The Design of Project Risk Management to Mitigate Project Delay in the Onshore Construction Industry (A Case Study of a Shore Protection Project)

Management Analysis Journal · Vol. 14 No. 4 (2025) · pp. 509–523

DOI
10.15294/maj.v14i4.26631
ISSN
2502-1451, 2252-6552
Published
2025-12-30
Publisher
Universitas Negeri Semarang
Language
eng
License
creativecommons.org/licenses/by/4.0

Abstract

This study research focuses on a three-month delay in a shore protection project undertaken by PT Sabar Sejahtera, which resulted in financial, time, and opportunity losses. Electricity is essential for human life and can be generated in various ways; therefore, the construction of power plants must be well planned. Effective project planning helps manage resources and schedules, while poor planning can lead to project delays. This study aims to identify the root causes of the delay, propose solutions and mitigation plans, and develop a lessons learned register. A mixed-method approach was employed, including focus group discussions and Risk Priority Number (RPN) analysis. The Current Reality Tree identified two main root causes: systematic errors during the tendering and planning stages and the absence of a mitigation plan. The Future Reality Tree demonstrated that involving multiple departments and correcting systematic errors could prevent similar issues in future projects. To manage project risks, this study applied the PMBOK 6th Edition project risk management framework, covering risk identification through monitoring. The lessons learned register highlights the importance of early planning, appropriate working methods, and a comprehensive risk mitigation plan. The company is encouraged to adopt this approach in future projects.

Keywords

Collaboration network of the authors

8 authors · 12 co-authorship links

Hover or tap a name to highlight its co-authors. Double-click to open the author's page.

  • Bandung Institute of Technology
  • Different organisations
  • Same organisation
  • Affiliation unknown
  • Thicker line = more joint articles · bigger circle = more articles
Show as table
Co-authorOrganisationJoint articles
Niken PrilanditaBandung Institute of Technology2
Tamara Latifah JasmineBandung Institute of Technology2
Heru Purboyo Hidayat PutroBandung Institute of Technology2
Miming MiharjaBandung Institute of Technology1
Nurlaela Kumala DewiBandung Institute of Technology1

Affiliations come from OpenAlex; journal OAI-PMH metadata carries none. Authors without an OpenAlex ID are matched by name, which can merge or split people.

Metadata source: OAI-PMH (metadata jurnal) https://journal.unnes.ac.id/journals/maj/oai, first harvested 6 Nov 2026, last seen 8 Nov 2026.
Original metadata (oai_dc)
<oai_dc:dc xmlns="http://www.openarchives.org/OAI/2.0/" xmlns:dc="http://purl.org/dc/elements/1.1/" xmlns:oai_dc="http://www.openarchives.org/OAI/2.0/oai_dc/" xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:schemaLocation="http://www.openarchives.org/OAI/2.0/oai_dc/  http://www.openarchives.org/OAI/2.0/oai_dc.xsd">
	<dc:title xml:lang="en">The Design of Project Risk Management to Mitigate Project Delay in the Onshore Construction Industry (A Case Study of a Shore Protection Project)</dc:title>
	<dc:creator xml:lang="en">Muhammad, Firdaus Yusri</dc:creator>
	<dc:creator xml:lang="en">Yudoko, Gatot</dc:creator>
	<dc:creator xml:lang="en">Hanafi, Muhammad</dc:creator>
	<dc:subject xml:lang="en">Project Delay</dc:subject>
	<dc:subject xml:lang="en">Current Reality Tree</dc:subject>
	<dc:subject xml:lang="en">Future Reality Tree</dc:subject>
	<dc:subject xml:lang="en">Project Risk Management</dc:subject>
	<dc:description xml:lang="en">This study research focuses on a three-month delay in a shore protection project undertaken by PT Sabar Sejahtera, which resulted in financial, time, and opportunity losses. Electricity is essential for human life and can be generated in various ways; therefore, the construction of power plants must be well planned. Effective project planning helps manage resources and schedules, while poor planning can lead to project delays. This study aims to identify the root causes of the delay, propose solutions and mitigation plans, and develop a lessons learned register. A mixed-method approach was employed, including focus group discussions and Risk Priority Number (RPN) analysis. The Current Reality Tree identified two main root causes: systematic errors during the tendering and planning stages and the absence of a mitigation plan. The Future Reality Tree demonstrated that involving multiple departments and correcting systematic errors could prevent similar issues in future projects. To manage project risks, this study applied the PMBOK 6th Edition project risk management framework, covering risk identification through monitoring. The lessons learned register highlights the importance of early planning, appropriate working methods, and a comprehensive risk mitigation plan. The company is encouraged to adopt this approach in future projects.</dc:description>
	<dc:publisher xml:lang="en">Universitas Negeri Semarang</dc:publisher>
	<dc:date>2025-12-30</dc:date>
	<dc:type>info:eu-repo/semantics/article</dc:type>
	<dc:type>info:eu-repo/semantics/publishedVersion</dc:type>
	<dc:type xml:lang="en">Peer-reviewed Article</dc:type>
	<dc:format>application/pdf</dc:format>
	<dc:identifier>https://journal.unnes.ac.id/journals/maj/article/view/26631</dc:identifier>
	<dc:identifier>10.15294/maj.v14i4.26631</dc:identifier>
	<dc:source xml:lang="en">Management Analysis Journal; Vol. 14 No. 4 (2025): Special Edition; 509-523</dc:source>
	<dc:source>2502-1451</dc:source>
	<dc:source>2252-6552</dc:source>
	<dc:source>10.15294/maj.v13i4</dc:source>
	<dc:language>eng</dc:language>
	<dc:relation>https://journal.unnes.ac.id/journals/maj/article/view/26631/10565</dc:relation>
	<dc:rights xml:lang="en">Copyright (c) 2025 Management Analysis Journal</dc:rights>
	<dc:rights xml:lang="en">https://creativecommons.org/licenses/by/4.0</dc:rights>
</oai_dc:dc>