Analisa Percepatan Dengan Metode Time Cost Trade Off Pada Proyek Pembangunan SPBI 2 × 200 Kl

Sultra Civil Engineering Journal (SCiEJ) · Vol. 6 No. 1 (2025) · pp. 446–457

DOI
10.54297/sciej.v6i1.927
ISSN
2716-1714
Published
2025-04-22
Publisher
Universitas Sulawesi Tenggara
Language
eng
License
creativecommons.org/licenses/by/4.0

Abstract

The SPBI 2×200 KL construction project, initially planned to be completed in 360 days, experienced significant delays in the 21st week, with a progress deviation of -16.434%. To address this issue, the Time Cost Trade Off (TCTO) acceleration method was implemented by adding 4 hours of overtime work per day. This strategy successfully shortened the project duration from 336 days to 231 days, reducing the total project time by 37%. The acceleration efforts were focused on critical paths that influenced the project's completion. Although there was a 17.1% increase in direct costs due to overtime wages, additional labor, and extra materials, the application of TCTO effectively reduced indirect costs associated with prolonged project duration, such as administrative and operational expenses. Overall, this method proved to be effective in bringing the project back on schedule and preventing further losses due to delays.

Collaboration network of the authors

6 authors · 9 co-authorship links

Hover or tap a name to highlight its co-authors. Double-click to open the author's page.

  • Universitas Bina Darma
  • Different organisations
  • Same organisation
  • Affiliation unknown
  • Thicker line = more joint articles · bigger circle = more articles
Show as table
Co-authorOrganisationJoint articles
Dwi KurniaUniversitas Bina Darma1
Achmad SyarifudinUniversitas Bina Darma1
Wanda Yudha PrawiraUniversitas Bina Darma1

Affiliations come from OpenAlex; journal OAI-PMH metadata carries none. Authors without an OpenAlex ID are matched by name, which can merge or split people.

Metadata source: OAI-PMH (metadata jurnal) https://jurnal-unsultra.ac.id/index.php/scej/oai, first harvested 30 Oct 2026, last seen 22 Nov 2026.
Original metadata (oai_dc)
<oai_dc:dc xmlns="http://www.openarchives.org/OAI/2.0/" xmlns:dc="http://purl.org/dc/elements/1.1/" xmlns:oai_dc="http://www.openarchives.org/OAI/2.0/oai_dc/" xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:schemaLocation="http://www.openarchives.org/OAI/2.0/oai_dc/  http://www.openarchives.org/OAI/2.0/oai_dc.xsd">
	<dc:title xml:lang="en-US">Analisa Percepatan Dengan Metode Time Cost Trade Off Pada Proyek Pembangunan SPBI 2 × 200 Kl</dc:title>
	<dc:creator>Sakinah, Sakinah</dc:creator>
	<dc:creator>Mazpar, Ely</dc:creator>
	<dc:creator>Mulyati, Ely</dc:creator>
	<dc:description xml:lang="en-US">The SPBI 2×200 KL construction project, initially planned to be completed in 360 days, experienced significant delays in the 21st week, with a progress deviation of -16.434%. To address this issue, the Time Cost Trade Off (TCTO) acceleration method was implemented by adding 4 hours of overtime work per day. This strategy successfully shortened the project duration from 336 days to 231 days, reducing the total project time by 37%. The acceleration efforts were focused on critical paths that influenced the project's completion. Although there was a 17.1% increase in direct costs due to overtime wages, additional labor, and extra materials, the application of TCTO effectively reduced indirect costs associated with prolonged project duration, such as administrative and operational expenses. Overall, this method proved to be effective in bringing the project back on schedule and preventing further losses due to delays.</dc:description>
	<dc:publisher xml:lang="en-US">Universitas Sulawesi Tenggara</dc:publisher>
	<dc:date>2025-04-22</dc:date>
	<dc:type>info:eu-repo/semantics/article</dc:type>
	<dc:type>info:eu-repo/semantics/publishedVersion</dc:type>
	<dc:format>application/pdf</dc:format>
	<dc:identifier>https://jurnal-unsultra.ac.id/index.php/scej/article/view/927</dc:identifier>
	<dc:identifier>10.54297/sciej.v6i1.927</dc:identifier>
	<dc:source xml:lang="en-US">Sultra Civil Engineering Journal (SCiEJ); Vol 6 No 1 (2025): Sultra Civil Engineering Journal (SCiEJ); 446-457</dc:source>
	<dc:source>2716-1714</dc:source>
	<dc:source>10.54297/sciej.v6i1</dc:source>
	<dc:language>eng</dc:language>
	<dc:relation>https://jurnal-unsultra.ac.id/index.php/scej/article/view/927/706</dc:relation>
	<dc:relation>10.54297/sciej.v6i1.927.g706</dc:relation>
	<dc:rights xml:lang="en-US">Copyright (c) 2025 Sakinah Sakinah, Ely Mazpar, Ely Mulyati</dc:rights>
	<dc:rights xml:lang="en-US">http://creativecommons.org/licenses/by/4.0</dc:rights>
</oai_dc:dc>