Analysis of Labor Productivity in Floor Plate Work Using The Work Sampling Method: Case Study: Udayana University Faculty of Medicine Building and The Calna Villa

Logic: Jurnal Rancang Bangun dan Teknologi · Vol. 23 No. 1 (2023) · pp. 42–48

DOI
10.31940/logic.v23i1.42-48
ISSN
2580-5649, 1412-114X
Published
2023-03-30
Publisher
Unit Publikasi Ilmiah, P3M, Politeknik Negeri Bali
Language
eng

Abstract

Labor productivity is very important in carrying out a job, in the field of construction output can be seen from the quantity of work that has been done, while input is the amount of resources used such as labor. This study aims to determine the amount of labor required per 1 m2 (OH) and the standard time for labor productivity in completing 1 m2 of floor slab work. The method of collecting primary data is the source of research data obtained directly, such as the number of workers and observation of sampling data, while secondary data is obtained from projects such as working drawings. The data is then processed using Microsoft Excel. This research is a type of quantitative research with work sampling method. From the results of research on floor slab work in the Udayana University Faculty of Medicine Building Construction project, it shows that the calculation of the volume of labor per day (OH) requires 0.011 OH masons and 0.011 OH workers and the results of calculating the standard time to complete 1 m2 of floor slab work is 3.15 minutes/m2. The Calna Villa project shows that the calculation of the volume of labor (OH) requires 0.039 OH masons and 0.039 OH workers and the results of calculating the standard time to complete 1 m2 of floor slab work is 10.37 minutes/m2.

Keywords

Collaboration network of the authors

3 authors · 3 co-authorship links

Hover or tap a name to highlight its co-authors. Double-click to open the author's page.

  • Universitas Hindu Indonesia
  • Different organisations
  • Same organisation
  • Affiliation unknown
  • Thicker line = more joint articles · bigger circle = more articles
Show as table
Co-authorOrganisationJoint articles

Affiliations come from OpenAlex; journal OAI-PMH metadata carries none. Authors without an OpenAlex ID are matched by name, which can merge or split people.

Metadata source: OAI-PMH (metadata jurnal) https://ojs2.pnb.ac.id/index.php/LOGIC/oai, first harvested 19 Nov 2026, last seen 19 Nov 2026.
Original metadata (oai_dc)
<oai_dc:dc xmlns="http://www.openarchives.org/OAI/2.0/" xmlns:dc="http://purl.org/dc/elements/1.1/" xmlns:oai_dc="http://www.openarchives.org/OAI/2.0/oai_dc/" xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:schemaLocation="http://www.openarchives.org/OAI/2.0/oai_dc/  http://www.openarchives.org/OAI/2.0/oai_dc.xsd">
	<dc:title xml:lang="en-US">Analysis of Labor Productivity in Floor Plate Work Using The Work Sampling Method: Case Study: Udayana University Faculty of Medicine Building and The Calna Villa</dc:title>
	<dc:creator>Indriani, Made Novia</dc:creator>
	<dc:creator>Widnyana, I Nyoman Suta</dc:creator>
	<dc:creator>Mahendra, I Putu Agus Ari</dc:creator>
	<dc:subject xml:lang="en-US">Labor</dc:subject>
	<dc:subject xml:lang="en-US">Productivity</dc:subject>
	<dc:subject xml:lang="en-US">Work sampling</dc:subject>
	<dc:description xml:lang="en-US">Labor productivity is very important in carrying out a job, in the field of construction output can be seen from the quantity of work that has been done, while input is the amount of resources used such as labor. This study aims to determine the amount of labor required per 1 m2 (OH) and the standard time for labor productivity in completing 1 m2 of floor slab work. The method of collecting primary data is the source of research data obtained directly, such as the number of workers and observation of sampling data, while secondary data is obtained from projects such as working drawings. The data is then processed using Microsoft Excel. This research is a type of quantitative research with work sampling method. From the results of research on floor slab work in the Udayana University Faculty of Medicine Building Construction project, it shows that the calculation of the volume of labor per day (OH) requires 0.011 OH masons and 0.011 OH workers and the results of calculating the standard time to complete 1 m2 of floor slab work is 3.15 minutes/m2 . The Calna Villa project shows that the calculation of the volume of labor (OH) requires 0.039 OH masons and 0.039 OH workers and the results of calculating the standard time to complete 1 m2 of floor slab work is 10.37 minutes/m2.</dc:description>
	<dc:publisher xml:lang="en-US">Unit Publikasi Ilmiah, P3M, Politeknik Negeri Bali</dc:publisher>
	<dc:date>2023-03-30</dc:date>
	<dc:type>info:eu-repo/semantics/article</dc:type>
	<dc:type>info:eu-repo/semantics/publishedVersion</dc:type>
	<dc:format>application/pdf</dc:format>
	<dc:identifier>https://ojs2.pnb.ac.id/index.php/LOGIC/article/view/999</dc:identifier>
	<dc:identifier>10.31940/logic.v23i1.42-48</dc:identifier>
	<dc:source xml:lang="en-US"> Logic : Jurnal Rancang Bangun dan Teknologi; Vol. 23 No. 1 (2023): March; 42-48</dc:source>
	<dc:source>2580-5649</dc:source>
	<dc:source>1412-114X</dc:source>
	<dc:source>10.31940/logic.v23i1</dc:source>
	<dc:language>eng</dc:language>
	<dc:relation>https://ojs2.pnb.ac.id/index.php/LOGIC/article/view/999/511</dc:relation>
	<dc:rights xml:lang="en-US">Copyright (c) 2023  Logic : Jurnal Rancang Bangun dan Teknologi</dc:rights>
	<dc:rights xml:lang="en-US">https://scholar.google.co.id/citations?user=smBuD3gAAAAJ&amp;hl=id</dc:rights>
</oai_dc:dc>