Open access Journal
Comparative Analysis of CPM and PERT Methods for Scheduling the Repair Process of KMP. Kormomolin
Zona Laut Jurnal Inovasi Sains Dan Teknologi Kelautan · Vol. ume (2026) · pp. 190–197
- ISSN
- 2721-5717, 2747-2124
- Published
- 2026-07-21
- Publisher
- Departemen Teknik Kelautan Universitas Hasanuddin
- Language
- en
Abstract
English
In the maritime industry, scheduling ship repair projects is an important aspect that determines operational efficiency and navigational safety. An appropriate scheduling method can help optimize project duration and manage uncertainties that may arise during project implementation. Two commonly used methods are the Critical Path Method (CPM) and the Program Evaluation and Review Technique (PERT), which apply deterministic and probabilistic approaches, respectively. This study was conducted on the repair project of KMP. Kormomolin, which had an initial planned duration of 52 days and involved 58 technical activities. The CPM method was used to identify the critical path based on fixed activity durations obtained from the repair list, while the PERT method was applied to estimate project duration using three-time estimates: optimistic, most likely, and pessimistic. The analysis was carried out using Microsoft Project and manual calculations to determine Early Finish (EF), Late Finish (LF), Total Float, and the probability of project completion. The CPM analysis showed that the project could be completed within 48 days, with a critical path consisting of activities with no slack. Meanwhile, the PERT method produced an estimated project duration of 50 days, with a completion probability of 95.82%. The CPM method provides stricter time control, whereas PERT offers greater flexibility in dealing with uncertainty. CPM is more suitable for projects with a stable work structure and clear activity sequences, while PERT is more appropriate for projects involving many variables and risks. The integration of both methods is recommended to produce more adaptive and comprehensive project planning in the ship repair industry.
Indonesian
In the maritime industry, scheduling ship repair projects is an important aspect that determines operational efficiency and navigational safety. An appropriate scheduling method can help optimize project duration and manage uncertainties that may arise during project implementation. Two commonly used methods are the Critical Path Method (CPM) and the Program Evaluation and Review Technique (PERT), which apply deterministic and probabilistic approaches, respectively. This study was conducted on the repair project of KMP. Kormomolin, which had an initial planned duration of 52 days and involved 58 technical activities. The CPM method was used to identify the critical path based on fixed activity durations obtained from the repair list, while the PERT method was applied to estimate project duration using three-time estimates: optimistic, most likely, and pessimistic. The analysis was carried out using Microsoft Project and manual calculations to determine Early Finish (EF), Late Finish (LF), Total Float, and the probability of project completion. The CPM analysis showed that the project could be completed within 48 days, with a critical path consisting of activities with no slack. Meanwhile, the PERT method produced an estimated project duration of 50 days, with a completion probability of 95.82%. The CPM method provides stricter time control, whereas PERT offers greater flexibility in dealing with uncertainty. CPM is more suitable for projects with a stable work structure and clear activity sequences, while PERT is more appropriate for projects involving many variables and risks. The integration of both methods is recommended to produce more adaptive and comprehensive project planning in the ship repair industry.
Keywords
Collaboration network of the authors
24 authors · 69 co-authorship links
Hover or tap a name to highlight its co-authors. Double-click to open the author's page.
- Hasanuddin University
- Affiliation unknown
- Different organisations
- Same organisation
- Affiliation unknown
- Thicker line = more joint articles · bigger circle = more articles
Show as table
| Co-author | Organisation | Joint articles |
|---|---|---|
| Juswan Sade | Affiliation unknown | 3 |
| Habibi Palippui | Hasanuddin University | 2 |
| Muh. Syaifullah | Hasanuddin University | 1 |
| Paroka Paroka | Hasanuddin University | 1 |
| Firman Husain | Affiliation unknown | 1 |
| Firman Husain | Hasanuddin University | 1 |
| Cynthia Sampe Lolo | Hasanuddin University | 1 |
| Habibi Palippui | Affiliation unknown | 1 |
| Windi Widianingrum | Affiliation unknown | 1 |
| Windi Widianingrum | Hasanuddin University | 1 |
| Daeng Paroka | Affiliation unknown | 1 |
| Makbul Mubarak | Affiliation unknown | 1 |
| Daeng Paroka | Hasanuddin University | 1 |
| Makbul Mubarak | Hasanuddin University | 1 |
| Fuad Mahfud Assidiq | Affiliation unknown | 1 |
| Ahmad Faiq Dhiyaulhaq Karya | Affiliation unknown | 1 |
| Fuad Mahfud Assidiq | Hasanuddin University | 1 |
| Ahmad Faiq Dhiyaulhaq Karya | Hasanuddin University | 1 |
| Salsa Fitrah | Affiliation unknown | 1 |
| Salsa Fitrah | Hasanuddin University | 1 |
| Ainun Jariah | Hasanuddin University | 1 |
Affiliations come from OpenAlex; journal OAI-PMH metadata carries none. Authors without an OpenAlex ID are matched by name, which can merge or split people.