kV ULP Blangkejeren system if supplied with the Kutacane GI and parallel with Distributed Generation (DG). This is because there is no distribution network that can connect the Blangkejeren ULP load centre to the Kutacane GI. Using the PSS Sincal Power System Analysis Application, load scenarios for power plants and distribution networks are modeled and simulated. The findings indicate that the 20kV Ulp Blangkjeren system provided by GI Kutacana, PLTMH, PLTM Lawe, and PLTD Rema is the most appropriate scenario. This situation is regarded as optimal, with a network voltage of 21.07 kV on the ULP Blangkejeren Connection Guard Bus. </dc:description>
	<dc:publisher xml:lang="en">PTE FTK UIN Ar-Raniry</dc:publisher>
	<dc:date>2024-01-29</dc:date>
	<dc:type>info:eu-repo/semantics/article</dc:type>
	<dc:type>info:eu-repo/semantics/publishedVersion</dc:type>
	<dc:format>application/pdf</dc:format>
	<dc:identifier>https://jurnal.ar-raniry.ac.id/index.php/circuit/article/view/19441</dc:identifier>
	<dc:identifier>10.22373/crc.v8i1.19441</dc:identifier>
	<dc:source xml:lang="en">Circuit: Jurnal Ilmiah Pendidikan Teknik Elektro; Vol. 8 No. 1 (2024); 34-45</dc:source>
	<dc:source>2549-3701</dc:source>
	<dc:source>2549-3698</dc:source>
	<dc:language>eng</dc:language>
	<dc:relation>https://jurnal.ar-raniry.ac.id/index.php/circuit/article/view/19441/9120</dc:relation>
	<dc:rights xml:lang="en">Copyright (c) 2024 Ulil Azmi Panggabean, Suriadi, Rakhmad Syafutra Lubis</dc:rights>
</oai_dc:dc>