EFISIENSI BIAYA DAN WAKTU PELAKSANAAN PEKERJAAN LAPIS PERKERASAN AGREGAT KELAS B PADA RUAS JALAN SORUMBA KOTA KENDARI

Media Konstruksi : Jurnal Ilmiah Teknik Sipil · Vol. 5 No. 1 (2020)

DOI
10.33772/jmk.v5i1.24099
ISSN
2503-2712
Published
2020-04-01
Publisher
PRODI D3 TEKNIK SIPIL
Language
eng

Abstract

Abstract In planning a project that is done with heavy equipment, one thing that is important is how to calculate the cost and time efficiency of the machine. The first step in calculating the cost and time of a machine is to carry out a theoretical calculation. Then with this final project to determine the cost efficiency and time of heavy equipment used during the Wua-Wua Area Road Improvement project process (DAK 2019) - Jalan Sorumba, Kendari City.The data in this study are secondary data obtained from the executing contractor which includes the budget plan for the implementation process of class B aggregate pavement work.The cost of implementing the rental of tools and materials from the calculation is Rp. 1.581.019.052,29, while the value of the contract fee is Rp. 1.597.496.916,63. The implementation time of class B aggregate pavement work (LPB) from the calculation, which takes 35 (thirty five) calendar days and is still in accordance with the estimated implementation of the work in the contract. Abstrak Dalam merencanakan proyek yang dikerjakan dengan alat berat, satu hal yang penting adalah bagaimana menghitung efisiensi biaya dan waktu alat berat. Langkah pertama dalam menghitung biaya dan waktu alat berat adalah melakukan perhitungan secara teoritis. Kemudian dengan adanya tugas akhir ini untuk mengetahui efisiensi biaya dan waktu alat berat yang digunakan selama proses proyek Peningkatan Jalan Kawasan Wua-Wua (DAK 2019) – Jalan Sorumba, Kota Kendari.Data dalam penelitian ini adalah data sekunder yang diperoleh dari kontraktor pelaksana yang meliputi laporan rencana anggaran biaya proses pelaksanaan pekerjaan perkerasan pondasi agregat kelas B.Adapun biaya pelaksanaan sewa alat dan bahan dari perhitungan yakni sebesar Rp. 1.581.019.052,29, sedangkan nilai dari biaya kontrak yakni sebesar Rp. 1.597.496.916,63. Waktu pelaksanaan pekerjaan perkerasan agregat kelas B (LPB) dari perhitungan yakni membutuhkan waktu 35 (tiga puluh lima) hari kalender dan masih sesuai dengan estimasi pelaksanaan pekerjaan dalam kontrak.

Collaboration network of the authors

40 authors · 117 co-authorship links · 3 across different organisations · showing the 40 most connected

Hover or tap a name to highlight its co-authors. Double-click to open the author's page.

  • Universitas Halu Oleo
  • Universitas Sembilanbelas November Kolaka
  • Affiliation unknown
  • Different organisations
  • Same organisation
  • Affiliation unknown
  • Thicker line = more joint articles · bigger circle = more articles
Show as table
Co-authorOrganisationJoint articles
sulha sulhaAffiliation unknown8
Fitriah Mas'udAffiliation unknown5
Fitriah FitriahAffiliation unknown3
Weko Indira RomantiauliaAffiliation unknown2
Try Sugiyarto SoeparyantoUniversitas Halu Oleo2
Wayan MustikaAffiliation unknown2
ARMAN FASLIHAffiliation unknown2
La Ode Muhamad Nurrakhmad ArsyadUniversitas Halu Oleo2
Anafi MinmahddunUniversitas Halu Oleo2
Evy YusufAffiliation unknown2
Fathur Rahman RustanUniversitas Sembilanbelas November Kolaka2
Muhammad Syarif PrasetiaAffiliation unknown2
La WelendoAffiliation unknown2
I Made Krisna Adi DahrmaAffiliation unknown1
Wa Ode Nartin HamunduAffiliation unknown1
Abdi Juryan LadiantoUniversitas Halu Oleo1
La Ode Amrul HasanAffiliation unknown1
Try SugiyartoAffiliation unknown1
Adrianto YusufAffiliation unknown1
Muhammad Handy Dwi AdityawanAffiliation unknown1
Diki DarmawanAffiliation unknown1
Asraf AsrafAffiliation unknown1
Veny AnjarwatiAffiliation unknown1
Imam MulyonoAffiliation unknown1
Arung PatandiananAffiliation unknown1
Rika Fitriani MallaAffiliation unknown1
Dedi Indra PurnomoAffiliation unknown1
Sitti Kosma AsmatunAffiliation unknown1
Aksar AksarAffiliation unknown1
Muh Thahir AzikinAffiliation unknown1
Edi KusnadiAffiliation unknown1
Muriadin MuriadinUniversitas Halu Oleo1
Iksan Ade SaputraAffiliation unknown1
Mega Dwi AnitaAffiliation unknown1
La Ode YasirUniversitas Halu Oleo1

Affiliations come from OpenAlex; journal OAI-PMH metadata carries none. Authors without an OpenAlex ID are matched by name, which can merge or split people.

Metadata source: OAI-PMH (metadata jurnal) https://ojs.uho.ac.id/index.php/MedKons/oai, first harvested 31 Oct 2026, last seen 8 Nov 2026.
Original metadata (oai_dc)
<oai_dc:dc xmlns="http://www.openarchives.org/OAI/2.0/" xmlns:dc="http://purl.org/dc/elements/1.1/" xmlns:oai_dc="http://www.openarchives.org/OAI/2.0/oai_dc/" xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:schemaLocation="http://www.openarchives.org/OAI/2.0/oai_dc/  http://www.openarchives.org/OAI/2.0/oai_dc.xsd">
	<dc:title xml:lang="en-US">EFISIENSI BIAYA DAN WAKTU PELAKSANAAN  PEKERJAAN LAPIS PERKERASAN AGREGAT KELAS B PADA RUAS JALAN SORUMBA KOTA KENDARI</dc:title>
	<dc:creator>Haji, La Ode</dc:creator>
	<dc:creator>Nashrun, Mappa</dc:creator>
	<dc:creator>Sarita, Umran</dc:creator>
	<dc:creator>Masikki, Sultan Machmud Hasan</dc:creator>
	<dc:creator>Ikhsan, Ainussalbi Al</dc:creator>
	<dc:description xml:lang="en-US"> Abstract In planning a project that is done with heavy equipment, one thing that is important is how to calculate the cost and time efficiency of the machine. The first step in calculating the cost and time of a machine is to carry out a theoretical calculation. Then with this final project to determine the cost efficiency and time of heavy equipment used during the Wua-Wua Area Road Improvement project process (DAK 2019) - Jalan Sorumba, Kendari City.The data in this study are secondary data obtained from the executing contractor which includes the budget plan for the implementation process of class B aggregate pavement work.The cost of implementing the rental of tools and materials from the calculation is Rp. 1.581.019.052,29, while the value of the contract fee is Rp. 1.597.496.916,63. The implementation time of class B aggregate pavement work (LPB) from the calculation, which takes 35 (thirty five) calendar days and is still in accordance with the estimated implementation of the work in the contract.  Abstrak Dalam merencanakan proyek yang dikerjakan dengan alat berat, satu hal yang penting adalah bagaimana menghitung efisiensi biaya dan waktu alat berat. Langkah pertama dalam menghitung biaya dan waktu alat berat adalah melakukan perhitungan secara teoritis. Kemudian dengan adanya tugas akhir ini untuk mengetahui efisiensi biaya dan waktu alat berat yang digunakan selama proses proyek Peningkatan Jalan Kawasan Wua-Wua (DAK 2019) – Jalan Sorumba, Kota Kendari.Data dalam penelitian ini adalah data sekunder yang diperoleh dari kontraktor pelaksana yang meliputi laporan rencana anggaran biaya proses pelaksanaan pekerjaan perkerasan pondasi agregat kelas B.Adapun biaya pelaksanaan sewa alat dan bahan dari perhitungan yakni sebesar Rp. 1.581.019.052,29, sedangkan nilai dari biaya kontrak yakni sebesar Rp. 1.597.496.916,63. Waktu pelaksanaan pekerjaan perkerasan agregat kelas B (LPB) dari perhitungan yakni membutuhkan waktu 35 (tiga puluh lima) hari kalender dan masih sesuai dengan estimasi pelaksanaan pekerjaan dalam kontrak. </dc:description>
	<dc:publisher xml:lang="en-US">PRODI D3 TEKNIK SIPIL</dc:publisher>
	<dc:contributor xml:lang="en-US"></dc:contributor>
	<dc:date>2020-04-01</dc:date>
	<dc:type>info:eu-repo/semantics/article</dc:type>
	<dc:type>info:eu-repo/semantics/publishedVersion</dc:type>
	<dc:type xml:lang="en-US">Peer-reviewed Article</dc:type>
	<dc:format>application/pdf</dc:format>
	<dc:identifier>https://ojs.uho.ac.id/index.php/MedKons/article/view/24099</dc:identifier>
	<dc:identifier>10.33772/jmk.v5i1.24099</dc:identifier>
	<dc:source xml:lang="en-US">Media Konstruksi : Jurnal Ilmiah Teknik Sipil; Vol 5, No 1 (2020): MedKons</dc:source>
	<dc:source>2503-2712</dc:source>
	<dc:source>10.33772/jmk.v5i1</dc:source>
	<dc:language>eng</dc:language>
	<dc:relation>https://ojs.uho.ac.id/index.php/MedKons/article/view/24099/14452</dc:relation>
	<dc:rights xml:lang="en-US">Copyright (c) 2022 MEDIA KONSTRUKSI</dc:rights>
</oai_dc:dc>